BHOPAL DIVISION
WELCOMES
2
State | Route KMs | Electrified RKMs |
MP | 2191 | 2191 |
Rajasthan | 821 | 821 |
UP | 54 | 54 |
Total | 3066 | 3066 |
Division | Route KMs | Electrified RKMs |
Kota | 959 | 959 |
Jabalpur | 1085 | 1085 |
Bhopal | 1022 | 1022 |
Total | 3066 | 3066 |
JURISDICTION OF WEST CENTRAL RAILWAY
3
JURISDICTION OF BHOPAL DIVISION
BINA- BPL = 138 KM
BPL-ET = 92 KM
ET-KNW = 183 KM
BINA- GUNA = 118 KM
GUNA- MKC = 214 KM
GUNA - GWL = 228 KM
TOTAL 1022 RKM
4
JURISDICTION OF BHOPAL DIVISION
RKM | 1022 |
TKM | 2166 |
ELECTRIFIED RKM | 1022 |
ELECTRIFIED TKM | 2166 |
ORIGINATING TRAINS | 46 |
NOS. OF STATIONS | 87 |
DISTRICTS IN DIVISION | 14 |
CONSTITUENCY IN DIVISION | 10 |
INTERCHANGE WITH OTHER RAILWAYS & WITHIN WCR
Sr | WITH OTHER RAILWAYS | Interchange (Ave/day) | | WITHIN WCR | Interchange (Ave/day) |
1 | KNW (BSL Division/ CR) | 25.99 | 1 | ET (JBP Division/WCR) | 16.25 |
2 | JUH (NGP Division/CR) | 35.10 | 2 | BINA-NKJ(JBP Division/WCR) | 12.20 |
3 | MKC (RTM Division/WR) | 2.61 | 3 | MDVK-MAKR(JBP Division/WCR) | 34.69 |
4 | SHRN(RTM Division/WR) | 23.41 | 4 | RTA(KOTA Division/WCR) | 34.67 |
5 | MAT-ANI (RTM Division/WR) | 6.33 | Total | 97.81 | |
6 | MDVK-AGD(JHS Division/NCR) | 2.04 | | | |
7 | GWL (JHS Division/NCR) | 4.14 | | | |
8 | BINA-JHS(JHS Division/NCR) | 30.28 | | | |
Total | 129.9 | | | | |
NI Activity
LIST NI ACTIVITIES – BY OPTG DEPT
S.No. | Location | Executing Agency | TDC as per Exec Agency | DCN finalized by Div (date) | DCN shared with dates for NI (date) | Remark |
01 | SHRN | CONSTRUCTION/BPL | DEC 23 | 04.12.23 | 02.12.23 | NI START FROM 03.01.23. |
02 | NSZ-D | CONSTRUCTION/BPL | OCT 23 | 19.12.23 | 18.12.23 | PRE-NI planned from 09.1.24 & NI from 14.01.24. |
03 | PNHR | DRM/BPL | MARCH 24 | UNDER DISCUSSION | | Loading restriction to be applied. |
04 | HD | CSTE/P & DRM/BPL | DEC23 | DCN NOT SUBMITTED | | EI UNDER PH-16 IS DONE BY PROJECT & SHIFTING OF GOODS SHED BY DRM/BPL. |
05 | DKI | CSTE/P | DEC23 | DCN NOT SUBMITTED | | |
06 | DRA | CSTE/P | JAN 24 | DCN NOT SUBMITTED | | |
07 | BINA GOODS YARD | CSTE/P | NOV 23 | DCN NOT SUBMITTED | | |
08 | MAKR-MDVK DOUBLING | RVNL | JAN 24 | DCN SUBMITTED BY RVNL ON 06.11.23 | | DCN TO BE FINALIZED WITH MAKR DCN |
09 | PGL | CSTE/P | FEB 24 | DCN NOT SUBMITTED | | |
Rolling block
ROLLING BLOCK PROGRAM OF BHOPAL DIVISION (w.e.f. 12.06.23)
Engineering | TRD | S&T | ||||||
Hours demanded | Hours Granted | %� | Hours demanded | Hours Granted | %� | Hours demanded | Hours Granted | %� |
26481:20:00 | 18140:10 | 68.50% | 9062:55:00 | 6301:50:00 | 69.53% | 11130:12:00 | 9969:45:00 | 89.57% |
