DEVELOPMENT
OF
20 RAILWAY STATIONS
UNDER
AMRIT BHARAT STATION SCHEME
IN
PUNE DIVISION
BY
GATI-SHAKTI UNIT
Section | SN | Station | Estimated cost (in Cr.) |
PA-LNL | 1 | Chinchwad | 20.44 |
2 | Akurdi | 33.83 | |
3 | Dehu road | 8.05 | |
4 | Talegaon | 40.34 | |
PA-BRMT | 5 | Hadapsar | 24.86 |
6 | Uruli | 12.86 | |
7 | Kedgaon | 12.55 | |
8 | Baramati | 11.40 |
Section | SN | Station | Estimated cost (in Cr.) |
PA-KRD | 9 | Lonand | 10.48 |
10 | Wathar | 7.97 | |
11 | Satara | 34.31 | |
12 | Karad | 12.51 | |
13 | Phaltan | 0.76 | |
KRD-KOP | 14 | Sangli | 24.20 |
15 | Hathkanangle | 6.00 | |
16 | Kolhapur | 43.03 |
STATIONS
Section | SN | Station | Estimated cost (in Cr.) |
�����DD-MMR | 1 | Daund | 44.17 |
2 | Ahmednagar | 30.92 | |
3 | Belapur | 31.96 | |
4 | Kopargaon | 29.94 |
STATIONS
Amrit Station Works Status (Except FOB) Pune GSU
S N | Name of station | TDC | Position of FOB | S N | Name of station | TDC | Position of FOB |
1 | Kedgaon | Complete | NA | 11 | Belapur | 31.12.25 | 1. FOB – 31.03.26 |
2 | Lonand | Complete | NA | 12 | Ahmednagar | 30.07.25 | 1. FOB – 31.03.26 |
3 | Talegaon | 30.06.25 | 1. FOB - 30.12.25�2. 3 LIFT & 3 ESC - 31.03.26 | 13 | Akurdi | 30.09.25 |
|
4 | Baramati | 30.06.25 | NA | 14 | Daund | 31.12.25 | 1. FOB – 31.03.26 2. Escalator-31.03.26 |
5 | Wathar | 30.07.25 | NA | 15 | Sangli | 30.11.25 | 1. FOB - 31.03.26�2. 2 LIFT & 3 ESC - 31.03.26 |
6 | Phaltan | Complete | NA | 16 | Dehu Road | 31.10.25 | 1. FOB - 30.03.26 |
7 | Kopargaon | 30.06.25 | FOB - 31.03.26 | 17 | Uruli | 31.03.26 | NA |
8 | Satara | 30.09.25 | 1. FOB - 28.02.26�2. 1 LIFT & 3 ESC -31.03.26 | 18 | Hathkangale | 21.11.25 | NA |
9 | Chinchwad | 31.08.25 | 1. FOB (extn) – 31.03.26�2. 4 LIFT & 2 ESC - 31.03.26 | 19 | Kolhapur | 21.11.25 | 1. FOB – 31.03.26�2. 2 LIFT & 2 ESC – 31.03.26 |
10 | Karad | 30.09.25 | NA | 20 | Hadapsar | 15.12.25 | 1. FOB & Skywalk– 15.12.25�2. 2 LIFT & 02 Escalator – 31.03.2026 |
Talegaon (Estimated cost: 40.39 Cr)
Current status
Physical Progress- 55%
Phase-I Works TDC: Soft- 30.06.2025
FOB- 30.12.2025
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
TALEGAON (SG-3) –Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1
| Provision of New Portico (DN Side) | |
Development of Circulating Area and Parking on Main entry (DN Side) | ||
Development of Circulating Area and Parking on Main entry (UP Side) | ||
Provision of COP (approx. 380 sq.m.) | ||
PF Surface Improvement | 100 % | |
Provision of new toilet Block at PF-1 | ||
Provision of new toilet Block at PF-2 | ||
Renovation of existing Booking office | ||
Renovation of existing waiting room with roof replacement (Mangalore tile) at PF-2 (Interior) | ||
Construction of new waiting room at PF-1 | ||
Construction of new water booth (6 Nos) (3 at each PF) | 85 % | |
•Provision of 03 escalators and 03 lifts (Foundation of 2 lifts in progress ) | ||
| Electrical |
|
| Electrical works of TRD and general portion | 90 % |
| Provision of 3 lifts and 3 escalators | 55 % |
| Minimum Essential Amenities and facilities for divyangjan (Except telecom, lift and quick watering system) | 80 % |
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 85 % |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items | 85 % |
|
|
|
| Commercial |
|
| Provision of Furniture |
|
Important new additions and Improvement works planned (Talegaon)
Dehu Road (Estimated cost: 8.05 Cr)
Phase-I Works TDC: Soft- 31.10.2025
FOB- 30.03.2026
Current status
Physical Progress-10%
Dehu Road (NSG-3)–Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1 | Main Entry Gate | N/A |
Provision of New portico with entrance lobby extension |
| |
