TASKS

Gary w/ Stefan’s Assistance

  • Cut main roof 2x12 rafters (trim to length and cut birdsmouth) √
  • Cut main roof fascia √

4 of 9

CREW - 3

Shaun Quirk

Bernard Bédard

Nicolas Bodet

OCTOBER 29 - SATURDAY

TASKS

Crew

  • Cut top floor siding to 5 ft and 1 ft sizes √
  • Stain top floor siding

5 of 9

CREW - 6

Shaun Quirk

Drew Scheneman

Bernard Bédard

Nicolas Bodet

Jabari Allen

Lara Redmond

OCTOBER 30 - SUNDAY

TASKS

Gary Leads Crew

  • Determine birdsmouth for utility roof and cut 2x8 rafters (trim to length and cut birdsmouth)
  • Make pre-workshop modules
  • Cut siding panels for all doors and windows
  • Determine rafter seat for greenhouse roof and cut 1 template

6 of 9

CREW - 9

Shaun Quirk

Drew Scheneman

Bernard Bédard

Nicolas Bodet

Jabari Allen

Lara Redmond

Stefan Karl Watzke

Richard White

Ana Lavanholi

OCTOBER 31 - MONDAY

TASKS

Marcin

  • Finish foundation forms and pour

Catarina

  • Stain panels
  • Paint rafters white
  • Paint ceiling sheathing white (bottom of floor plywood)
  • Cut and paint trim for top floor windows

7 of 9

CREW - 10

Shaun Quirk

Drew Scheneman

Bernard Bédard

Nicolas Bodet

Stefan Karl Watzke

Richard White

Ana Lavanholi

Ioan Lascu

Mark Huntsberry

Jeremy Lauten

NOVEMBER 1 - TUESDAY

TASKS

Gary

  • Remove forms
  • Install sill plate
  • Bend and install aluminum flashing for foundation
  • Bend aluminum flashing for fascia

Catarina

  • Finish staining modules
  • Transport modules and materials to build site
  • Adjust window module
  • Clean faculty house
  • Cover wood and modules

Jenna

  • Make CEB frame
  • Make 32” and 36” door modules
  • Cut utility room door sheathing

8 of 9

CREW - 12

Shaun Quirk

Drew Scheneman

Bernard Bédard

Nicolas Bodet

Stefan Karl Watzke

Richard White

Ana Lavanholi

Ioan Lascu

Mark Huntsberry

Jeremy Lauten

Michael Beyer

Will Lennox

NOVEMBER 2 - WEDNESDAY

TASKS

  • Receive Menards materials delivery (afternoon)
  • Organize workshop and materials
  • Inventory tools
  • Purchase additional tools and supplies
  • Setup and orient Adrian

  • Make 37” utility room module
  • Cut greenhouse window sheathing

  • Food purchase
  • Fill propane tanks (there are 2 by the main house)
  • Tools + materials purchase

9 of 9

CREW - 12

Shaun Quirk

Drew Scheneman

Bernard Bédard

Nicolas Bodet

Stefan Karl Watzke

Richard White

Ana Lavanholi

Ioan Lascu

Mark Huntsberry

Jeremy Lauten

Michael Beyer

Will Lennox

NOVEMBER 3 - THURSDAY

TASKS

  • Stefan: paint floor joists (all sides), ceiling plywood (1 side) and 1x6s (all sides)
  • Adrian: cut spacers for exterior trim out of T1-11 scraps: 110 - 5” x 3” pieces (they don’t need to be perfect size/shape)
  • Adrian (after spacers are done): cut (20) 2x6 to 93” from 8ft boards + (40) 2x6 to 48” (cut 8 ft in half if there is no additional length for cut)
  • Sutherlands (Cameron) run:

  • Prepare main house floor pad + lay down OSB