TONGYEONG�ANJEONG Industrial Complex Investment proposal
Anjeong Industrial Complex
1 | Business overview & Extension | 3P |
2 | Investment & profit structure | 16P |
3 | Financial operation plan | 27P |
4 | Financial modeling | 32P |
Table of Contents
Anjeong Industrial Complex
Business overview
01
Anjeong Industrial Complex
- 4 -
Business Overview
Project name
Tongyeong Anjeong general industrial complex development business
Project period
2010 ~ 2022 (scheduled)
Project Area
1,304,939㎡ (Approx. 400,000 pyeong)
-Land: 387,492㎡ (Approx. 120,000 pyeong)
-Coastal: 917,447㎡ (Approx. 280,000 pyeong)
Development Company
Anjeong Corporation Co., Ltd
Gyeongsangnam-do Tongyeong-si, Gwangdo-myeong, Anjeong-li
- Port facilities (Wharf): 1.4km
- Front depths: 16m, large vessel can be moored
- Anjeong routes are opened so convenient sea logistics and vessel
entry and exit
- Industrial land: 868,735m2 (262,792 PY)
Project site
Tongyeong
Anjeong National industrial Complex
Anjeong industrial Complex
Dosan-myeon
Gwangdo-myeon
Deokpo industrial Complex (planned)
Main Contents
Anjeong Industrial Complex
- 5 -
Ground plan
Industrial complex land
869,180 ㎡
Background land
436,204 ㎡
Anjeong Industrial Complex
- 6 -
Business schedule & Seal plan
◎ Business schedule
Construction duration : August, 2020 ~ July, 2023 (36 Months)
▷ Phase 1: Offshore civil construction (Wharf & reclamation)
▷ Phase 2: Onshore civil construction (land leveling & subsidiary facilities)
◎ Sales plan
KOGAS: Construction for 20 of 200,000㎘ storage tanks by 2031 according to the 13th long-term natural gas supply and demand plan, and attracting unsettled 10 sets to Anjeong industrial complex (Refer to 13th long-term natural gas supply and demand plan)
▷ Sale area: 396,000 m2 (Around January ~ March, 2020 contract scheduled)
▷ Sale amount: 168,000,000 USD
◎ KRW exchange rate against USD
▷ Please note that the exchange rate in this proposal has been applied to USD 1 as 1,000 KRW for
convenience of calculation.
Anjeong Industrial Complex
- 7 -
Business Progress
October
Anjeong corporation co., Ltd district designation and licensing started
2006
2007
2008
2010
2014
August
Anjeong District Industrial Complex Corporation established
(Joint business agreement: Sungjin Geotech, Gaya Heavy Industries, Anjeong Development and Woori bank)
July
Reflected land reclamation plan issued by government (Ministry of Land, Transport and Maritime Affairs notification 2008-325
September
Applied for Expression of interest of investment (Gyeongsangnam-do)
January
Approval on Industry Complex plan completed (Gyeongsangnam-do Notice 2010-7)
May
Acquired from Sungjin Geotech Co.Ltd. And POSCO Group (POSCO Plantec)
February
Construction contract completed (POSCO PLANTEC: 100,000 pyeong, Gaya heavy industry: 100,000 pyeong) 2/6 and construction commenced (deposit of KRW 2 billion received) 2/20
June
Construction stopped (Rate: 11.86%)
August
First installment (2 billion won from each company) received (8/5)
Anjeong Industrial Complex
- 8 -
Business Progress _ Continued
2016
2017
2018
February
Issued Asset Retirement Obligation Guarantee Securities
Issued letter of commitment of construction completion and expression of interest by financial institutions
Submitted supplementary documents related to industrial plan (amended version) Request for consultation of related organizations according to application for industrial complex plan (amended)
April
Notified of Industrial complex plan (amended) approval
December
Signed a construction contract (STX Construction)
December
Submitted supplementary documents
for industrial complex plan (amended version)
January
Converted to general property sale
December
Applied for business period extension
2020
January
Commencing Anjeong General industrial complex development construction (scheduled)
Anjeong Industrial Complex
- 9 -
Site sale plan
Under consultation
(under consultation)
Residential site (Apartment House)
20,955 m2
(Pre-sale prior to construction)
Support Facility site 39,672m2 (Pre-sale prior to construction)
Parking lot 26,208m2 (Pre-sale prior to construction)
Industrial Complex site: 868,735m2
Industrial site A: Sale under consultation
Industrial site B: Sale under consultation
Anjeong Industrial Complex
- 10 -