Provision of new toilet block at PF-1 | ||
Development of Circulating Area and parking | 0 % | |
Renovation of existing Booking office with entrance lobby after completion and extension of entrance lobby |
| |
COP at PF-1 & 2 | ||
PF Surface |
| |
•Improvement to Façade |
| |
•Augmentation of Seating Facilities and signages, Improvement to Illumination |
| |
Renovation of existing waiting room, SS office |
| |
| Electrical |
|
| Electrical works of TRD and general portion (DG Room completed) | 100 % |
| Provision of lifts and escalators |
|
| Minimum Essential Amenities and facilities for Divyangjan (Except telecom, lift and quick watering system) |
|
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 35% |
| Telecom, Expansion of information system to facilitate Divyangjan and other PA items | 35% |
| Commercial |
|
| Provision of Furniture |
|
Important new additions and Improvement works planned (Dehu road)
AKURDI (SG-3) Estimated Cost: 33.83 Cr.
Current status
Physical Progress- 48 %
Phase-I Works TDC:
Soft- 30.09.2025
FOB- 30.12.2025
Escalator TDC - 31.03.2026
�
�
AKURDI (SG-3) Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
| Construction of New Waiting Area(LHS &RHS SIDE) | |
Construction of Portico | ||
Construction of DG Room | 100 % | |
Construction of UGWT | 100 % | |
Main Entry Gate | 0 % | |
Construction of Parking/Circulation Area | 47 % | |
Construction of Public Plaza | 0 % | |
Renovation Work ( Existing Booking Office ) | 15 % | |
Construction of Water Booth 4 nos | 90 % | |
COP Work | ||
PF - 1 Flooring Work | ||
COP Work | 95 % | |
PF - 2 Flooring Work | 80 % | |
Construction of New FOB | ||
| Electrical |
|
| Electrical works of TRD and general portion. | 20% |
| Provision of lifts and escalators. |
|
| Minimum Essentials Amenities and facilities for divyangjan (Except telecom, lift and quick watering system). |
|
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 55% |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items. | 55% |
| Commercial |
|
| Provision of Furniture. |
|
Important new additions and Improvement works planned (Akurdi)
CHINCHWAD (SG-3) (Estimated cost: 20.44 Cr-)
Current status
Physical Progress- 46 %
Phase-I Works TDC:
Soft- 31.08.2025
FOB- only extension at 2nd Entry 31.03.2026
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
CHINCHWAD(SG-3) –Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1
| Provision of New Entrance lobby cum waiting lounge at main entry with portico (DN Side) | |
TOILET UNDER FOB | 80% | |
Construction of New RPF THANA | 100% | |
Construction of New OHE room | ||
Development of Circulating Area and parking on Main entry (DN Side) by demolishing existing RPF SETUP | ||
Extension of booking office with provision of OFC room, Electrical panel room, CBS room with toilet | ||
Renovation of existing Booking office | ||
Provision of new toilet Block at PF-1/2 | ||
Provision of new toilet Block at PF-3/4 | ||
Provision of 1 Lift and 1 escalator at main entrance | ||
Renovation of water booths and existing toilet | 0 % | |
Renovation of existing waiting room , SS office | 50% | |
Provision of 03 lift (01 each at PF 1 / 2 & 3 / 4 at 2nd entry) | ||
COP Work | ||
Platform surface improvement | 0% | |
| Electrical |
|
| Electrical works of TRD and general portion. |
|
| Provision of lifts and escalators. |
|
| Minimum Essential Amenities and facilities for Divyangjan (Except telecom, lift and quick watering system). |
|
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 80% |
| Telecom, Expansion of information system to facilitate Divyangjan and other PA items. | 75% |
| Commercial |
|
| Provision of Furniture |
|
