Construction Update

2 of 7

Construction Activities Update as of 10/3/2023:

  • Poured loading dock slab at the restaurant/auditorium

  • Site curbs/sidewalk in progress

  • Stormwater detention chamber in progress

  • Rock wall at terrace garden in progress

  • Restaurant/Auditorium aluminum doors & windows in progress

  • Restaurant/Auditorium exterior sheathing in progress

  • Innovation Center metal roof panels substantially complete

  • Innovation Center MEP rough-in in progress

3 of 7

Aerial view of the CIP campus - 13 March 2024

4 of 7

Looking towards Diamond Head at Restaurant/Auditorium Building

5 of 7

Looking towards Kaimuki, view of the Auditorium entrance (left) and back of restaurant (right).

6 of 7

Looking East at Restaurant entryway and lookout area.

7 of 7

Looking East, view of the Culinary Innovation Center -roofing and exterior sheathing complete.