Land use plan
Classification | Contents |
Basic direction |
|
| |
|
Classification | Contents |
Industrial complex site |
|
|
Classification | Contents |
Residential site |
|
|
Anjeong Industrial Complex
- 11 -
Land Use Plan _ Continued
Classification | Contents |
Support facilities site |
|
Classification | Contents |
Public facilities site |
|
|
Anjeong Industrial Complex
- 12 -
Classification | Area(m2) | Composition ratio(%) | |
Industrial Complex Site | 867,214 | 66.5 | |
Support Facility Site | 39,603 | 3.0 | |
Residential site | Apartment House | 20,919 | 1.6 |
Residential site | Parking lot | 26,162 | 2.0 |
Public facilities site | Road | 87,010 | 6.7 |
Park | 12,443 | 1.0 | |
Green tract of land | 227,399 | 17.4 | |
Pedestrian road | 600 | 0.1 | |
Waste water treatment plant | 19,362 | 1.5 | |
Water supply facility | 951 | 0.1 | |
Reservoir | 3,276 | 0.3 | |
Sub Total | 351,041 | 26.9 | |
Total | 1,304,939 | 100.0 | |
⊙ Land use plan by Anjeong corporation co., Ltd
Anjeong general industrial complex
Land use plan
Overview of land use planning and facility management & processing plan
Anjeong Industrial Complex
- 13 -
Classification | Supply Area(m2) | Method of disposition | Subject | Remarks | |
Industrial Facility site | 867,214 | Sale | End user | End user 953,898 (73.2%)
| |
Support Facility site | 39,603 | Sale | |||
Residential site | Apartment house | 20,919 | Sale | ||
Residential site | Parking lot | 26,162 | Sale | ||
Public facility site | Green tract of land | 227,399 | Nil cost | Tongyeong city | 351,014 (26.9%) |
Park | 12,443 | Nil cost | Tongyeong city | ||
Pedestrian road | 600 | Nil cost | Tongyeong city | ||
Road | 87,010 | Nil cost | Tongyeong city | ||
Waste water treatment plant | 19,362 | Nil cost (national cost) | Tongyeong city | ||
Water supply facility | 951 | Nil cost | Tongyeong city | ||
Reservoir | 3,276 | Nil cost | Tongyeong city | ||
Sub Total | 351,041 | | | ||
Total | 1,304,939 | | | 1,304,939(100%) | |
Overview of land use planning and facility management & processing plan _ Continued
⊙ Facility Management Plan of the Anjeong corporation co., Ltd
Anjeong Industrial Complex
- 14 -
Site classification | Area (m2) | Remarks |
Industrial facility site | 867,214 | Industrial facilities such as factories |
Support facility site | 39,603 | Industrial Support Facilities |
Residential site | 20,919 | Residential site |
Parking lot | 26,162 | Parking lot |
Private land subtotal | 953,898 | Sale site subtotal |
Public facility site | 351,041 | Public facility site such as green tracts and sewage treatment facilities |
TOTAL | 1,304,939 | |
1. The industrial complex development plan is as follows:
2. The Industrial complex development schedule of the Company is as follows:
Classification | 2020 | 2021 | 2022 ~ 2023 | |||
Submission of project | | | | | | |
Compensation consultation & payment | | | | | | |
Construction start | | | | | | |
Site use | | | | | | |
Site completion | | | | | | |
Project termination | | | | | | |
Complex Development Plan
Anjeong Industrial Complex
- 15 -
Classification | Use area (m2) | Remarks |
Industrial Land A | 495,000 | Sale confirmed (payment to be received within 6 months after the construction has started) |
Industrial Land B | 372,214 | Sale scheduled (payment to be received from mid 2019) |
Support facilities Land | 39,603 | Sale prior to construction |
Housing Land | 20,919 | Sale prior to construction |
Packing Land | 26,162 | Sale prior to construction |
Public facility Land | 351,041 |
|
TOTAL | 1,304,939 |
|
1. The industrial complex land using plan is as follows:
2. Company’s site sale schedule is as follows:
Classification | 2020 | 2021 | 2022 | |||||||||
| 1Q | 2Q | 3Q | 4Q | 1Q | 2Q | 3Q | 4Q | 1Q | 2Q | 3Q | 4Q |
Industrial facility site A | | | | | | | | | | | | |
Industrial facility site B | | | | | | | | | | | | |
Support facility site | | | | | | | | | | | | |
Residential site | | | | | | | | | | | | |
Parking lot | | | | | | | | | | | | |
Industrial Complex Sales Plan
Anjeong Industrial Complex
Investment & Profit structure
2
Anjeong Industrial Complex
- 17 -
Investment amount for Offshore Civil construction
⊙ Estimated amount
Division | Amount(USD) | Ratio | Remarks | |
