Goochland County Public Schools�

Capital Improvement Plan Draft

School Board Meeting

Nov. 9, 2021

1

2 of 19

Basis of Capital Improvement Plan

  1. Address capital needs of the School division so that school buildings remain inviting, safe, and comfortable for students and staff
  2. Build off of previous years where possible but when new information arises (such as the Dewberry Facility Assessment study this year and/or updated long-term economic information) the plan may be significantly modified to address School needs
  3. Present full capital costs of projects, including industry-standard contingencies, so that there are few surprises when projects are started
  4. Support the ENGAGE 20/26 Strategic Plan to “exceed indoor environmental quality standards”, “maintain and create sustainable facilities and equipment”, and “create flexible learning spaces.”

2

3 of 19

10 Year CIP Approval - SB 12/8/2020

650 student with 50 student preschool wing - new GES school.

3

4 of 19

10 Year CIP Approval - BOS 4/20/2021

Board of Supervisors moved the GHS projects out by one year and moved BES and RES land purchase and new school construction out of the 10 year window (BES FY2034 and RES FY2039)

4

5 of 19

Retained HBA Engineering Capital Cost Model

for all large projects

  • HBA model is being used by the County for their projects (two 5% contingencies on hard costs plus industry standard soft costs)
  • Last year model: Construction variable

inflation from Market Watch (Oct. 2020)

  • Square footage cost based on 2020 VDOE statewide construction costs and reviewed by HBA for GES - increase from $262.50/sf to $282/sf. School site increased to 25 acres.
  • Current model - no change for 2022 projects; changed all other projects to 5% inflation model (currently preferred by capital planners) and inflated to County-approved project year. Complete set of capital cost worksheets

5

6 of 19

HBA Capital Cost Model for new construction at GHS - CTE Addition, Auxiliary Gym, Wrestling Room, General renovations for CTE/Fine Arts (FY 2025*)

2018 2024/25 (last yr) 2025/26

30,000 sf CTE Addition $9,750,000 → $13,202,933 → $14,479,058

10,000 sf Auxiliary Gym $2,500,000 → $ 3,705,179 → $ 4,032,758

3,000 sf Wrestling Room $ 750,000 → $ 1,111,554 → $ 1,209,827

General Renovations (fine arts) $1,372,712 → $ 2,042,628 → $ 2,223,219

Total new HS additions/general renovations $21,944,862

*County moved this to FY2025. New GCPS recommended timeframe: FY2024 Engineering, FY2025/26 bid and construction. Higher costs due to 5% annual inflation, added year, and addition of project manager and commissioning.

6

7 of 19

HBA Capital Cost Model for C-143 renovations at GHS (FY 2026)*

2018 2025 (Last year) 2026

C-143 Renovation estimate $1,038,090 → $1,621,938 → $1,765,335

*County moved this to FY2026; new GCPS recommended timeframe: FY2024 Engineering, FY2026 bid/construction. Higher costs due to 5% annual inflation and added year.

7

8 of 19

HBA Capital Cost Model for new HS Fields, field house (FY 2028)*

2018 2028 (Last year) 2028/29

New fields (artificial turf, new

soccer/lacrosse practice fields) $1,038,090 → $2,893,668 → $2,893,668

NEW NEED: Expanded field house space

(use Wrestling room as cost model)** n/a n/a $1,400,526

Total fields/field house renovations $4,294,194

*County kept this at FY2028; new GCPS recommended timeframe: FY2024 Engineering**, FY2028 bid and construction.

8

9 of 19

Recommended Capital Costs in Future Modeling

  • Project Manager and Commissioning Services on all major construction/ renovation projects - 4% of construction cost
    1. Added almost $1 Million to GHS Renovation/Addition Projects (FY2024)
  • Demolition/Renovation costs when a building is no longer used as a school - placeholder values and years
    • GES - County has $2M in their FY2025 Facility CIP for Human Services/School Admin renov.
    • $500K (G Tech/ECSE) - FY2028
    • $1M (BES) - FY2036
    • $1.5M (RES) - FY2042

9

10 of 19

Capital Maintenance Pool - single HVAC unit replacements, sidewalks, painting schedule, plumbing, well repairs

10

School

FY2023

FY2024

FY2025

FY2026

FY2027

BES

$50,000

$50,000

$50,000

$50,000

$50,000

GES/ECSE

0

0

New Building

50,000

50,000

RES

50,000

50,000

50,000

50,000

50,000

GMS

75,000

75,000

100,000

100,000

100,000

GHS

75,000

75,000

75,000

75,000

75,000

All facilities

$250,000

$250,000

$275,000

$325,000

$325,000

11 of 19

Capital Technology/Security Pool - cameras, door access, Promethean boards/projectors