Grand Total | ||
Total�Hours Demanded | Total�Hours Granted | %� |
85893:26 | 63079:43 | 73.43% |
Initial Railway Board Format
ROLLING BLOCK PROGRAM OF BHOPAL DIVISION (w.e.f. 09.10.23)
Dept | Hours demanded for >30 GMT | Hours Granted for >30 GMT | % | Hours demanded for <30 GMT | Hours Granted for <30 GMT | % | Track length with >30 GMT (in KM) | Track length with <30 GMT (in KM) |
Engg | 8599:30:00 | 5765:35:00 | 67% | 1732:00:00 | 1372:50:00 | 79% | 39819.6 | 13165.8 |
TRD | 3214:00:00 | 2137:15:00 | 66% | 433:00:00 | 231:15:00 | 53% | -- | -- |
S&T | 3761:04:00 | 3256:38:00 | 87% | 1584:07:00 | 1537:35:00 | 97% | -- | -- |
Total | 15574:34:00 | 11159:28:00 | 72% | 3749:07:00 | 3141:40:00 | 84% | -- | -- |
% of Total | 80.60% | 78.03% | -- | 19.40% | 21.97% | -- | 75.15% | 24.85% |
Total Hours Demanded | 19323:41 | Total Hours Granted | 14301:08 | % | 74.01% | |||
Revised Railway Board Format
OPERATING
QUANTUM OF COACHING & FREIGHT OVER BHOPAL DIVISON
SN | Section | % of Utilization of Charted Capacity | 00-08 | 08-16 | 16-24 | Total CHG | Freight in 24 hrs | Total in 24 hrs |
With Maint. Block | ||||||||
1 | KNW-ET Dn | 95.1 | 13 | 14 | 18 | 45 | 18 | 63 |
2 | ET-KNW Up | 119.6 | 17 | 18 | 15 | 50 | 22 | 72 |
3 | ET-BPL Dn | 115.2 | 26 | 12 | 28 | 66 | 23 | 89 |
4 | BPL-ET Up | 121.5 | 25 | 15 | 26 | 66 | 25 | 91 |
5 | BPL-BINA Dn | 117.4 | 26 | 20 | 30 | 76 | 24 | 100 |
6 | BINA-BPL Up | 107.1 | 25 | 20 | 31 | 76 | 25 | 101 |
7 | BINA-RTA Dn | 122.5 | 4 | 5 | 4 | 13 | 22 | 35 |
8 | RTA-BINA Up | 133.9 | 3 | 6 | 4 | 13 | 24 | 37 |
9 | RTA-MKC Dn | 99.9 | 3 | 4 | 2 | 9 | 2 | 11 |
10 | MKC-RTA Up | 90.1 | 1 | 3 | 5 | 9 | 2 | 11 |
11 | Guna-GWL Dn | 106.3 | 3 | 1 | 4 | 8 | 2 | 10 |
12 | GWL-Guna Up | 100.2 | 2 | 1 | 5 | 8 | 3 | 11 |
1 | Freight figure are actual average of 2023-24 (up to Dec-23). | |||||||
2 | Current average of freight trains run per day is 192. | |||||||
3 | Coaching figures are charted path after zero-Base time table. | |||||||
4 | Current average reporting of train is 237 (M/E+PSPC+TOD) + 4 (PPEX) = 241 trains per day. | |||||||
5 | Average Punctuality performance is 71.03% (Figures FY 2023-24 till Dec-23) | |||||||
6 | Percentage of manual reporting of coaching train is 2%. | |||||||
GOODS SHED & SIDINGS
SECTION | GOODS SHED | SIDING |
KNW-ET SECTION | MTA, HD, TBN, BPF = 04 | PSSS (BIR) = 01 |
ET-BPL SECTION | ET, BNI, MDDP = 03 | IOCE (IOC-ET), FISG (FCI-ET), KPFP (PFT-PRKP), PVSB (BNI), HEG & CCMP (MDDP) = 06 |
BPL-BINA SECTION | NSZ (INCLUDING CWC), SUW, SMT, SORI, BAQ, BINA = 06 | - |
BINA-GUNA SECTION | ASKN, GUNA = 02 | MBPC & BRSM (MDVK), JBTS (SRKI), PMHP (GCT-PIGT) = 04 |