Input contents | Construction cost | 59,166,910 | 74.0% | Phase 1 construction cost (90% of Designing cost) |
Outsourcing service fee | 1,270,000 | 1.6% | Supervision fee, outsourcing service fee, license fee,… etc | |
Compensation fee | 10,180,000 | 12.7% | Deposit for compensation, compensation management fee | |
Additional fee | 1,717,000 | 2.1% | SPC operation fee, tax fee… etc | |
Reserve fee (others) | 7,666,090 | 9.6% | Reserve | |
Sum of costs already inputted | 80,000,000 | 100.00% |
| |
Division | Rationale | Amount | Ratio | Remarks | |
Contraction cost | Direct cost | Phase 1 construction cost (offshore & Reclamation) | 59,166.91 | 74.0% | Included VAT |
Sub total |
| 59,166,910 | 74.0% |
| |
Outsourcing service fee | Supervision | Supervision fee | 1,020,000 | 1.3% |
|
Design & License | Design changing & permission, License fee | 250,000 | 0.3% |
| |
Sub total |
| 1,270,000 | 1.6% |
| |
Compensation | Compensation | Deposit for fishing right, obstacle, compensation of right | 10,000,000 | 12.5% |
|
compensation management fee | Compensation management fee (Compensation team management fee, appraisal & assessment… etc) | 180,000 | 0.2% |
| |
Sub total |
| 10,180,000 | 12.7% |
| |
Additional fee | SPC operation fee | Labor, management, other operation fee | 240,000 | 0.3% |
|
Tax | Various contributions, deposits, other taxes | 1,477,000 | 1.8% |
| |
Sub total |
| 1,717,000 | 2.1% |
| |
Reserve fee | Payables |
| 5,500,000 | 6.9% | 50% of payables |
Other reserve |
| 2,166,090 | 2.7% |
| |
Sub total |
| 7,666,090 | 9.6% |
| |
TOTAL |
|
| 80,000,000 | 100.0% |
|
⊙ Estimated Input Details
(Ratio: 1USD/ 1,000 KRW)
(Ratio: 1USD/ 1,000 KRW)
Anjeong Industrial Complex
- 18 -
Overview of total project cost
⊙ Summary of total project costs are as follows:
Item | Details | Amount (1,000USD) |
Developing | Field investigation costs, Design in construction, Licensing costs, Cultural properties prospecting survey costs | 8,445 |
Business expense | Construction supervision costs and other service charges | 4,905 |
Compensation fees | Land, Other obstructions | 45,818 |
Fishing right and other | 10,909 | |
Movement, management of other compensation | 1,818 | |
Construction cost | Based on PPS reviewed cost | 211,767 |
Other operation costs | Selling and administrative expenses | 3,636 |
Finance costs | Interest | 16,725 |
TOTAL | 304,050 | |
Anjeong Industrial Complex
- 19 -
Overview of total project costs
⊙ Summary of total project cost
Total Project Cost Input Schedule (Quarterly) (Unit: USD) | |||||||||||||||
| 2020 | 2021 | 2022 | 2023 | |||||||||||
1st quarter | 2nd quarter | 3rd quarter | 4th quarter | 1st quarter | 2nd quarter | 3rd quarter | 4th quarter | 1st quarter | 2nd quarter | 3rd quarter | 4th quarter | 1st quarter | 2nd quarter | ||
Division | Summary | 20/3/31 | 20/6/30 | 20/09/30 | 20/12/31 | 21/3/31 | 21/6/30 | 21/9/30 | 21/12/31 | 22/3/31 | 22/6/30 | 22/9/30 | 22/12/31 | 23/3/31 | 23/6/30 |
Total costs | 304,052,544 | 7,364,355 | 24,300,841 | 30,126,072 | 26,879,000 | 20,834,103 | 39,895,389 | 34,217,372 | 37,925,815 | 24,730,176 | 28,963,123 | 25,631,837 | 1,387,945 | 1,569,026 | 227,491 |
Land compensation cost | 58,547,709 | 4,544,922 | - | 9,090,845 | 3,635,938 | 908,984 | 7,272,876 | 11,181,809 | 16,272,722 | 4,900,916 | 726,988 | - | - | 11,709 | - |
Land cost | 1,006,966 | 65,219 | 372,857 | 111,775 | 74,653 | 37,327 | 37,327 | 37,327 | 74,653 | 37,327 | 18,663 | 55,990 | 55,990 | 18,630 | 9,229 |
Construction cost | 211,767,000 | - | 17,255,711 | 18,534,838 | 19,013,886 | 16,696,656 | 30,758,050 | 21,171,099 | 19,332,917 | 18,114,796 | 26,762,654 | 24,126,393 | - | - | - |
Design costs | 8,455,000 | 455,000 | 3,545,000 | 273,000 | 1,909,000 | 1,364,000 | - | - | - | - | - | - | - | 909,000 | - |
Auditing costs | 3,685,876 | 238,727 | 1,364,796 | 409,138 | 273,259 | 136,630 | 136,630 | 136,630 | 273,259 | 136,630 | 68,315 | 204,945 | 204,945 | 68,191 | 33,782 |
Other expense related to development | 215,993 | 13,989 | 79,977 | 23,976 | 16,013 | 8,007 | 8,007 | 8,007 | 16,013 | 8,007 | 4,003 | 12,010 | 12,010 | 3,996 | 1,980 |
Corporate operating expense | 2,734,000 | 409,461 | 136,738 | 136,738 | 341,844 | 136,738 | 136,738 | 136,738 | 341,844 | 136,738 | 136,738 | 136,738 | 273,475 | 136,738 | 136,738 |
