1 of 27

Infrastructure Development & Funding: Unlocking Opportunities for Water Systems

2 of 27

2

Creating Opportunities in Ontario

WOMC

October 2025

COMMERCIALLY SENSITIVE

3 of 27

EPCOR in Ontario

3

Ontario Head Office

Industrial Water

Electricity

Natural Gas

EPCOR Operations

South Bruce Natural Gas

Southern Bruce natural gas distribution system for Kincardine, Arran- Elderslie and Huron - Kinloss (4,500+ connections)

2019

Acquired NRG Natural Gas

Natural gas distribution system serving located in Aylmer serving +10,000 connections – in Elgin, Middlesex, Oxford and Norfolk Counties

2017

Ontario Head Office

Located at 55 University Avenue

Toronto ON

2019

Darlington Demineralized �Water Treatment

Design-Build-Finance-Operate the Darlington Demineralized Water Treatment Facility for OPG

2021

Electricity local distribution company serving more than 20,000 residential, commercial and industrial customers in Collingwood, Stayner, Creemore and Thornbury

2018

Acquired Collus-Powerstream LDC

COMMERCIALLY SENSITIVE

4 of 27

Defining the Problem

4

    • Water and wastewater investments carry large risks
      • This type of infrastructure is very expensive for municipalities
      • Uncertain population and economic growth often hinders investment
      • Project risks include design, construction, finance, operations, environmental, regulatory and revenue
      • Political risk exists with the optics of private involvement with municipal water

    • An alternative delivery approach can help municipalities better manage these risks

COMMERCIALLY SENSITIVE

5 of 27

Risk Transfer in Alternative Delivery

5

COMMERCIALLY SENSITIVE

6 of 27

Risk Sharing Example: DBFOM

Risk Transfer: �Through a Single Point of Responsibility all obligations related to the project are met under one project-related proponent or company. The focus is on outcomes delegating the responsibility and risk, related to design, build, operation, or finance, to one entity so that interfaces and integration aspects of the project are not at risk to fall through the gaps due to inter-party communication issues.

Efficiency: �The private sector, due to its commercial mind-set, involvement, flexibility with employee management, and focus on cost effectiveness, can provide a greater level of efficiency in project delivery.

Technology and Know-how: �The public sector often looks to the private sector to provide technology and know-how both in asset development and service delivery. Expertise is not limited to technology but also includes approaches to management and methods of operation and maintenance.

Financing: �Private sector financing, when risk adjusted, is less expensive in most cases.

Cost of Procurement: �The direct cost and efficiency comparison of public versus private finance is difficult to quantify. Based on EPCOR's project experience, there is evidence that 20-40% savings can be realized with private participation through the synergy of a design-build-operate process, risk transfer and cost certainties.

6

COMMERCIALLY SENSITIVE

7 of 27

Risk Sharing Example: DBFOM

7

EPCOR

  • Design Management
  • Technology Selection
  • Design Errors and Omissions
  • Constructability Design
  • Construction Health, Safety, and Environment
  • Construction Management
  • Subcontractor Tendering and Management
  • Construction / Building Permits
  • Material Procurement
  • Equipment Warrantees
  • Construction Schedule
  • Construction Costs
  • Construction Resource Availability
  • Commissioning and Performance Testing
  • Construction Insurance
  • Financing Interest Rates

Shared

  • Overall project delivery
  • Stakeholder and Indigenous Consultant

Municipality

  • Project Scope Changes
  • Political and Stakeholder Management
  • Rate Setting / Revenue Generation
  • Ongoing Operations and Maintenance
  • Force Majeure
  • Changes in Law
  • Ownership of Assets
  • Influent / Effluent Quality
  • Governmental / Environmental Approvals
  • Land Acquisition

COMMERCIALLY SENSITIVE

8 of 27

EPCOR’s ability to manage shared risk

8

    • Over 130 years of experience in allocating technical and commercial risk, navigating unique regulatory and compliance processes
    • Life-cycle focus from initiation of a project with focus on minimizing total cost of ownership
    • Capable of providing fixed O&M costs providing cost certainty
    • O&M risks assumed by EPCOR include but are not limited to:
        • Asset replacement value and durations
        • O&M resourcing including labour relations
        • Supplier/contractor management
        • Consumable (i.e. chemicals, membranes, etc.) sourcing and pricing
    • Ability to transition union employees to EPCOR
    • Capacity building of local personnel, including attaining certifications

COMMERCIALLY SENSITIVE

9 of 27

Case Study 1 | Regina Wastewater Treatment Plant

9

Client

City of Regina

Year

2017 (Final Completion)

Delivery Method

P3 DBFOM

Project Value

Initial Contract Price (Construction only): $158.5M

Total NPV (Construction, O&M, Renewal, Financing, Utilities): $611M

Treatment Capacity

156MLD

Roles of Team Members

EPCOR - Project Lead, Financier & Operator

Aecon - Construction Lead JV

Stantec - Design Lead

Key Treatment Technologies

Vortex grit removal, repurposed primary clarification, new BNR bioreactors, new secondary clarifiers, upgraded fermenter, upgraded mesophilic digestion and a new UV treatment

COMMERCIALLY SENSITIVE

10 of 27

Case Study 1 | Value for Money Analysis in Regina

10

The Regina project experience shows that 20-30% savings can be achieved with private participation through the synergy of the Design Build Finance Operate process including, risk transfer, and cost certainties.