RTA-MKC SECTION | BRRG, PFR, SFY = 03 | NFL & GAIL (VJP) = 02 |
GUNA-GWL SECTION | PNHR, SVPI = 02 | - |
Total | 20 | 13 |
GOODS LOADING
S.No. | COMMODITY | ACTUAL 2022-23 | TARGET 2023-24 | CUMMULATIVE UP TO DEC-23 | %AGE VARIATION | |||
LY | TARGET | ACTUAL | LY | TARGET | ||||
1 | FERTILISER | 2.307 | 2.47 | 1.734 | 1.800 | 1.582 | -8.78% | -12.12% |
2 | FOOD GRAINS | 4.436 | 4.93 | 3.128 | 3.580 | 2.596 | -16.99% | -27.48% |
3 | POL/LPG | 0.992 | 1.32 | 0.770 | 0.970 | 0.592 | -23.21% | -39.01% |
4 | CONTAINER | 0.434 | 0.49 | 0.322 | 0.360 | 0.330 | 2.32% | -8.41% |
5 | IRON ORE | 0.043 | 0.12 | 0.008 | 0.090 | 0.071 | 769.99% | -21.51% |
6 | P/COKE | 0.138 | 0.24 | 0.097 | 0.180 | 0.113 | 16.40% | -37.19% |
7 | OTHERS | 1.219 | 1.43 | 0.690 | 1.040 | 1.300 | 88.28% | 24.96% |
TOTAL | 9.569 | 11 | 6.750 | 8.020 | 6.583 | -2.48% | -17.92% | |
ACTION PLAN FOR IMPROVEMENT IN LOADING
ACTION PLAN FOR IMPROVEMENT IN LOADING
FREIGHT TRAIN SPEED
| Excluding Stabling and Yarding Time | ||
Year | FY 2021-22 | FY 2022-23 | FY 2023-24 |
Speed | 54.94 | 45.33 | 30.18 |
| Including Stabling and Yarding Time | ||
Year | FY 2021-22 | FY 2022-23 | FY 2023-24 |
Speed | 19.26 | 21.81 | 16.87 |
REASONS FOR REDUCTION IN FREIGHT TRAIN SPEED
Month | Mobility (Speed with stabling) | Ave interchange (per month) | DWB | Loco Change | Stabling of BCN/BCNHL rakes (per month) | ACP | CRO | Crew shortfall �(waiting for Crew) |
Apr-23 | 22.5 | 6920 | 3613 | 9.5 | 50 | 13.0 | 4.0 | 0.2 |
May-23 | 19.5 | 7012 | 3840 | 11.1 | 30 | 14.7 | 4.8 | 1.7 |
Jun-23 | 18.7 | 6664 | 3975 | 10.3 | 34 | 11.4 | 6.3 | 1.2 |
Jul-23 | 16.0 | 6978 | 4190 | 11.9 | 35 | 12.5 | 5.1 | 1.8 |
Aug-23 | 15.9 | 6804 | 4586 | 13.2 | 125 | 12.6 | 5.0 | 2.9 |
Sep-23 | 15.1 | 6786 | 4794 | 15.0 | 102 | 12.3 | 4.7 | 3.9 |
Oct -23 | 15.87 | 7159 | 4685 | 13.64 | 133 | 11.61 | 3.96 | 3.8 |
Nov-23 | 14.04 | 7039 | 5172 | 13.50 | 166 | 16.70 | 3.80 | 6.1 |
Dec-23 | 17.35 | 7260 | 4296 | 14.29 | 45 | 17.35 | 3.87 | 2.1 |
REASONS FOR REDUCTION IN FREIGHT TRAIN SPEED
ACTION PLAN TO IMPROVE FREIGHT TRAIN SPEED
WAGON TURNAROUND
Year | FY 2021-22 | FY 2022-23 | FY 2023-24 |
WTR | 0.87 | 0.92 | 0.99 (Till Dec-23) |
REASONS FOR HIGHER WTR
ACTION PLAN TO IMPROVE WTR
Manual S/On –S/Off : PERFORMANCE & ACTION PLAN
Year | Total S/ON (Train Manager) | Manual S/ON | Manual S/ON % | Total S/Off | Manual S/Off | Manual S/Off % |
2022-23 | Data not available in CMS | |||||
2023-24 | 90782 | 2234 | 2.46% | 88717 | 3637 | 4.09% |
01.12.23 to 31.12.23 | 14573 | 74 | 0.51% | 14277 | 142 | 0.99% |
Action Plan
PUNCTUALITY