Other expense | 915,000 | 137,036 | 45,763 | 45,763 | 114,406 | 45,763 | 45,763 | 45,763 | 114,406 | 45,763 | 45,763 | 45,763 | 91,525 | 45,763 | 45,763 |
Interest expense | 16,725,000 | 1,500,000 | 1,500,000 | 1,500,000 | 1,500,000 | 1,500,000 | 1,500,000 | 1,500,000 | 1,500,000 | 1,350,000 | 1,200,000 | 1,050,000 | 750,000 | 375,000 | - |
Anjeong Industrial Complex
- 20 -
Sales target
| Sales | Marketing |
2Q of 2020 | Pre-sale before construction | Pricing policy establish Distribution agency company DB and network build Selected as a sales and promotion company |
3Q of 2020 | Start of construction (planned) / Sale start | |
1Q of 2022 | 70% complete sale | Strengthen of Support Facility Partner DB build Corporate cooperation marketing progressing Business presentation, advertising by media |
1Q of 2023 | Completion (planned) / 100% sale completed | Progressing of visitor DB utilization marketing Find of related demand |
Sales target
Anjeong Industrial Complex
- 21 -
Division | Industrial land A | Industrial land B | Support facilities Land | Parking land | Housing land | Total |
Sale area(m2) | 495,000 | 372,214 | 39,603 | 26,162 | 20,919 | 953,898 |
Sale unit price (USD) | 385.7 | 385.7 | 689 | 220 | 551 | 397 |
Sale rate (%) | 100% | 100% | 100% | 100% | 100% | 100% |
Sale price (1000 USD) | 190,910 | 143,616 | 27,273 | 5,727 | 11,546 | 379,072 |
Sale start date | Sale Confirmed | July 01, 2020 | July 01, 2021 | December, 2020 | | |
Sale schedule | Sale Confirmed | Sale Confirmed | Best Competitive Bidding (Individuals, Corporations) | | ||
Sake income model
Industrial land sales plan
① Energy-related company (under sale discussion)
Sales area – Stage 1: 66,000 m2 (Expected to be contracted in July 2020)
Stage 2: 330,000 m2 (Expected to be used for stage 1, 2)
Input cost – Stage 1: 121 million USD (Including facility funds) (Sales amount: 28 Million USD)
Stage 2: 717.4 million USD (Including facility funds) (Sales amount: 130 Million USD)
② KOGAS: 10 of 200,000 kl storage tank (13th long-term natural gas supply and demand plan )
Sales area – 396,000m2 (Contract planned around January-March in 2020)
Input fund – Around 1.0 billion USD (Included facility fund) (Sales amount: 192 million USD)
Anjeong Industrial Complex
- 22 -
Sales income flow
Input date | Industrial land A | Industrial land B | Support facilities Land | Parking land | Housing land | Total |
March 31, 2020 | | | | | 545.5 | 546 |
June 30, 2020 | | | | | 1,636.4 | 1,636 |
September 30, 2020 | 19,090.9 | | | | | 19,091 |
December 31, 2020 | | | | | | - |
January 31, 2021 | 38,181.8 | | | | | 38,182 |
June 30, 2021 | | 28,717.3 | | | | 28,717 |
September 30, 2021 | 38,181.8 | | | | | 38,182 |
December 31, 2021 | | 43,090.9 | | | | 43,091 |
March 31, 2022 | 38,181.8 | | | | | 38,182 |
June 30, 2122 | | 43,090.9 | | | | 43,091 |
September 30, 2022 | 38,181.8 | | | | | 38,182 |
December 31, 2022 | | | 19,090.9 | 2,727.3 | | 21,818 |
March 31, 2023 | 19,090.9 | 28,717.3 | 8,181.8 | 3,000 | 9,363.6 | 68,354 |
Total | 190,909 | 143,545 | 27,273 | 5,727 | 11,545 | 379,071 |
Anjeong Industrial Complex
- 23 -
Sales income flow
Anjeong Industrial Complex
- 24 -
Time | Borrowing | Property Sales | Total |
June 30, 2020 | 100,000,000 |
| 100,000,000 |
September 30, 2020 |
| 545,500 | 545,500 |
December 31, 2020 |
| 1,636,400 | 1,636,400 |
January 31, 2021 |
| 19,090,900 | 19,090,900 |
June 30, 2021 |
| - | - |
September 30, 2021 |
| 38,181,800 | 38,181,800 |
December 31, 2021 |
| 28,717,300 | 28,717,300 |
March 31, 2022 |
| 38,181,800 | 38,181,800 |
June 30, 2122 |
| 43,090,900 | 43,090,900 |
September 30, 2022 |
| 38,181,800 | 38,181,800 |
December 31, 2022 |
| 43,090,900 | 43,090,900 |
March 31, 2023 |
| 38,181,800 | 38,181,800 |
June 30, 2023 |
| 21,818,200 | 21,818,200 |
September 30, 2023 |
| 68,353,600 | 68,353,600 |
Total | 100,000,000 | 379,070,900 | 479,070,900 |
Financing plan
Anjeong Industrial Complex
- 25 -
Initial investment borrowing fund exit structure
Commencement of Anjeong industrial complex
Completion of phase 1 offshore civil construction (Reclamation)
Completion of Phase 2 onshore civil construction
Repayment after loan by bank after land registration
Transferable mortgage: Less than 30% of the estimated value.