Important new additions and Improvement works planned (Chinchwad)
HADAPSAR
(Estimated cost: 24.86 Cr)
Current status
Overall Physical Progress- 45 %
Phase-I Works TDC: Soft- 15.12.2025� FOB & Skywalk– 15.12.25� 2 LIFT & 02 Escalator – 31.03.2026
�
SN | Scope | Progress |
PHASE-I | | |
1 | PF surface at PF no. 1, 2 & 3 | 40 % |
2 | PF 1 building A (reservation office, waiting room, dormitory) | |
| PF 1 building B (Existing building extension, RPF Post, child care room) | 100% |
4 | Building C (VIP waiting room, upper class waiting, toilet block, RPF office) | 100 % |
5 | Building D parcel office | 100% |
6 | COP | 85% |
7 | FOB | 25% |
HADAPSAR (NSG-6)–Scope of work (with TDC and overall progress)
HADAPSAR
(Estimated cost: 24.86 Cr in PH-53 under ABSS & 135.81 Cr. under PH-16)
Highlights of Planned works
URULI (NSG-5) (Estimated cost: 12.86 Cr)-
Current status
Overall Physical Progress- 94 %
Phase-I Works TDC: Soft- 31.03.26� FOB- NA
URULI (NSG-5) –Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1 | PF1- Construction of Parking Area | 75 % |
PF1- Construction of Portico | 80 % | |
Construction of front elvation | 90 % | |
Renovation of Existing booking area, Entrance lobby & waiting room | 95 % | |
Renovation of Waiting Area attached Toilet | 95 % | |
Construction of PF Toilet Block | 100 % | |
Construction of Water Booth | 90 % | |
COP & PF SURFACE | 100 % | |
Platform Flooring Work PF1 | 90 % | |
Cover Over Platform ( COP ) PF1 | 100 % | |
FOB ramp - |
| |
Ramp work | 95 % | |
| Electrical |
|
| Electrical works of TRD and general portion. |
|
| Provision of lifts and escalators. |
|
| Minimum Essential Amenities and facilities for divyangjan (Except telecom, lift and quick watering system). |
|
| S & T |
|
| Provision of Pasanger Amanities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 70% |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items. | 70% |
| Commercial |
|
| Provision of Furniture. |
|
Important new additions and Improvement works planned (Uruli)
KEDGAON (NSG-5)(Estimated cost: 12.54 Cr)
Current status
Physical Progress- 100%
Phase-I Works TDC: Soft- 28.02.25
FOB- NA
KEDGAON (NSG-5)–Scope of work (with TDC and overall progress)
Sr. No. | Scope | Physical Progress |
| Civil |
|
PH-1
| Main Entry Gate | 100% |
PF1- Construction of Compound Wall | 100% | |
PF1- Construction of Parking Area | 100% | |
PF1- Construction of Portico | 100% | |
Construction of front elevation | 100% | |
Renovation of Existing booking area, Entrance lobby & waiting room | 100% | |
Renovation of Waiting Hall | 100% | |
Construction of PF Toilet Block | 100% | |
Construction of Water Booth | 100% | |
PF SURFACE |
| |
PF-1 | 100% | |
PF-2 | 100% | |
Cover Over Platform ( COP ) |
| |
PF-1 | 100% | |
PF-2 | 100% | |
FOB ramp PF-1 | 100% | |
FOB ramp PF-2 | 100% | |
| Electrical |
|
| Electrical works of TRD and general portion. | 100 % |
| Provision of lifts and escalators. | 100 % |
| Minimum Essential Amenities and facilities for Divyangjan (Except telecom, lift and quick watering system) | 100 % |
| S & T |
|
| Provision of Pasanger Amanities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 100% |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items. | 100% |
| Commercial |
|
| Provision of Furniture. |
|
Important new additions and Improvement works planned (Kedgaon)
BARAMATI (NSG-5) (Estimated cost: 11.40 Cr)
Current status
Physical Progress- 78%
Phase-I Works TDC: Soft- 30.06.2025
FOB- NA
BARAMATI (NSG-5)–Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1 | Main Entry Gate | 75 % |
PF1- Construction of Compound Wall | 100 % | |
PF1- Construction of Parking Area | 75 % | |
PF1- Construction of Portico | 87 % | |