Punctuality Performance of Bhopal Division 01.04.2023 to 31.12.2023 | ||||||||
|
|
|
|
|
|
|
|
|
Year | TOTAL TRAIN DEPARTED | BT | RIGHT TIME | MAKE UP | NLT | LT | PUNCT | VARIATION |
| MAIL/EXPRESS | |||||||
2022-23 | 55027 | 15359 | 22291 | 7179 | 6251 | 3947 | 92.83 | 21.82 |
2023-24 | 55654 | 12421 | 13128 | 8889 | 5095 | 16121 | 71.03 | |
| PASSENGER | |||||||
2022-23 | 7135 | 1740 | 3065 | 487 | 801 | 1042 | 85.40 | 21.86 |
2023-24 | 8827 | 1537 | 1349 | 888 | 1835 | 3218 | 63.54 | |
| GRAND TOTAL | |||||||
2022-23 | 62162 | 17099 | 25356 | 7666 | 7052 | 4989 | 91.97 | 21.96 |
2023-24 | 64481 | 13958 | 14477 | 9777 | 6930 | 19339 | 70.01 | |
PUNCTUALITY
| PUNCTUALITY�M/EXP | DWB | ACP | CRO | Received late� | Nos of trains upto 10 minutes late� | Nos of M/E trains with Goods loco� | Nos of Train On Demand (TOD) |
Apr-23 | 81% | 3613 | 13.03 | 3.97 | 90.63 | 15.13 | - | 272 |
May-23 | 77% | 3840 | 14.74 | 4.77 | 105.32 | 17.48 | - | 451 |
Jun-23 | 71% | 3975 | 11.37 | 6.30 | 123.23 | 19.50 | - | 438 |
Jul-23 | 66% | 4190 | 12.55 | 5.13 | 123.97 | 22.71 | - | 366 |
Aug-23 | 66% | 4586 | 12.58 | 5.03 | 110.58 | 20.23 | - | 383 |
Sep-23 | 69% | 4794 | 12.30 | 4.73 | 89.03 | 19.10 | 9.07 | 253 |
Oct-23 | 73.25% | 4685 | 11.61 | 3.96 | 87.93 | 18.19 | 8.67 | 281 |
Nov-23 | 64.37% | 5172 | 16.70 | 3.80 | 114.80 | 22.43 | 9.13 | 574 |
Dec-23 | 70.05 | 4296 | 17.35 | 3.87 | 95.84 | 15.58 | 9.03 | 256 |
REASONS FOR DROP IN PUNCTUALITY
Asset Failure:-
Increase in Number of Coaching Trains
Out of Path
Trains are getting Out of Path from adjacent divisions. Precedence given to high priority Trains like Duranto, Rajdhani, Shatabdi etc over less priority trains.
Data Rectification:-
REASONS FOR DROP IN PUNCTUALITY
Bottleneck in Trains operations:-
Junction Constraints
Ghat Section
Highly Saturated Section
ET-BPL UP -121.5 %, ET-BPL DN -115.2%, ET-KNW UP-119.6%, BPL-BINA DN-117.4%, RTA-BINA UP-133.9%.
ACTION PLAN
B.MID TERM
1. Stabling of Goods trains occurred in the division due to poor availability of ALPs/LPs/TMs. At Present,
there are 313 Vacancy of TM. Need to fill the vacancy faster.
2. Bhopal yard remodelling phase-I :- to achieve directionality in BPL yard in connection with 3 line
between BPL-BINA.
3 BINA yard remodelling phase-II :- connection of 3rd line to BINA in connection with JHS-BINA 3rd line.
C. LONG TERM
BHOPAL and BINA Yards are major bottleneck in the division. For debottlenecking of these yards,
works are under process. Re-modelling are proposed as:-
1 . Bhopal yard remodelling phase II :- complete yard remodelling.
Work is being sanctioned by Railway Board.