11

School

FY2023

FY2024

FY2025

FY2026

FY2027

BES

$25,000

$25,000

$25,000

$25,000

RES

25,000

25,000

25,000

25,000

GMS

$50,000*

50,000*

25,000

25,000

25,000

GHS

25,000

25,000

25,000

25,000

25,000

All facilities

$75,000

$125,000

$100,000

$100,000

$100,000

*Promethean Board replacement project

12 of 19

Randolph ES Renovation Projects

12

Project

FY2023

FY2024

FY2025

FY2026

FY2027

Aging Kitchen equipment replacement*

$59,220

$67,461

$70,834

Replace all building lights with LED and upgrade lighting controls*

$161,406

$169,476

177,950

Replace needed electrical panels and switchgear in 1958 section/transformer*

298,006

Renovate Boys & Girls Restrooms at main entrance to current code and ADA requirements/new tile & drainage*

264,865

Roof repairs - oldest sections*

153,762

246,067

Furniture refresh

300,000

Playing fields refresh

50,000

Total

$59,220

$724,277

$219,476

$699,173

$316,901

*As recommended in Dewberry Engineering study, October 2021 (Total $2,019,047)

13 of 19

Byrd ES Renovation Projects

13

Project

FY2023

FY2024

FY2025

FY2026

FY2027

Aging Kitchen equipment replacement

$80,339

$84,356

Replace all building lights with LED/upgrade lighting controls - start 3 year phase-in*

$161,747

Replace needed electrical panels and switchgear in 1958 section/transformer*

$202,970

Renovate Boys & Girls Restrooms at main entrance to current code and ADA requirements/new tile & drainage*

278,108

Roof repairs - oldest sections*

321,357

82,776

Furniture refresh

300,000

Replace failing windows/refinish gym floor*

55,062

43,266

Total

$202,970

$401,696

$800,302

$205,013

*As recommended in Dewberry Engineering study, October 2021 (Total $1,609,982)

14 of 19

Miscellaneous Special Projects

14

School/facility project

FY2023

FY2024

FY2025

FY 2026

FY2027

GMS Video camera replacements**

$302,479

GMS carpet and tile replacements

$100,000

57,443

GMS playing field upgrade

$50,000

Bus Garage projects*

$51,931

$82,694

Bus & vehicle purchases (one each)

110,250

115,763

156,279

164,093

172,298

All other facilities

$162,181

$165,763

$238,973

$264,093

$532,220

*Window and HVAC replacements (FY2023); plumbing, security, and front lot paving (FY 2025)

**As recommended by Dewberry Engineering, October 2021

15 of 19

Goochland HS Renovation Projects

15

Project

FY2023

FY2024

FY2025

FY2026

FY2027

Replace kitchen equipment*

$125,906

$132,201

$138,811

$145,751

Tile replacement

100,000

HVAC system upgrades*

$1,153,906

2,376,623

2,922,154

523,032

1,138,571

Athletic department upgrades

40,000

40,000

40,000

60,000

40,000

Upgrade generator transfer switches; replace video cameras*

304,511

310,775

Replace all building lights with LED and upgrade lighting controls*

215,015

225,766

237,054

248,907

Total

$1,193,906

$3,062,055

$3,320,121

$1,058,897

$1,884,004

*As recommended by Dewberry Engineering, October 2021 (Total $11,018,981)

16 of 19

HVAC projects changes from last year:

16

Projects

FY2023

FY2024

FY2025

FY2026

FY2027

Total

Last year COVID-19 funding allowed us to spend over $1M in proactive HVAC projects at RES and GES. These facilities may not need HVAC equipment replacement during their remaining life. Staff knew equipment replacement was needed at 20 year old GHS but thought that it could be handled in-house as each piece of equipment failed with minimal upgrades needed.

Schools division -wide

$100,000

100,000

200,000

200,000

100,000

$700,000

The Dewberry Engineering study* pointed out the need to be proactive on all equipment replacement, especially equipment that had a school-wide impact and could shut the school down.

GMS equipment will need $4,547,341 in replacements starting in 2028, as GMS reaches its 20th year.

GHS HVAC system upgrades*

$1,153,906

2,376,623

2,922,154

523,032

1,138,571

$8,114,285

Year over Year Difference

$7,414,285

*As recommended by Dewberry Engineering, October 2021 (Total $11,018,981)

17 of 19

10 Year CIP Draft - SB 11/9/2021

17

18 of 19

30 Year CIP Draft - SB 11/9/2021

18

19 of 19

Next Steps

  • December 2021: 30-year CIP adopted by School Board
  • Jan/Feb 2022: Joint Board of Supervisors/School Board CIP discussions
  • Feb/Mar 2022: Board of Supervisors presents county-wide CIP for public hearing
  • April 2022: Board of Supervisors adopts 25-year CIP (FY2023 appropriated, FY 2024-2027 funded; FY2028-2047 information only for proffer analysis and capital planning)

Any questions?