Construction of Verandah | 90% | |
Renovation of Existing booking area, Entrance lobby & waiting room | 77 % | |
Renovation of Waiting Area attached Toilet | 95% | |
Construction of Toilet Block | 100% | |
Construction of Septic Tank | 100% | |
Construction of Water Booth | 100% | |
Platform Flooring Work | 97% | |
Cover Over Platform ( COP ) | 98% | |
| Electrical |
|
| Electrical works of TRD and general portion |
|
| Provision of lifts and escalators | NA |
| Minimum Essential Amenities and facilities for divyangjan (Except telecom, lift and quick watering system) |
|
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 50% |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items | 40% |
| Commercial |
|
| Provision of Furniture |
|
Important new additions and Improvement works planned (Baramati)
WATHAR (NSG-6) (Estimated cost: 7.97 Cr)
Current status
Physical Progress- 75%
Phase-I Works TDC:
Soft- 30.07.25
FOB- NA
WATHAR (NSG-6) Scope of work (with TDC and overall progress) | ||
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 55 % |
2 | Construction Of Compound Wall | 95 % |
3 | Construction Of Parking Area and Circulation Area | 80 % |
4 | Renovation of Existing Booking Office and Entrance Lobby | 90 % |
5 | Renovation of Portico | 90 % |
6 | Improvement of Façade |
|
7 | Improvement of Roof | 100% |
11 | Dismantling of Union Office | 100% |
12 | PF-1 Construction of new water booths |
|
13 | COP PF1 | 100 % |
14 | Improvement of Platform Surface PF1 | 85% |
Important new additions and Improvement works planned (Wathar)
Current status
Physical Progress- 100%
PHALTAN (Estimated cost: 0.92 Cr)
Phase-I Works TDC: Soft- 08.03.2025
FOB- NA
Important new additions and Improvement works planned (Phaltan)
LONAND (Estimated cost: 10.47 Cr)
Current status
Physical Progress- 100%
Phase-I Works TDC: Soft- 28.02.2025
FOB- NA
LONAND (NSG-6) Scope of work (with TDC and overall progress) | ||
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 100% |
2 | Construction of Compound Wall | 100% |
3 | Construction of New portico | 100% |
4 | Construction of Circulation Area | 100% |
5 | Construction of Parking | 100% |
6 | Renovation of Booking Office and Entrance Lobby | 100% |
7 | PF-1 Construction of New Toilet block | 100 % |
8 | PF-1 Construction of Waiting Room | 100 % |
9 | PF-1 Improvement of new water booths | - |
10 | PF-2 Construction of New Toilet block | - |
11 | COP PF 1 | 100 % |
12 | COP PF 2 | 100 % |
13 | Improvement of Platform Surface PF1 | 100 % |
14 | Improvement of Platform Surface PF2 | 100 % |
Important new additions and Improvement works planned (Lonand)
SATARA (Estimated cost: 34.31 Cr)
Current status
Physical Progress- 54 %
Phase-I Works TDC:
Soft- 30.09.2025
FOB- 28.02.2026
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
Sr. No. | Scope | Progress |
2 | Construction of Exit Gate | 95 % |
3 | Construction of New Portico | 90 % |
4 | Construction of Parking Area and Widening of Road | 80 % |
5 | Construction of Curtain Wall | 0 % |
6 | Construction of new TI Room | 80 % |
7 | Construction of VIP Waiting Room Extension | 75 % |
8 | Renovation of Booking Office | 5 % |
9 | Improvement of Façade |
|
10 | PF-1 Renovation of existing General class waiting room / SM Rest Room | 90 % |
11 | PF-1 Renovation of Entrance Lobby | 10 % |
12 | PF-1 Renovation of Upper-Class waiting room with Toilet Block | 100 % |
13 | PF-1 Renovation of Parcel Office | 0 % |
14 | PF-1 Renovation of Ladies waiting room with Toilet Block | 85 % |
15 | PF-1 Construction of New Toilet block | 90 % |
16 | PF-1 Development of new water booths | 0 % |
17 | PF-2&3 - Construction of New Toilet block | |
