Fire Inspection and�Code Enforcement
8th Edition�Inspector II
Chapter 15 — Plans Review and� Field Verification
�Learning Objective 1
Explain the impact of local codes and ordinances on the plans review process.
15–1
Reviewing documents and issuing permits are official government acts.
15–2
Many agencies use third-party agencies to assist with construction document review
In this instance, they should coordinate the review with the fire department to make sure locally adopted statutes and codes are addressed
Many plans review agencies publish a process guide that outlines the plans review process
Individuals can review a copy and ask questions before they submit applications
Courtesy of Rich Mahaney
Understand the general steps in the plans review process.
15–3
Application and Submittal
(Cont.)
Understand the general steps in the plans review process.
15–4
Review
(Cont.)
Understand the general steps in the plans review process.
15–5
Resubmittal
(Cont.)
Understand the general steps in the plans review process.
15–6
Accept
(Cont.)
Understand the general steps in the plans review process.
15–7
Authorize
Administrative chapter of the model building code contains specific provisions for permit applications.
15–8
Requirements
Understand the importance of tracking project changes.
15–9
Clients may make minor revisions, called change orders
Plans examiners must maintain records of these communications for possible reference
Inspectors should be aware of all changes to the construction plans; inspect the project to verify that the changes are made as approved
In some locations, all changes made throughout the project must be collated into a single set of documents and submitted as a record set of construction documents for the project; known as an “as-built” set of documents
The local jurisdiction determines manner in which plans are handled or routed through the review process.
15–10
In some jurisdictions, building department examiners review the plans before plumbing, electrical, mechanical, or fire protection reviewers
Ideally, all plans for a project are submitted to the reviewing authority at the same time
There are times when this procedure is not best
Agencies that review construction documents may charge a fee.
15–11
Used to defray administrative costs associated with the review
Fees are established by ordinances and are similar to other municipal fees
Manner in which fees are determined varies with the jurisdiction
Submitted plans should have all information necessary to evaluate compliance with locally adopted code.
15–12
Help an inspector know what to expect during construction
All information must be clearly visible and not obscured because of the size or print quality of the drawing
Details may be required to be in a larger scale than the floor plan or elevation drawings
Know the different types of supporting documentation that may be required for review.
15–13
Hydraulic calculations
Material specifications
Safety data sheets (SDS)
Manufacturers’ product submittal information sheets; called cut sheets
Project manuals or specification books
REVIEW QUESTION
What are the general steps of the plans review process?
15–14
�Learning Objective 2
Describe the different views for building construction plans.
15–15
Working drawings detail the design and building’s construction using four main views.
15–16
Plan
Elevation
Sectional
Detailed
Each of these drawings should have a title block that contains specific information.
15–17
Title of the drawing, such as Basement Floor Plan or Site Plan
Description of the project
Scale of the drawing; for example, 1/8” = 1’0”
(Cont.)
NOTE
Scaling the drawing provides a view in exact proportion to the actual size of the building. Sometimes the scale is placed on the drawing rather than in the title block. If a drawing is not to scale, there will be a note indicating that it is not. Copies of old drawings are often not drawn to scale.
15–18
Each of these drawings should have a title block that contains specific information.
15–19
Date the drawing was completed
Revision dates
Name of the firm producing the drawings
Name (usually initials) of the person who made the drawings; person responsible for checking the final drawings
Sheet number in the set
Design professional's official stamp or seal
Working drawings on commercial projects are typically divided into groups by individual discipline.
15–20
Architectural
Structural
Mechanical
Electrical
Inspectors need to understand plan views.
15–21
A two-dimensional view of the site or the building as seen from directly above the area
Provides information concerning the overall layout of the site or building
An inspector or plans examiner will commonly see two basic plan views: site and floor
Occasionally, ceiling and roof plans will also be submitted
Inspectors need to understand plan views.
15–22
Usually one of the first sheets of a set of construction drawings
Identifies conditions currently existing on the site
Relates information needed to locate the building
Know what information is usually found on a site plan.
15–23
North direction symbol
Lot dimensions
(Cont.)
Know what information is usually found on a site plan.
15–24
Utility lines
(Cont.)
Know what information is usually found on a site plan.
15–25
Structures to be removed
(Cont.)
Know what information is usually found on a site plan.
15–26
(Cont.)
Contour lines
Know what information is usually found on a site plan.
15–27
Fire apparatus access
Placing of the building on a site plan is called dimensioning.
15–28
Dimensions are usually placed some distance away from the shapes on the drawing through the use of extension lines
Dimensions are expressed in feet and inches (meters and millimeters)
REVIEW QUESTION
What information is provided by a site plan?
15–29
Floor plans provide general information about building components.
15–30
External walls
Internal walls and partitions
Fire separation walls
Doors
Windows
Ceiling and roof joists or trusses
Stairs
Ramps
Building services
Elevators or escalators
(Cont.)
Floor plans provide general information about building components.
