Goochland County Public Schools�
Capital Improvement Plan Draft
School Board Meeting
Nov. 9, 2021
1
Basis of Capital Improvement Plan
2
10 Year CIP Approval - SB 12/8/2020
650 student with 50 student preschool wing - new GES school.
3
10 Year CIP Approval - BOS 4/20/2021
Board of Supervisors moved the GHS projects out by one year and moved BES and RES land purchase and new school construction out of the 10 year window (BES FY2034 and RES FY2039)
4
Retained HBA Engineering Capital Cost Model
for all large projects
inflation from Market Watch (Oct. 2020)
5
HBA Capital Cost Model for new construction at GHS - CTE Addition, Auxiliary Gym, Wrestling Room, General renovations for CTE/Fine Arts (FY 2025*)
2018 2024/25 (last yr) 2025/26
30,000 sf CTE Addition $9,750,000 → $13,202,933 → $14,479,058
10,000 sf Auxiliary Gym $2,500,000 → $ 3,705,179 → $ 4,032,758
3,000 sf Wrestling Room $ 750,000 → $ 1,111,554 → $ 1,209,827
General Renovations (fine arts) $1,372,712 → $ 2,042,628 → $ 2,223,219
Total new HS additions/general renovations $21,944,862
*County moved this to FY2025. New GCPS recommended timeframe: FY2024 Engineering, FY2025/26 bid and construction. Higher costs due to 5% annual inflation, added year, and addition of project manager and commissioning.
6
HBA Capital Cost Model for C-143 renovations at GHS (FY 2026)*
2018 2025 (Last year) 2026
C-143 Renovation estimate $1,038,090 → $1,621,938 → $1,765,335
*County moved this to FY2026; new GCPS recommended timeframe: FY2024 Engineering, FY2026 bid/construction. Higher costs due to 5% annual inflation and added year.
7
HBA Capital Cost Model for new HS Fields, field house (FY 2028)*
2018 2028 (Last year) 2028/29
New fields (artificial turf, new
soccer/lacrosse practice fields) $1,038,090 → $2,893,668 → $2,893,668
NEW NEED: Expanded field house space
(use Wrestling room as cost model)** n/a n/a $1,400,526
Total fields/field house renovations $4,294,194
*County kept this at FY2028; new GCPS recommended timeframe: FY2024 Engineering**, FY2028 bid and construction.
8
Recommended Capital Costs in Future Modeling
9
Capital Maintenance Pool - single HVAC unit replacements, sidewalks, painting schedule, plumbing, well repairs
10
School | FY2023 | FY2024 | FY2025 | FY2026 | FY2027 |
BES | $50,000 | $50,000 | $50,000 | $50,000 | $50,000 |
GES/ECSE | 0 | 0 | New Building | 50,000 | 50,000 |
RES | 50,000 | 50,000 | 50,000 | 50,000 | 50,000 |
GMS | 75,000 | 75,000 | 100,000 | 100,000 | 100,000 |
GHS | 75,000 | 75,000 | 75,000 | 75,000 | 75,000 |
All facilities | $250,000 | $250,000 | $275,000 | $325,000 | $325,000 |
Capital Technology/Security Pool - cameras, door access, Promethean boards/projectors
11
School | FY2023 | FY2024 | FY2025 | FY2026 | FY2027 |
BES | | $25,000 | $25,000 | $25,000 | $25,000 |
RES | | 25,000 | 25,000 | 25,000 | 25,000 |
GMS | $50,000* | 50,000* | 25,000 | 25,000 | 25,000 |
GHS | 25,000 | 25,000 | 25,000 | 25,000 | 25,000 |
All facilities | $75,000 | $125,000 | $100,000 | $100,000 | $100,000 |
*Promethean Board replacement project
Randolph ES Renovation Projects
12
Project | FY2023 | FY2024 | FY2025 | FY2026 | FY2027 |
Aging Kitchen equipment replacement* | $59,220 | | | $67,461 | $70,834 |
Replace all building lights with LED and upgrade lighting controls* | | $161,406 | $169,476 | 177,950 | |
Replace needed electrical panels and switchgear in 1958 section/transformer* | | 298,006 | | | |
Renovate Boys & Girls Restrooms at main entrance to current code and ADA requirements/new tile & drainage* | | 264,865 | | | |