18 | PF-4&5 -Construction of Toilet Block |
|
19 | COP PF1 | 80 % |
20 | COP PF 2-3 | 23 % |
21 | Improvement of Platform Surface PF 1 | 15% |
22 | Improvement of Platform Surface PF 2-3 |
|
23 | Construction of Civil Works For Escalator |
|
24 | Construction of 12m wide FOB | 30 % |
SATARA (NSG-5) Scope of work (with TDC and overall progress)
Important new additions and Improvement works planned (Satara)
KARAD (NSG-5) (Estimated cost: 12.50 Cr)
Current status
Physical Progress- 65%
Phase-I Works TDC: Soft- 30.09.2025
FOB- NA
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 55 % |
2 | Construction of Compound Wall | 100 % |
3 | Construction of New Portico | 80 % |
4 | Construction of Parking Area | 16 % |
5 | Improvement of Façade |
|
6 | Improvement of Roof | 80% |
7 | PF-1 Renovation of existing General class waiting room | 100% |
8 | PF-1 Renovation of New Upper Class Waiting Room | 100 % |
9 | PF-1 Renovation of Booking Office |
|
10 | PF-1 Renovation of Existing Entrance lobby | 70 % |
11 | PF-1 Construction of New Toilet block |
|
12 | PF-1 Construction of new water booths |
|
13 | COP PF1 | 70 % |
14 | Improvement of Platform Surface PF1 | 20% |
15 | Construction of Civil Works For Escalator |
|
KARAD (NSG-5) Scope of work (with TDC and overall progress)
Important new additions and Improvement works planned (Karad)
SANGLI (Estimated cost: 24.19 Cr)
Current status
Physical Progress- 60 %
Phase-I Works TDC: Soft- 30.11.2025
FOB- 31.03.2026
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 80% |
2 | Construction of New Portico | 70% |
3 | Construction of Parking Area | 35 % |
4 | Construction of Circulation Area | 35 % |
5 | Construction of Compound Wall | PF No. 01 95% |
6 | Construction of Ramp |
|
7 | Construction of New Booking office | 80 % |
8 | Improvement of Facade | 10 % |
9 | PF-1 Renovation of existing General class waiting room | 40 % |
10 | PF-1 Renovation of existing Upper Class waiting room With Male & Female Toilet Blocks | 55 % |
11 | PF-1 Renovation Exisiting Entrance lobby | 5% |
12 | PF-1 Renovation of Existing VIP Lounge | 90% |
13 | PF-1 Renovation of Existing Male, Ladies and Divyangjan Toilet Block | 95 % |
14 | PF-1 Construction of Water Booth | 60% |
15 | COP- PF1 | 97 % |
16 | COP- PF2-3 | 15 % |
17 | Improvement of Platform Surface -PF1 | 80 % |
18 | Improvement of Platform Surface -PF 2-3 | - |
19 | Construction of Civil Works For Escalator | - |
20 | Construction of 12m wide FOB | 35 % |
SANGLI (NSG-5) Scope of work (with TDC and overall progress)
Important new additions and Improvement works planned (Sangli)
HATKANANGLE (NSG-5) (Estimated cost: 6.00 Cr)
Current status
Physical Progress- 93 %
Phase-I : Soft TDC - 21.11.2025
FOB TDC - NA
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 0 % |
2 | Construction of Retaining Wall | 100 & |
3 | Construction of New Portico | 90 % |
4 | Construction of Parking Area and Circulation Area | 80 % |
5 | Construction of Ramp |
|
6 | Construction of Staircase | 95 % |
7 | Construction of New Entrance Lobby | 75 % |
8 | Improvement of Façade | 15 % |
9 | PF-1 Renovation of Existing Booking Office and Existing Entrance Lobby |
|
10 | PF-1 Construction of New Toilet block | 85 % |
11 | PF-1 Construction of New Waiting Room | 80 % |
12 | COP- PF1 | 90 % |
13 | COP- PF 2 | 90 % |
14 | Improvement of Platform Surface PF1 | 75 % |
15 | Improvement of Platform Surface PF 2 | 95 % |
|
|
|
HATHAKANANGLE (NSG-5) Scope of work (with TDC and overall progress)
Important new additions and Improvement works planned (Hatkanangle)
KOLHAPUR (NSG-3) (Estimated cost: 43.03 Cr)
Current status
Physical Progress- 71 %