15–31
Items that may be listed
May reflect the location
Understand symbols used on floor plans.
15–32
Walls
Windows
(Cont.)
Understand symbols used on floor plans.
15–33
Doors
Elevation view is a two-dimensional view of a building as seen from the exterior.
15–34
Labeling and orientation of the drawing are usually defined by the AHJ
There are four exterior elevation views on any rectangular building
There are two labeling methods commonly used
Contain information about the exterior components of the building
Grade level is shown as a dark line
Utility service line connection points and FDCs will also appear
A sectional view is a vertical view of a building cut into two parts.
15–35
Purpose is to show the internal construction of each assembly
Three types of sectional views: cross-section, typical cross section, detailed cross section
Sectional views show a number of construction details.
15–36
Exterior walls
Interior walls
Floor
Roof
Foundation
Listing the construction materials is referred to as “calling up the materials”.
15–37
Procedure is used to describe wall, floor, and ceiling/roof assemblies
Materials are listed on the drawing or in the construction documents
REVIEW QUESTION
What is the purpose of a sectional view?
15–38
Detailed views show features in larger sizes than other views.
15–39
Additional information is provided in a larger scale on a separate sheet of the plans
A floor plan drawing may show a fire door; a detailed view will show the exact construction of the fire door and its activation mechanism
REVIEW QUESTION
What are the four main views for building construction working drawings?
15–40
�Learning Objective 3
Describe building system plans.
15–41
System plans provide details of the various systems in the building.
15–42
Mechanical systems
Electrical systems
Plumbing systems
Automatic sprinkler systems
Standpipe and hose systems
Special-agent fire extinguishing systems
Fire detection and alarm systems
Know what inspectors need to understand about system plans.
15–43
May only be concerned with the fire protection systems plans
However, should be aware that elements of the other plans may influence the review of the fire protection systems plans
Mechanical systems provide occupants with HVAC and access to upper and subgrade floors.
15–44
Systems included should be designed by a mechanical engineer or building systems engineer
Mechanical systems are capable of spreading fire and smoke
Must verify that all detection and alarm systems and control dampers are included in the plans
Inspectors should verify the style and design of the HVAC system.
15–45
Type of refrigerant used in the system and listed in the construction documents should be checked
Be familiar with code requirements concerning the automatic de-energizing of heating systems
Plans must indicate the location and type of smoke detectors inside the ductwork used to de-energize air handlers
Fire and/or smoke dampers may be required where the ductwork penetrates fire-resistive walls/floors.
15–46
Plans will indicate the location of these features
Some codes prohibit ductwork from penetrating exit areas
Exits are not permitted to be used for supply or return air
Additional references for damper placement and installation of ductwork are contained in NFPA® 90A, 90B, 92A, 92B, or the locally adopted mechanical code
Know code requirements for commercial kitchen equipment and systems.
15–47
Cooking appliances
Range ventilation hoods
Fuel shutoffs
Automatic fire suppression systems
Fire alarm systems
Know what to verify when reviewing electrical systems.
15–48
Location of exit signs
Means of egress lighting
Emergency and standby power
Power supply to fire detection and alarm systems
Emergency or standby power systems
Hazardous location electrical equipment
NFPA 70 regulates the design/installation of electrical systems
Plumbing systems include the layout of the water distribution system.
15–49
Wastewater piping
Storm drains
Roof drains
Secondary containment and drainage systems for hazardous materials
Inspectors may review plumbing systems to determine the adequacy of the water supply.
15–50
Adequate water supply is important when residential automatic sprinkler systems are installed
Other fire protection system components that may appear on the plumbing plans are water supply connections to the standpipe system and fire pump
A thorough, accurate review of sprinkler systems plans is necessary to verify compliance and effectiveness.
15–51
Inspectors need to be familiar with different types of automatic sprinkler systems.
15–52
Be familiar with operations and specifications for each type of system
When required, an inspector needs to be able to develop a field inspection checklist of the specific requirements for sprinkler systems and the code sections that relate to the requirements
This checklist can be used as a guide during sprinkler plans review
Verify that the proper NFPA® standard has been applied.
15–53
Occurs before plans review begins
Involves classifying hazards
Drawings for hydraulically calculated sprinkler systems require supporting documentation.
15–54
Proves the design complies with code
System designer provides all necessary information including calculations and applicable data
All documentation must be reviewed carefully for accuracy
Plans reviewers need to check several sprinkler design factors.
15–55
Extent of coverage
Design area of system
Type of system
Size of system
Water supply connections and valves
Water supply capacity at site
Fire department connection (FDC)
Sprinkler types, temperature ratings, and locations
Pipe sizes and lengths
Number of pipe elbows and tees
Type and number of pipe hangers
Requirements for seismic bracing
Become familiar with other items that require review.
15–56
Sprinkler cut sheet
Installation
Installation standards determine
(Cont.)
Become familiar with other items that require review.