Preliminary Appraisal Price of Industrial land: 509 USD / m2
Industrial land area: 867,900m2
Preliminary Appraisal Price for Industrial land: 867,900 X 509 USD = Around 약 441,761,000 USD (Total)
Transferable mortgage amount = 441 billion USD X 25% = Around 110 million USD
After the completion of the phase-1 of civil construction work in the first stage of the project (completed reclamation), the initial investment fund can be repaid through a transferable mortgage loan.
Anjeong Industrial Complex
- 26 -
Repayment time | Borrowing | Repayment | Financial costs | Balance |
June 30, 2020 | 100,000,000 | | | 100,000,000 |
September 30, 2020 | | | 1,500,000 | 100,000,000 |
December 31, 2020 | | | 1,500,000 | 100,000,000 |
January 31, 2021 | | | 1,500,000 | 100,000,000 |
June 30, 2021 | | | 1,500,000 | 100,000,000 |
September 30, 2021 | | | 1,500,000 | 100,000,000 |
December 31, 2021 | | | 1,500,000 | 100,000,000 |
March 31, 2022 | 차입금 대환 | | 1,500,000 | 100,000,000 |
June 30, 2122 | | 10,000,000 | 1,500,000 | 90,000,000 |
September 30, 2022 | | 10,000,000 | 1,350,000 | 80,000,000 |
December 31, 2022 | | 10,000,000 | 1,200,000 | 70,000,000 |
March 31, 2023 | | 20,000,000 | 1,050,000 | 50,000,000 |
June 30, 2023 | | 25,000,000 | 750,000 | 25,000,000 |
September 30, 2023 | | 25,000,000 | 375,000 | - |
Total | 100,000,000 | 100,000,000 | 16,725,000 | |
Debt repayment plan
Anjeong Industrial Complex
Fund Management plan
3
Anjeong Industrial Complex
- 28 -
Usage time | Compensation Cost | Cost of construction | Investigation and design | Additional cost | Financial costs | Other costs | Total |
June 30, 2020 | 4,545 | | 455 | 318 | 1,500 | 545 | 5,864 |
September 30, 2020 |
| 17,254 | 3,545 | 1,818 | 1,500 | 182 | 24,300 |
December 31, 2020 | 9,091 | 18,533 | 273 | 545 | 1,500 | 182 | 30,123 |
January 31, 2021 | 3,636 | 19,012 | 1,909 | 364 | 1,500 | 455 | 25,876 |
June 30, 2021 | 909 | 16,695 | 1,364 | 182 | 1,500 | 182 | 20,832 |
September 30, 2021 | 7,273 | 30,755 | | 182 | 1,500 | 182 | 39,891 |
December 31, 2021 | 11,182 | 21,169 | | 182 | 1,500 | 182 | 34,214 |
March 31, 2022 | 16,273 | 19,331 | | 364 | 1,500 | 455 | 37,922 |
June 30, 2122 | 4,901 | 18,113 | | 182 | 1,350 | 182 | 24,088 |
September 30, 2022 | 727 | 26,760 | | 91 | 1,200 | 182 | 29,110 |
December 31, 2022 | | 24,124 | | 273 | 1,050 | 182 | 26,233 |
March 31, 2023 | | | | 273 | 750 | 364 | 1,686 |
June 30, 2023 |
| | 909 | 91 | 375 | 182 | 2,295 |
September 30, 2023 | 11 | | | 45 | | 182 | 602 |
Total | 58,548 | 211,767 | 8,455 | 4,909 | 16,725 | 3,636 | 304,037 |
Fund using plan
Anjeong Industrial Complex
- 29 -
Flow of funds
| 2020 | 2021 | ||||||
Division | 2Q | 3Q | 4Q | 1Q | 2Q | 3Q | 4Q | |
Revenue | Capital |
|
|
|
|
|
|
|
Industrial complex A |
|
|
| 19,091 |
| 38,182 |
| |
Industrial complex B |
|
|
|
|
|
| 28,717 | |
Residential site |
| 546 | 1,636 |
|
|
|
| |
Support facility site |
|
|
|
|
|
|
| |
Parking lot |
|
|
|
|
|
|
| |
Borrowing | 100,000 |
|
|
|
|
|
| |
Total | 100,000 | 546 | 1,636 | 19,091 | 0 | 38,182 | 28,717 | |
Input | Compensation cost | 4,545 |
| 9,091 | 3,636 | 909 | 7,273 | 11,182 |
Cost of construction |
| 17,254 | 18,533 | 19,012 | 16,695 | 30,755 | 21,169 | |
