Instream Restoration in the Mid Klamath
By Mitzi Wickman, Project Coordinator, Mid Klamath Watershed Council, mitzi@mkwc.org
May 13, 2025
Construction complete. Heavy equipment operations occurred on August 7, 11, 15, 16, 18, 24, and 25 and September 11, 12, and 15, and October 5, 2023. Remnant hatchery infrastructure and associated berms were removed to provide fish habitat on 1.25 acres, along 0.1 miles of Camp Creek.
Funded by the Collaborative Forest Landscape Restoration Program
Partners: Karuk Tribe, Six Rivers National Forest, Mid Klamath Watershed Council
Thank you for letting me share my perspective on what the Instream Restoration group is trying to accomplish, what we do on the daily basis to get there, what that looked like for the Camp Creek hatchery and berm removal project, and looking ahead to future projects.
Questions?
Comments?
Please feel free to reach out anytime.
Mitzi Wickman, Project Coordinator, Mid Klamath Watershed Council, mitzi@mkwc.org