2. Bhopal yard remodelling phase II :- complete yard remodelling.
ACTION PLAN
SN | TRAIN NO | TA |
1 | 20171/72 | 00” |
2 | 20173 | 01” |
3 | 12270 | 5” |
4 | 12286 | 5” |
5 | 19168 | 3” |
6 | 11126 | 5” |
7 | 18237/38 | 5” |
8 | 11058 | 2” |
9 | 19812 | 5” |
10 | 12198 | 1” |
11 | 21125 | 2” |
12 | 12002 | 1” |
13 | 19166 | 3” |
(Annexure – “B”)
SN | TRAIN NO | STOPPAGE AT BINA |
1 | 20414 | 2” |
2 | 20468 | 2” |
3 | 19305 | 5” |
4 | 19313 | 5” |
5 | 19321 | 5” |
6 | 14313 | 5” |
7 | 14319 | 5” |
8 | 20416 | 2” |
(ANNEXURE “C”)
(ANNEXURE “D”)
SN | TRAIN NO | From-TO | Exiting Terminal & TIME | Proposed Terminal & Time |
1 | 19323 | DADN-BPL | BPL 10.55 | NSZ 10.55 |
2 | 19340 | BPL-DHD | BPL 12.35 | NSZ 12.35 |
3 | 19339 | DHD-BPL | BPL 16.10 | NSZ 16.10 |
4 | 13924 | BPL-DADN | BPL 17.00 | NSZ 17.10 |
5 | 12198 | GWL-BPL | BPL 14.35 | NSZ 14.40 |
6 | 12197 | BPL-GWL | BPL 15.15 | NSZ 15.20 |
7 | 11606 | BINA-BPL | BPL 13.40 | NSZ 13.30 |
8 | 11605 | BPL-BINA | BPL 14.20 | NSZ 14.20 |
9 | 12153 | LTT-RKMP | RKMP 05.50 | BINA 08.10 |
10 | 12154 | RKMP-LTT | RKMP 18.00 | BINA 15.30 |
12919 | | 12920 | ||
Exisiting | Proposed | | Exisiting | Proposed |
16.58 – 17.00 | 16.58-17.00 | SHRN | 08.26 -08.28 | 08.18-08.20 |
17.20 – 17.40 | NA | BPL | 07.35-07.55 | NA |
TH 17.45 | 17.28-17.38 | NSZ | TH 07.26 | 07.30-07.40 |
19.40 -19.45 | 19.40-19-45 | BINA | 05.40-05.45 | 05.40-05.45 |
INFRASTRUCTURE WORKS
Important Traffic Facilities Works Underway | ||
S No | | Remarks |
1 | Itarsi North south Grade Separator/Fly-over. UP direction (BPL Construction) | TDC DEC 23 |
2 | MAKR- MDVK: (8.7 KM) Doubling of MAKR -KRD- MDVK Fly Over. | PH-I-work of single line done. PH-II work of track linking underway. TDC FEB 24 |
Works under WP/ Umbrella . | ||
1 | Automatic Signaling with CTC- BPL-BINA S&T Project | Sanctioned, Detailed estimate under sanction, plans are being approved. |
2 | Chord line at RTA (BPLConstruction) | Detail estimate was sanctioned, FLS awarded on 19.08.23 |
3 | Chord line at GUN (BPLConstruction) | Detail estimate was sanctioned, FLS awarded on 19.08.23 |
INFRASTRUCTURE WORKS
Progress of Traffic Facilities & Other, Works sanctioned under PWP/LAW | ||||
S No | | Cost | Year | Remarks |
1 | Itarsi North south Grade Separator/Fly-over.UP direction (BPL Construction) | 2470200 | 16-17 | TDC JAN 23 |
2 | MAKR- MDVK: (8.7 KM) Doubling of MAKR -KRD- MDVK Fly Over. | 543247 | 15-16 | PH-I-work of single line done. PH-II work of track linking underway. TDC FEB 24 |
3 | Up gradation of ASKN, MDDP & SVPI Sr DEN | 44900 | 20-21 | Sanctioned in 22-23 work in progress. TDC – Mar-24. |
Works under WP/ Umbrella . | ||||
4 | Automatic Signaling with CTC- BPL-BINA S&T Project | 2650000 | 22-23 | Sanctioned, Detailed estimate under sanction, plans are being approved. |
5 | Chord line at RTA (BPL Construction) | 494400 | 19-20 | Detail estimate was sanctioned, FLS awarded on 19.08.23 |
6 | Chord line at GUN (BPL Construction) | 517200 | 19-20 | Detail estimate was sanctioned, FLS awarded on 19.08.23 |
7 | HD-New goods shed | 75000 | 22-23 | PH-16 Work sanctioned (22-23), Joint work with PH-33 for replacement of old aged gears. TDC- yard March 24, Goods shed April-24 |