Investigation and design | 455 | 3,545 | 273 | 1,909 | 1,364 |
|
| |
Additional cost | 318 | 1,818 | 545 | 364 | 182 | 182 | 182 | |
Financial costs |
| 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | 1,500 | |
Other expenses such as operating expenses | 545 | 182 | 182 | 455 | 182 | 182 | 182 | |
Debt repayment |
|
|
|
|
|
|
| |
Total | 5,863 | 24,299 | 30,124 | 26,876 | 20,832 | 39,892 | 34,215 | |
Balance | 94,137 | -23,753 | -28,488 | -7,785 | -20,832 | -1,710 | -5,498 | |
Anjeong Industrial Complex
- 30 -
Flow of funds _ Continued
* To expenditure in the form of dividends, including clearing dividends
| 2022 | 2023 | Total | ||||||
Division | 1Q | 2Q | 3Q | 4Q | 1Q | 2Q | 3Q | ||
Revenue | Capital |
|
|
|
|
|
|
|
|
Industrial complex A | 38,182 |
| 38,182 |
| 38,182 |
| 19,091 | 190,910 | |
Industrial complex B |
| 43,091 |
| 43,091 |
|
| 28,717 | 143,616 | |
Residential site |
|
|
|
|
|
| 9,364 | 11,546 | |
Support facility site |
|
|
|
|
| 19,091 | 8,182 | 27,273 | |
Parking lot |
|
|
|
|
| 2,727 | 3,000 | 5,727 | |
Borrowing |
|
|
|
|
|
|
| 100,000 | |
Total | 38,182 | 43,091 | 38,182 | 43,091 | 38,182 | 21,818 | 68,354 | 479,072 | |
Input | Compensation cost | 16,273 | 4,901 | 727 | |
| 11 |
| 58,548 |
Cost of construction | 19,331 | 18,113 | 26,760 | 24,124 |
|
|
| 211,746 | |
Investigation and design |
|
|
|
|
| 909 |
| 8,455 | |
Additional cost | 364 | 182 | 91 | 273 | 273 | 91 | 45 | 4,910 | |
Financial costs | 1,500 | 1,500 | 1,350 | 1,200 | 1,050 | 750 | 375 | 16,725 | |
Other expenses such as operating expenses | 455 | 182 | 182 | 182 | 364 | 182 | 182 | 3,639 | |
Debt repayment |
| 10,000 | 10,000 | 10,000 | 20,000 | 25,000 | 25,000 | 100,000 | |
Total | 37,923 | 34,878 | 39,110 | 37,779 | 21,687 | 26,943 | 25,602 | 404,023 | |
Balance | 259 | 8,213 | -928 | 7,312 | 16,495 | -5,125 | 42,752 | 75,049 | |
Anjeong Industrial Complex
31
Project Master Plan
Anjeong Industrial Complex
Financial Modeling
4
Anjeong Industrial Complex
- 33 -
Financial modeling
⊙ The annual financial statement of the company for each business year are as follows:
1. Statement of financial position | | | | | (Unit: USD) |
| 2020 | 2021 | 2022 | 2023 | 2024 |
Division | 20/12/31 | 21/12/31 | 22/12/31 | 23/12/31 | 24/12/31 |
Asset |
|
|
|
|
|
Ⅰ. Current Asset | 109,417,678 | 158,362,395 | 81,532,245 | 1,125,000 | 1,125,000 |
(1) Quick Asset | 32,619,688 | 38,012,311 | 30,380,935 | 1,125,000 | 1,125,000 |
1. Cash and cash equivalents | 31,119,688 | 36,512,311 | 28,880,935 | - | - |
2. DSRA (Interest hold account) | 1,500,000 | 1,500,000 | 1,500,000 | 1,125,000 | 1,125,000 |
(2) Inventory | 76,797,990 | 120,350,084 | 51,151,310 | - | - |
1. Land | 16,950,541 | 35,492,201 | 10,920,797 | - | - |
2. Construction in progress | 59,847,449 | 84,857,883 | 40,230,514 | - | - |
Total asset | 109,417,678 | 158,362,395 | 81,532,245 | 1,125,000 | 1,125,000 |
Liability |
|
|
|
|
|
Ⅰ. Current Liability | 15,266,869 | 56,742,294 | 10,981,039 | - | - |
1. Sales advance received | 15,266,869 | 53,464,857 | 1,410,756 | - | - |
2. Income tax payable | 0 | 3,277,436 | 9,570,283 | - | - |
Ⅱ. Non-current Liability | 100,000,000 | 90,000,000 | 25,000,000 | - | - |