Roof repairs - oldest sections* | | | | 153,762 | 246,067 |
Furniture refresh | | | | 300,000 | |
Playing fields refresh | | | 50,000 | | |
Total | $59,220 | $724,277 | $219,476 | $699,173 | $316,901 |
*As recommended in Dewberry Engineering study, October 2021 (Total $2,019,047)
Byrd ES Renovation Projects
13
Project | FY2023 | FY2024 | FY2025 | FY2026 | FY2027 |
Aging Kitchen equipment replacement | | | $80,339 | $84,356 | |
Replace all building lights with LED/upgrade lighting controls - start 3 year phase-in* | | | | | $161,747 |
Replace needed electrical panels and switchgear in 1958 section/transformer* | | $202,970 | | | |
Renovate Boys & Girls Restrooms at main entrance to current code and ADA requirements/new tile & drainage* | | | | 278,108 | |
Roof repairs - oldest sections* | | | 321,357 | 82,776 | |
Furniture refresh | | | | 300,000 | |
Replace failing windows/refinish gym floor* | | | | 55,062 | 43,266 |
Total | | $202,970 | $401,696 | $800,302 | $205,013 |
*As recommended in Dewberry Engineering study, October 2021 (Total $1,609,982)
Miscellaneous Special Projects
14
School/facility project | FY2023 | FY2024 | FY2025 | FY 2026 | FY2027 |
GMS Video camera replacements** | | | | | $302,479 |
GMS carpet and tile replacements | | | | $100,000 | 57,443 |
GMS playing field upgrade | | $50,000 | | | |
Bus Garage projects* | $51,931 | | $82,694 | | |
Bus & vehicle purchases (one each) | 110,250 | 115,763 | 156,279 | 164,093 | 172,298 |
All other facilities | $162,181 | $165,763 | $238,973 | $264,093 | $532,220 |
*Window and HVAC replacements (FY2023); plumbing, security, and front lot paving (FY 2025)
**As recommended by Dewberry Engineering, October 2021
Goochland HS Renovation Projects
15
Project | FY2023 | FY2024 | FY2025 | FY2026 | FY2027 |
Replace kitchen equipment* | | $125,906 | $132,201 | $138,811 | $145,751 |
Tile replacement | | | | 100,000 | |
HVAC system upgrades* | $1,153,906 | 2,376,623 | 2,922,154 | 523,032 | 1,138,571 |
Athletic department upgrades | 40,000 | 40,000 | 40,000 | 60,000 | 40,000 |
Upgrade generator transfer switches; replace video cameras* | | 304,511 | | | 310,775 |
Replace all building lights with LED and upgrade lighting controls* | | 215,015 | 225,766 | 237,054 | 248,907 |
Total | $1,193,906 | $3,062,055 | $3,320,121 | $1,058,897 | $1,884,004 |
*As recommended by Dewberry Engineering, October 2021 (Total $11,018,981)
HVAC projects changes from last year:
16
Projects | FY2023 | FY2024 | FY2025 | FY2026 | FY2027 | Total |
Last year COVID-19 funding allowed us to spend over $1M in proactive HVAC projects at RES and GES. These facilities may not need HVAC equipment replacement during their remaining life. Staff knew equipment replacement was needed at 20 year old GHS but thought that it could be handled in-house as each piece of equipment failed with minimal upgrades needed. | | |||||
Schools division -wide | $100,000 | 100,000 | 200,000 | 200,000 | 100,000 | $700,000 |
The Dewberry Engineering study* pointed out the need to be proactive on all equipment replacement, especially equipment that had a school-wide impact and could shut the school down. GMS equipment will need $4,547,341 in replacements starting in 2028, as GMS reaches its 20th year. | | |||||
GHS HVAC system upgrades* | $1,153,906 | 2,376,623 | 2,922,154 | 523,032 | 1,138,571 | $8,114,285 |
| | | Year over Year Difference | $7,414,285 | ||
*As recommended by Dewberry Engineering, October 2021 (Total $11,018,981)
10 Year CIP Draft - SB 11/9/2021
17
30 Year CIP Draft - SB 11/9/2021
18
Next Steps
Any questions?
19