Further, EPCOR can shape the financing to better match customer growth, thus limiting rate increases and minimizing inter-generational inequities.

29.3%

20.1%

COMMERCIALLY SENSITIVE

11 of 27

Case Study 2 | Darlington Demineralize Water Treatment

Client

Ontario Power Generation

Project Dates

Project Start: 2022

Commissioned: Summer 2024

Delivery Method

DBFOM

Project Value

Overall Contract Price: $70M

Treatment Capacity

3MLD

Key Treatment Technologies

Raw water from Lake Ontario is treated to produce the ultra-pure demineralized process water utilized at the nuclear power plant for the purpose of steam production. Technologies include ultrafiltration, reverse osmosis, granular activated carbon, continuous electrodionization and mixed bed polishing.

Other Details

EPCOR is response for all O&M aspects of the facility including staffing, maintenance, major sustaining capital, chemical supply, laboratory analysis, and cyber security.

COMMERCIALLY SENSITIVE

11

12 of 27

Case Study 3 | Britannia Mine Water Treatment Plant

12

Client

Government of BC

Project Value

Overall Contract Price: $25M

Treatment Capacity

7MLD

Delivery Model

P3 DBFOM

Project Dates

2005 - Present

Project Overview

Acid rock drainage from Britannia mine entered the Howe Sound, killing all plant life around the outfall and driving away marine life. Using a fast-track approach, plant upgrades were substantially complete two months ahead of schedule and remove 1.3 million pounds of contaminants annually.

Innovation

Water collected from the mountain above the facility flows through a turbine to supply 70% of the electricity required to power the plant.

COMMERCIALLY SENSITIVE

12

13 of 27

Challenges creating Opportunity

13

    • Water and wastewater investments carry large risks
      • This type of infrastructure is very expensive for municipalities
      • Uncertain population and economic growth often hinders investment
      • Project risks include design, construction, finance, operations, environmental, regulatory and revenue
      • Political risk exists with the optics of private involvement with municipal water

    • An alternative delivery approach can better manage this risk
      • A Design Build Finance Operate & Maintain (DBFOM) approach can transfer risks to the contractor (EPCOR)
      • When risk adjusted over the life of a project, private financing can compete with public funds, and can be amplified with public-private partnerships (P3)
      • A DBFOM project does not have to include giving up municipal ownership

COMMERCIALLY SENSITIVE

14 of 27

Questions

COMMERCIALLY SENSITIVE

15 of 27

15

Decentralized Water & Wastewater Solutions:

Unlocking Scalable, Sustainable Growth for Municipalities

Romina Ferrada

Domain Manager – Decentralized Wastewater

16 of 27

16

Ontario’s Infrastructure Challenge

  • Housing-enabling Infrastructure Gap
  • Aging Centralized Upgrades
  • Significant Investment and Long Lead Times
  • Growing Development Restrictions in Rural Ontario

17 of 27

Centralized vs. Decentralized Water Systems

17

Conventional or Centralized

> 1,000 m3/day

Communal or Decentralized

10 m3/day – 10,000 m3/day

Individual or On-Site

< 10 m3/day

18 of 27

Decentralized Servicing

Residential Development in Frontenac County

INDIVIDUAL SERVICING

COMMUNAL SERVICING

Individual Servicing

EP Block = 10.87 ha

16 Single Detached Lots

Density = 0.94 units/ha

Communal Servicing

EP Block = 14.24 ha

62 Total Units (41 Single Detached Lots & 9 Townhouses Lots)

Density = 4.63 units/ha

18

Development Area = 27.85 ha

19 of 27

Decentralized Wastewater Servicing

Background

Ontario

    • 50 in the last 20 years

Colorado

    • 17 in the last 5 years

19

20 of 27

20

Advantages of Decentralized Systems

  • Enable rural growth without mega-projects
  • Lower upfront and lifecycle costs
  • Lower footprint for infrastructure
  • No single point of failure
  • Faster deployment timelines

21 of 27

The Decentralized Approach

  • Modular treatment units designed for expansion
  • Best available technology
  • Fully monitored with smart tech
  • Designed for compliance and resilience

21

22 of 27

Wastewater

Membrane Bioreactor

Sequencing Batch Reactor

Moving Bed Bioreactors

Potable Water

Filtration

Clarification

Disinfection

Water Treatment

Technologies

22

23 of 27

23

Modular Water Treatment Systems

24 of 27

Overcoming Barriers

Barrier

Solution

Regulatory Complexity

Updates are in progress

Perceived Risk

Proven technologies and municipal models

Capital Constrains

Phased decentralized approach, funding and grants

Lack of Expertise

Operations training, smart monitoring

24

25 of 27

An Innovative Municipal Model

  • Municipally owned utility – to operate and manage the systems

  • Helps municipalities bypass costly upgrades

  • Eliminates the need for developers to enter into Municipal Responsibility Agreements (MRAs) with Municipalities

  • Pioneering decentralized infrastructure in rural Ontario

  • www.frontenacms.ca

Frontenac County Municipal Services Corporation (FMSC)

25

26 of 27

Empower Community Growth Through Innovation

Diversifying Ontario’s Water Strategy

Decentralized Solutions to Complement Centralized Infrastructure an Enable Community Growth

26

Centralized Treatment

Decentralized Treatment

27 of 27

Questions &�Discussion

Romina Ferrada

Domain Manager – Decentralized Wastewater

rferrada@newterra.com

(647) 309-1847

27