1. Unsubordinated loans | 100,000,000 | 90,000,000 | 25,000,000 | - | - |
Total liability | 115,266,869 | 146,742,294 | 35,981,039 | - | - |
Equity |
|
|
|
|
|
Ⅰ. Capital stocks | - | - | - | - | - |
1. Capital common stock | - | - | - | - | - |
Ⅱ. Earned surplus | (5,849,191) | 11,620,102 | 45,551,206 | (23,875,000) | (23,875,000) |
1. Earned surplus reserve | - | - | - | - | - |
2. Retained earnings before disposal | (5,849,191) | 11,620,102 | 45,551,206 | (23,875,000) | (23,875,000) |
Total equity | (5,849,191) | 11,620,102 | 45,551,206 | (23,875,000) | (23,875,000) |
Total liability and equity | 109,417,678 | 158,362,395 | 81,532,245 | (23,875,000) | (23,875,000) |
Anjeong Industrial Complex
- 34 -
Financial modeling
⊙ The company’s annual estimated income statement for each business year is as follows:
2. Income Statement | | | | | (Unit: USD) |
|
| 2020 | 2021 | 2022 | 2023 |
Division | Total | 20/12/31 | 21/12/31 | 22/12/31 | 23/12/31 |
Sales | 379,311,664 | 6,023,087 | 110,067,314 | 193,413,243 | 69,808,020 |
Cost of sales | 283,678,544 | 4,504,529 | 82,316,834 | 144,649,354 | 52,207,827 |
Gross sales profit | 95,633,120 | 1,518,558 | 27,750,480 | 48,763,889 | 17,600,194 |
Selling and administrative expenses | 3,649,000 | 1,367,748 | 1,003,751 | 912,501 | 365,000 |
Operating profit | 91,984,120 | 150,809 | 26,746,729 | 47,851,388 | 17,235,193 |
Non-operating income | - | - | - | - | - |
Non-operating expense (Including operating interest expense) | 16,725,000 | 6,000,000 | 6,000,000 | 4,350,000 | 375,000 |
Income and loss before income taxes | 75,259,120 | (5,849,191) | 20,746,729 | 43,501,388 | 16,860,193 |
Corporate Taxes | 16,556,940 | - | 3,277,436 | 9,570,283 | 3,709,221 |
Net Income | 58,702,179 | (5,849,191) | 17,469,292 | 33,931,105 | 13,150,973 |
Anjeong Industrial Complex
- 35 -
Financial modeling
⊙ The annual cash flow statement of the company for each business year is as follows:
3. Cash flow statement | | | | | (Unit: USD) |
|
| 2020 | 2021 | 2022 | 2023 |
Division | Total | 20/12/31 | 21/12/31 | 22/12/31 | 23/12/31 |
Ⅰ. Cashflows from operating activities | 58,702,179 | (67,380,312) | 15,392,623 | 57,368,624 | 53,321,244 |
1. Cash inflows from operating activities | 379,311,664 | 21,289,956 | 148,265,302 | 141,359,141 | 68,397,265 |
A. Cash inflows from sales proceeds | 379,311,664 | 21,289,956 | 148,265,302 | 141,359,141 | 68,397,265 |
2. Cash outflows from operating activities | 320,609,485 | 88,670,268 | 132,872,679 | 83,990,517 | 15,076,021 |
A. Land Costs | 58,547,709 | 17,271,705 | 35,636,391 | 5,627,904 | 11,709 |
B. Land charge | 1,006,966 | 624,504 | 186,633 | 167,970 | 27,859 |
C. Composition cost | 224,123,869 | 63,406,310 | 90,045,904 | 69,654,706 | 1,016,949 |
D. General maintenance expenses | 2,734,000 | 1,024,780 | 752,057 | 683,688 | 273,475 |
E. Other expenses | 915,000 | 342,968 | 251,694 | 228,813 | 91,525 |
F. Interest expenses | 16,725,000 | 6,000,000 | 6,000,000 | 4,350,000 | 375,000 |
G. Corporate taxes | 16,556,940 | - | - | 3,277,436 | 13,279,504 |
Ⅱ. Cashflows from investing activities | - | - | - | - | - |
