KING’S BEACH �BASIS OF DESIGN STUDY��ALTERNATIVE SELECTION MEETING
October 3, 2022
OVERVIEW
Comparison of Key Metrics
Alt # | Description | Capital Cost* | Net Present Value* | Implementation Duration | % Beach Days Open | Peak Flow Capacity (MGD) |
3 | Chemical Disinfection | $27,000,000 | $25,400,000 | 3.3 years | 90% | 5 |
4 | UV Disinfection | $24,952,400 | $23,346,000 | 3.1 years | 97% | 15 |
5 | Extend Outfall | $55,800,000 | $47,000,000 | 8.8 years | 94% | 10 |
* Cost estimates are reflective of this stage of design and therefore include 50% contingency
Life Cycle Analysis Metrics*
Alt # | Description | Capital Cost | Salvage Value in 2042 | Salvage Present Value | Annual O&M | O&M Present Value | Net Present Value |
3 | Chemical Disinfection | $27,000,000 | $5,070,000 | $4,680,000 | $160,000 | $3,070,000 | $25,400,000 |
4 | UV Disinfection | $24,952,000 | $5,272,000 | $4,868,000 | $170,000 | $3,261,000 | $23,345,000 |
5 | Extend Outfall | $55,800,000 | $7,580,000 | $7,000,000 | $20,000 | $340,000 | $49,000,000 |
* Cost estimates are reflective of this stage of design and therefore include 50% contingency
Alternatives Screening Comparison
Advantages and Disadvantages
See Handout
Basis for Recommendation
OPEN DISCUSSION
Next Steps
�
BACKUP SLIDES
Alternative 3 – Chemical Disinfection
UPDATES TO ALTERNATIVE
Alternative 3 – Chemical Disinfection
UPDATES TO ALTERNATIVE
Bar Screen Section View
Chlorine Contact Tank
UPDATES TO ALTERNATIVE
Alternative 4 – UV Disinfection
UPDATES TO ALTERNATIVE
Alternative 4 – UV Disinfection
UV
Alternative 5 – �Outfall Extension
UPDATES TO ALTERNATIVE