Phase-I : Soft TDC - 21.11.2025
FOB TDC - 31.03.2026
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
KOLHAPUR (NSG-3) Scope of work (with TDC and overall progress)
SN | Scope | Progress |
1 | Construction of Entry Gate | 75 % |
2 | Construction of Exit Gate | 75 % |
3 | Construction of new portico | 95 % |
4 | Construction of Parking Area and Circulation area | 30 % |
5 | Extension of Existing portico | 60 % |
6 | Construction of New Booking office | 95 % |
7 | Construction of Public Toilet Block | 70 % |
8 | Cover over existing pathway in front of existing building | 85 % |
9 | Main Station Building Roofing Work | 100 % |
10 | Removal of Union office | 80 % |
11 | PF-1 Renovation of existing General class waiting room |
|
12 | PF-1 Renovation of existing AC waiting room With Male & Female Toilet Blocks | 100 % |
13 | PF-1 Renovation of existing PRS | 67 % |
14 | PF-1 Renovation of Exsiting Entrance lobby. | 2 % |
15 | PF-1 Renovation of VIP Entrance lobby. | 50 % |
16 | PF-1 Improvement of Facade | 65 % |
17 | PF-1 Renovation of existing Ladies waiting room | 62 % |
18 | PF-1 Construction of New Toilet block | 95 % |
19 | PF-1 Construction of new water booths | 0 % |
20 | PF-2&3 Construction of New Toilet block | 95 % |
21 | COP - PF1 | 95 % |
22 | COP - PF2-3 |
|
23 | Improvement of Platform Surface PF1 (Work done as per Instruction) | 10 % |
24 | Improvement of Platform Surface PF2-3 | 100 % |
25 | Construction of 12m wide FOB | 35 % |
PH-2 |
| 5% |
| - |
Important new additions and Improvement works planned (Kolhapur)
PUNE Division : Traffic Facility Works GM’s power
SN | Name of work | Year / Last Cost | Allocation/ Exec. Agency | ESP | SIP | Tender Status | CRS | Status | ||
Engg. | S&T | Elect. | ||||||||
1. | Hadapsar - Development as satellite terminal. Scope: Extn. of PF 1 & 2 and additional 3rd PF, 2 Common loops for RBPC trains. | 2016-17 135.81 Cr. (Rev.) | DF(3), RRSK & EBR(S) GSU/PA | 25.5.21 Rev. 31.8.23 | 26.8.21 Rev. 24.4.24
| Awarded | Awarded | Awarded | Ph-II: To be processed |
|
PUNE Division : Traffic Facility Works GM’s power
SN | Name of work | Year / Last San. Cost | Allocation/ Exec. Agency | ESP | SIP | Tender Status | CRS | Status | ||
Engg. | S&T | Elect. | ||||||||
2. | LONI: Development of Goods shed with acquisition of land for increase of circulating area and in length of Goods line with shunting neck. | 2022-23 47.1 Cr. | CAP GSU/PA | 23.05.23 Rev. 20.09.23 | 20.10.23 Revised 02.05.24 | Awarded | Awarded | Awarded | To be processed |
|
Daund Estimated cost: 44.17 Cr
Current status
Physical Progress- 62%
Phase-I : Soft TDC – 31.12.2025
FOB TDC - 31.03.2026
Escalator TDC - 31.03.2026
Renovation works: Renovation to existing quarters.
Important new additions and Improvement works planned (Daund)
AHMEDNAGAR (Estimated cost: 30.92 Cr)
Current status
Overall Physical Progress- 55 %
Phase-I Works TDC: Soft- 30.07.2025
FOB- 31.03.2026
Important new additions and Improvement works planned (Ahmednagar)
KOPARGAON (Estimated cost: 29.94 Cr)
Current status
Overall Physical Progress- 50 %
Phase-I Works TDC: Soft- 30.06.2025
FOB- 31.03.2026
Provision of 2 nos. retiring rooms for passengers, widening of platform 1 towards DD end for 45 m., improvement to drainage was also done.
Important new additions and Improvement works planned (KOPARGAON)
BELAPUR (Estimated cost: 31.96 Cr)
Current status
Overall Physical Progress- 45%
Phase-I Works TDC: Soft- 31.12.2025
FOB- 31.03.2026
Provision of 2 nos. retiring rooms for passengers, extension of platform 1 towards DD end for 150 m., improvement to drainage was also done.
Important new additions and Improvement works planned (BELAPUR)
THANKS