Ⅲ. Cashflows from financing activities | (58,702,179) | 98,500,000 | (10,000,000) | (65,000,000) | (82,202,179) |
1. Cash inflows from financing activities | 125,375,000 | 100,000,000 | - | - | 25,375,000 |
A. Increase in unsubordinated loans | 100,000,000 | 100,000,000 | - | - | - |
B. Decrease in loan redemption account | 25,000,000 | - | - | - | 25,000,000 |
C. Decrease in account for construction cost | - | - | - | - | - |
D. Decrease in DSRA | 375,000 | - | - | - | 375,000 |
E. Capital increase with consideration | - | - | - | - | - |
2. Cash outflows from financing activities | 184,077,179 | 1,500,000 | 10,000,000 | 65,000,000 | 105,577,179 |
A. Unsubordinated Loan Return | 100,000,000 | - | 10,000,000 | 65,000,000 | 25,000,000 |
B. Increase in DSRA | 1,500,000 | 1,500,000 | - | - | - |
C. Increase in Dividends | 82,577,179 | - | - | - | 82,577,179 |
Ⅳ. Changes in Cash | - | 31,119,688 | 5,392,623 | (7,631,376) | (28,880,935) |
Ⅴ. Beginning Balance of Cash |
| 57,998,688 | 41,335,745 | 33,440,120 |
|
Ⅵ. Ending Balance of Cash |
| 31,119,688 | 36,512,311 | 28,880,935 | - |
Anjeong Industrial Complex
- 36 -
Financial modeling
⊙ The estimated annual number of funds for each business year is as follows:
4. Funds receipts and disbursement | | | | | (Unit: USD) |
|
| 2020 | 2021 | 2022 | 2023 |
Division | Total | 20/12/31 | 21/12/31 | 22/12/31 | 23/12/31 |
Cash Inflows | 504,686,664 | 121,289,956 | 148,265,302 | 141,359,141 | 93,772,265 |
Income from sales | 379,311,664 | 21,289,956 | 148,265,302 | 141,359,141 | 68,397,265 |
Industrial complex site A | 191,070,000 | 19,107,000 | 76,428,000 | 76,428,000 | 19,107,000 |
Industrial complex site B | 143,674,604 | - | 71,837,302 | 43,102,381 | 28,734,921 |
Support facility site | 44,567,060 | 2,182,956 | - | 21,828,760 | 20,555,344 |
Decrease in Loan redemption account | 25,000,000 | - | - | - | 25,000,000 |
Decrease in account for the construction cost | - | - | - | - | - |
Decrease in DSRA | 375,000 | - | - | - | 375,000 |
Unsubordinated Loan Procurement | 100,000,000 | 100,000,000 | - | - | - |
Cash Outflows | 504,686,664 | 90,170,268 | 142,872,679 | 148,990,517 | 122,653,200 |
Total expense | 304,052,544 | 88,670,268 | 132,872,679 | 80,713,081 | 1,796,517 |
A. Land costs | 58,547,709 | 17,271,705 | 35,636,391 | 5,627,904 | 11,709 |
B. Land charges | 1,006,966 | 624,504 | 186,633 | 167,970 | 27,859 |
C. Composition costs | 224,123,869 | 63,406,310 | 90,045,904 | 69,654,706 | 1,016,949 |
D. General maintenance expense | 2,734,000 | 1,024,780 | 752,057 | 683,688 | 273,475 |
E. Other expense | 915,000 | 342,968 | 251,694 | 228,813 | 91,525 |
F. Interest expense | 16,725,000 | 6,000,000 | 6,000,000 | 4,350,000 | 375,000 |
Corporate tax expense | 16,556,940 | - | - | 3,277,436 | 13,279,504 |
Increase in DSRA | 1,500,000 | 1,500,000 | - | - | - |
Unsubordinated Loan Return | 100,000,000 | - | 10,000,000 | 65,000,000 | 25,000,000 |
Dividends (Including Liquidation Dividends) | 82,577,179 | - | - | - | 82,577,179 |
Cash flows (Current) | 0 | 31,119,688 | 5,392,623 | (7,631,376) | (28,880,935) |
Accumulated Cash flows | 36,512,311 | 31,119,688 | 36,512,311 | 28,880,935 | 0 |
Anjeong Industrial Complex
Thank you
Anjeong Industrial Complex