8 | Yard remodelling of SHRN in connection with RMA-BPL new line. | | | NI start from 03.01.24 to 05.01.24. |
9 | Yard remodelling of NSZ-D in connection with RMA-BPL new line. | | | Pre-NI planned from 09.01.24,NI planned from 14.01.24 to 16.01.24.CRS inspection of section on 17.01.24. |
INFRASTRUCTURE WORKS
S No | | Cost | Year | Remarks |
Works under WP/ Umbrella . | ||||
10 | New goods shed at PNHR | 74146 | 20-21 | Sanctioned in 22-23 Detailed estimate vetted. Work under progress. TDC- Mar-24. |
11 | Extension of SMT goods shed with other user amenities | 47710 | 20-21 | Sanctioned in 22-23, Detailed estimate vetted. Work under progress, line extended, Wharf work under progress. Nov-23 |
12 | Augmentation of BINA ,BPL & GUNA running rooms | 35563 | 20-21 | Sanctioned in 22-23, Detailed estimate vetted. |
13 | RKMP- Crossovers at ET end and increasing of CSR of PF 4/5 | 39900 | 22-23 | Detailed estimate under preparation. |
14 | Shifting of Goods Shed of ET to JUH | 87700 | 23-24 | Detailed estimate under preparation. |
15 | Additional goods shed line in SMT | 54189 | 23-24 | Detailed estimate under preparation. |
16 | Shifting of goods shed BAQ to BET | 80400 | 23-24 | Detailed estimate under preparation. |
17 | TBN: Up gradation of goods shed facility, making the siding common by providing over run on ET end. | 21500 | 23-24 | Detailed estimate under preparation. |
18 | Additional line in TLV-MTA (Multi tracking) | | 22-23 | Survey sanctioned. Alignment given to Cons Branch. |
19 | Additional line in MDDP-ODG(Multi tracking) | | 22-23 | Survey sanctioned. Alignment given to Cons Branch with one goods shed loop at ITKL location.. |
20 | ET-KNW 3rd & 4rth line | | 23-24 | Survey sanctioned. |
21 | PRKD-GRO chord line | | 23-24 | Survey sanctioned. |
INFRASTRUCTURE WORKS
S No | | Cost | Year | Remarks |
Works shortlisted under umbrella in 23-24. | ||||
1. | BIR Additional loop | 100000 | 23-24 | Shortlisted, under sanction with RB |
2 | Improvement of Goods shed facilities at SMT goods shed, additional siding. | 54189 | 23-24 | Shortlisted, under sanction with RB |
3 | Increasing CSR of 14 loops | 100000 | 23-24 | With Accounts for vetting. |
4 | RKMP two loops with two stabling lines (vande Bharat) | 219983 | 23-24 | With ED/WP. |
5 | 14 New stations in GUNA-GWL, RTA-MKC | 34800000 | 23-24 | Compliance to NDRB query. With GSU for DPR. |
6 | BPF- Up gradation of goods shed facility, increase of CST and provision of suitable crossover’s. | 72900 | 23-24 | With HQ |
7 | BPL yard remodelling phase I for cut and connection at RKMP end. | 179500 | 23-24 | With Accounts for vetting. |
Status of other important works:
TLV-BIR speed raising:
Presently the speed is 50 kmph. Application was moved for 110 kmph. CRS has commented to provide physical isolation in TLV Loop line for which ESP/SIP has been approved. Work has to be done by Division.
NSZ Yard Platforms
Commissioned, notification for stoppages to be issued by HQ.
Bina 3rd/4rth line(NCR) and doubling in BINA-MDVK:
ESP of BINA station prepared. Estimate consolidated and cost communicated to NCR.
THANK-YOU