Community Task Force

2019 Bond Project Update

March 10, 2020

2 of 66

Presentation Content

  • Review of Facility Planning

  • Process and Timeline for Projects

Secure Entrances Sunshine Jarrett

SW ECC Boyd Hillcrest

Delaware Williams

3 of 66

Draft Project Sequencing Plan

Provided to BOE November 13, 2018 - Posted on BoardDocs

Progression of the work presented April 2019 is on track.

4 of 66

Project Updates

  • Fulbright Early Childhood Center - Under Construction
  • Delaware Elementary - Under Construction
  • Sunshine Elementary - Under Construction
  • Boyd Elementary - Construction Drawings
  • Jarrett Middle School - Construction Drawings
  • Hillcrest High School - Construction Drawings
  • Williams Elementary - Design Development

5 of 66

Secure Entrances

6 of 66

Project Specifics - Secure Entrances $7.8 Million

31 sites and 33 secure entrances

Bingham Elementary

McBride Elementary

Shady Dell EC Center

Bissett Elementary

McGregor Elementary

Sherwood (former site)

Carver Middle

Parkview High (2)

Study Alternative Center

Central High (2)

Pershing K-8

Truman Elementary

Cowden Elementary

Phelps Gifted Center

Twain Elementary

Disney Elementary

Pipkin Middle

Watkins Elementary

Field Elementary

Pittman Elementary

Weller Elementary

Holland Elementary

Pleasant View K-8

Wilder Elementary

Jarrett Middle (current site)

Reed Academy

Wilson’s Creek 5-6

Mann Elementary

Robberson Community

York Elementary

Rountree Elementary

Schools highlighted have completed construction.

7 of 66

Updated Secure Entrance Sequencing Plan

8 of 66

Secure Entrances

Pleasant View K-8 main entrance

9 of 66

Secure Entrances

Wilson’s Creek main entrance

10 of 66

Secure Entrances

Bissett Elementary main entrance

11 of 66

Secure Entrances

Delaware Elementary (Former Sherwood) main entrance

12 of 66

Secure Entrances

Rountree Elementary main entrance

13 of 66

Secure Entrances

York Elementary main entrance

14 of 66

Secure Entrances

Field Elementary main entrance

15 of 66

Secure Entrances

McBride Elementary main entrance

16 of 66

Secure Entrances

Cowden Elementary main entrance

17 of 66

Secure Entrances

Holland Elementary main entrance

18 of 66

Secure Entrances

Pittman Elementary main entrance

19 of 66

Secure Entrances

Disney Elementary main entrance

20 of 66

Adah Fulbright Early Childhood Center

21 of 66

Fulbright Early Childhood Center

22 of 66

Fulbright Early Childhood Center

23 of 66

Fulbright Early Childhood Center

24 of 66

Fulbright Early Childhood Center

25 of 66

Delaware Elementary

26 of 66

Delaware Elementary

27 of 66

Delaware Elementary

28 of 66

Delaware Elementary

29 of 66

Delaware Elementary

30 of 66

Sunshine Elementary

31 of 66

Sunshine Elementary

32 of 66

Sunshine Elementary

33 of 66

Sunshine Elementary

34 of 66

Sunshine Elementary

35 of 66

Boyd Elementary

36 of 66

Boyd Elementary

37 of 66

Boyd Elementary

  • Bid opening - April 23, 2020
  • BOE recommendation of bid - May, 2020
  • Total project budget $20,340,000, original construction estimate $16,143,394
  • Anticipated construction begins - May, 2020
  • Anticipated construction completion - May, 2021

38 of 66

Jarrett Middle School

39 of 66

Jarrett Middle School

  • Demo anticipated start date at Portland - June, 2020
  • Anticipated bid opening - July, 2020
  • BOE recommendation of bid - August, 2020
  • Total project budget $41,540,000, original construction estimate $32,970,000
  • Anticipated construction begins - August, 2020
  • Anticipated construction completion - August, 2022

40 of 66

Jarrett Site Aerial View

Current Portland Elementary site

9.5 acres

41 of 66

Jarrett Middle School

42 of 66

Jarrett Middle School

43 of 66

Jarrett Middle School

44 of 66

Jarrett Middle School

45 of 66

Jarrett Middle School

46 of 66

Jarrett Middle School

47 of 66

Jarrett Middle School

48 of 66

Hillcrest High School

49 of 66

Hillcrest High School

  • Anticipated bid opening - July, 2020
  • BOE recommendation of bid - August, 2020
  • Total project budget $24,750,000, original construction estimate $19,641,369
  • Anticipated construction begins - August, 2020
  • Anticipated construction completion - August, 2022

50 of 66

Hillcrest Site Aerial View

51 of 66

Hillcrest High School

Playground equipment

Overall Site Plan

52 of 66

Hillcrest High School

53 of 66

Hillcrest High School

54 of 66

Hillcrest High School

55 of 66

Hillcrest High School

First Floor

56 of 66

Hillcrest High School

Second Floor

Basement

57 of 66

Williams Elementary

58 of 66

Williams Site Aerial View

Current Williams Elementary site

15.91 acres

59 of 66

Williams Elementary

60 of 66

Williams Elementary

61 of 66

Williams Elementary

62 of 66

Williams Elementary

63 of 66

Williams Elementary

64 of 66

Williams Elementary

  • Demo anticipated at Williams - June, 2020
  • Anticipated bid opening - June, 2020
  • BOE recommendation of bid - July, 2020
  • Total project budget $17,970,000, original construction estimate $14,264,586
  • Anticipated construction begins - July, 2020
  • Anticipated construction completion - August, 2021

65 of 66

Progress as Promised

66 of 66

Questions & Clarifications