15–57
Specifications to verify
Drawings should clearly indicate
Know how water supplies directly impact sprinkler performance.
15–58
Water supplies for sprinklers must have sufficient capacity and pressure to satisfy the calculated requirements for hydraulically designed systems
System designer must include a graph that shows the water demand compared to the available water supply
Fire protection and plumbing system plans are to determine several things.
15–59
System type
System classification
FDC location(s)
Water supply main location and capacity
Riser control valve type and location
Location of hose cabinets or discharges
Discharge control valves locations
Pressurized air supply type, capacity, and locations
Waterflow calculations
Be familiar with requirements for each type of special-agent fire extinguishing system.
15–60
Calculation sheets used to design the system
Definition of the area or equipment to be protected
Type of system (local application or total flooding)
Type of extinguishing agent being used
Amount of agent required
Concentration of extinguishing agent to be developed
Storage container size
(Cont.)
Be familiar with requirements for each type of special-agent fire extinguishing system.
15–61
Type of expellant gas
Rate of discharge
Duration of flow
Layout and type of piping included (whether engineered or pre-engineered)
Location and type of discharge nozzles
(Cont.)
Be familiar with requirements for each type of special-agent fire extinguishing system.
15–62
Method of actuation and auxiliary alarm functions such as turning off ventilation
Type of presignaling devices used if required
Area and volume of the protected space
Sequence of operation
Plans for fire protection and alarm signaling systems contain information on system components.
15–63
Signal initiation devices
Signal notification appliances
Automatic door closing devices
Lightning protection devices
Smoke control devices
Damper control devices
Fire pumps
Power supply
Auxiliary power supply
Plans for fire protection and alarm signaling systems contain information on system functions.
15–64
Supervision of alarm systems
Elevator control
Stair pressurization
Doors that unlock or close automatically when the alarm activates
NOTE
Consult NFPA 72®, Chapter 4, for information on detection and alarm system components.
15–65
Be familiar with additional information found in manufacturer documents.
15–66
Battery load and voltage drop calculations
Manufacturers’ cut sheets
Point-to-point wiring diagrams
Be familiar with additional information found in various other specifications.
15–67
Type and gauge of wire
Protection provided for the wire
Wiring methods
Methods of supervision
Sequence of operation
Be familiar with additional requirements for electrical systems.
15–68
All fire detection and alarm systems must have electrical supervision
All fire detection and alarm equipment must be listed by a nationally recognized testing agency for their intended use
Specified maximum travel distances to manual pull boxes
Code requirements concerning pull station placement for accessibility to persons with disabilities
REVIEW QUESTION
List various types of system plans.
15–69
�Learning Objective 4
Explain the process of systematic plans review.
15–70
General elements should be systematically reviewed.
15–71
Overall size of building (height and area)
Occupancy classification
Occupant load
Means of egress
Exit capacity
Building compartmentation
Review the overall size of the building in terms of height and area.
15–72
Courtesy of David DeStefano
Based on:
Know local code information for:
Review the overall size of the building in terms of area.
15–73
Fire control and suppression operations
Basis for area increase or decrease
Know inspector duties regarding occupancy and construction classification.
15–74
Occupancy
Construction
A plans examiner verifies the occupant load.
15–75
before evaluating the life safety and fire protection features of a building
Inspectors can use the occupant density or occupant load factors given in the codes to determine the occupant load
Design professionals are required to provide the occupant load calculations for verification
Know inspector duties regarding means of egress.
15–76
Should be highlighted on the construction, mechanical, and electrical drawings
Building plans must show details of the separation walls as well as fire door opening protectives information
(Cont.)
Know inspector duties regarding means of egress.
15–77
Codes
Items to verify
Know inspector duties regarding means of egress and exit capacity.
15–78
Additional means of egress items to verify
Exit capacity
Inspectors should understand building compartmentation.
15–79
Theory
Includes
Know what to look for when it comes to building compartmentation.
15–80
Verify the fire-resistance rating of the construction separating all vertical openings
Locate and check fire and smoke barriers for continuity, fire-resistance rating, and opening protection
During field inspections, it is often difficult to verify the existence of fire-stops in concealed spaces and penetrations
Design professional must provide plans that clearly show the location of required fire-stops and the building system that is being installed
When evaluating hazardous areas, verify the required separation and/or automatic sprinkler protection has been provided
Be aware of additional concerns when evaluating plans.
15–81
Omissions
Materials that produce smoke and toxic gases when burning
Interior finishes
(Cont.)
Be aware of additional concerns when evaluating plans.
15–82
Furnishings and decorations
Portable fire extinguishers
(Cont.)
Be aware of additional concerns when evaluating plans.
15–83
Insulation materials
Special hazards
REVIEW QUESTION
What are the general elements that should be reviewed in a systematic plans review?
15–84
�Summary
15–85
(Cont.)
�Summary
15–86
(Cont.)
�Summary
15–87