SAP Enterprise Asset Management
Plant Maintenance
(SAP S/4 HANA On Premise 2023)
S/4HANA 2023
Perform Emergency Maintenance
(Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
Create a simplified malfunction report for T-PA17.
Notification
10000091
Notification#10000091
Order#4000228
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
Navigate to Job Details > Work
Choose Edit
Set the Planned Effort to 3 Hour
Auto Assign to User who create the Malfunction Report but can be changed
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
In the screen Parts add material to this work item via button “Add”
T-PM1000 is the Construction type (Material BOM) assigned to the Equipment T-PA17
T-PM2400 is check with Available Stock
T-PM2400 is check with Available Stock
click ADD
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
At the top right choose Release
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
At the work item level use the drop-down list and choose In Process
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
Message indicate Notification created via the FIORI App
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
Book a goods issue for the planned material item.
Choose group Purchasing/Warehousing/Accounting
Start app Post Goods Movement
Choose Goods Issue / Order and enter your order number
Scroll to bottom of page and set the OK flag and assign storage location 101A.
and Choose Post
Material Document created
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
Navigate back to Corrective Maintenance and choose Repair Malfunction - My Job List and open your malfunction report.
In screen area Job Details >Work from the drop-down list choose Work is Done
then
choose newly created option Record Time
Check the Actual Effort and set flag Final Confirmation and choose SAVE
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
GI Material Doc &
Confirmation Doc
“Find Maintenance Orders” Fiori App and filter by the Order#
click on short text and then select “Change Maintenance Order”
Check the Document Flow
GI Material Doc &
Confirmation Doc
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
Let’s “Complete” TECO the Notification/Order
Note Overall Status is “Work is Done” on the Process Malfunction Report
choose “Complete” to TECO
Note Overall Status is “Work Completed” on the Process Malfunction Report
click on the Order short text then select “Change Maintenance Order”
Technically Completed (TECO) status
click on the Notification
the “Complete” Malfunction Report step
DID not
update status in the Notifications which is still
NOPR (Notification in Process) status
S/4HANA Perform Emergency Maintenance (Malfunction Report)
S/4HANA Perform Emergency Maintenance (Malfunction Report)
Let’s “Close” NOCO the Notification/Order
click “Close Report” which will set “NOCO” status to the Notification
Overall Status now EMPTY
click on the Order short text then select “Change Maintenance Order”
Technically Completed (TECO) status updated in the “Complete” step earlier
click on the Notification
the “Close Report” Malfunction Report step
update
the Notification
to “NOCO” status (Notification Complete)