DEVELOPMENT
OF
20 RAILWAY STATIONS
UNDER
AMRIT BHARAT STATION SCHEME
IN
PUNE DIVISION
BY
GATI-SHAKTI UNIT
Section | SN | Station | Estimated cost (in Cr.) |
PA-LNL | 1 | Chinchwad | 20.44 |
2 | Akurdi | 33.83 | |
3 | Dehu road | 8.05 | |
4 | Talegaon | 40.34 | |
PA-BRMT | 5 | Hadapsar | 24.86 |
6 | Uruli | 12.86 | |
7 | Kedgaon | 12.55 | |
8 | Baramati | 11.40 |
Section | SN | Station | Estimated cost (in Cr.) |
PA-KRD | 9 | Lonand | 10.48 |
10 | Wathar | 7.97 | |
11 | Satara | 34.31 | |
12 | Karad | 12.51 | |
13 | Phaltan | 0.76 | |
KRD-KOP | 14 | Sangli | 24.20 |
15 | Hathkanangle | 6.00 | |
16 | Kolhapur | 43.03 |
STATIONS
Section | SN | Station | Estimated cost (in Cr.) |
�����DD-MMR | 1 | Daund | 44.17 |
2 | Ahmednagar | 30.92 | |
3 | Belapur | 31.96 | |
4 | Kopargaon | 29.94 |
STATIONS
Amrit Station Works Status (Except FOB) Pune GSU
S N | Name of station | TDC | Position of FOB | S N | Name of station | TDC | Position of FOB |
1 | Kedgaon | Complete | NA | 12 | Ahmednagar | 30.07.25 | 1. FOB – 31.03.26� |
2 | Lonand | Complete | NA | 13 | Akurdi | 30.09.25 |
|
3 | Talegaon | 30.06.25 | 1. FOB - 30.12.25�2. 3 LIFT & 3 ESC - 31.03.26 | 14 | Daund | 31.12.25 | 1. FOB – 31.03.26 2. Escalator-31.03.26 |
4 | Baramati | 30.06.25 | NA | 15 | Sangli | 30.11.25 | 1. FOB - 31.03.26�2. 2 LIFT & 3 ESC - 31.03.26 |
5 | Wathar | 30.07.25 | NA | 16 | Dehu Road | 31.10.25 | 1. FOB - 30.03.26 |
6 | Phaltan | Complete | NA | 17 | Uruli | 31.03.26 | NA |
7 | Kopargaon | 30.06.25 | FOB - 31.03.26 | 18 | Hathkangale | 21.11.25 | NA |
8 | Satara | 30.09.25 | 1. FOB - 28.02.26�2. 1 LIFT & 3 ESC -31.03.26 | 19 | Kolhapur | 21.11.25 | 1. FOB – 31.03.26�2. 2 LIFT & 2 ESC – 31.03.26 |
9 | Chinchwad | 31.08.25 | 1. FOB (extn) – 31.03.26�2. 4 LIFT & 2 ESC - 31.03.26 | 20 | Hadapsar | 15.12.25 | 1. FOB & Skywalk– 15.12.25�2. 2 LIFT & 02 Escalator – 31.03.2026 |
10 | Karad | 30.09.25 | NA | | | | |
11 | Belapur | 31.12.25 | 1. FOB – 31.03.26 | | | | |
PUNE – LONAVALA
MAVAL CONSTITUENCY
(04- STATIONS)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
PA-LNL MAVAL | 1 | Talegaon | 40.34 |
2 | Dehu road | 8.05 | |
3 | Akurdi | 33.83 | |
4 | Chinchwad | 20.44 | |
Total | 102.71 | ||
Talegaon (Estimated cost: 40.39 Cr)
Phase-I Works TDC: Soft- 30.06.2025
FOB- 30.12.2025
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
Current status
Physical Progress- 57%
TALEGAON (SG-3) –Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1
| Provision of New Portico (DN Side) | |
Development of Circulating Area and Parking on Main entry (DN Side) | ||
Development of Circulating Area and Parking on Main entry (UP Side) | ||
Provision of COP (approx. 380 sq.m.) | ||
PF Surface Improvement | 100 % | |
Provision of new toilet Block at PF-1 | ||
Provision of new toilet Block at PF-2 | ||
Renovation of existing Booking office | ||
Renovation of existing waiting room with roof replacement (Mangalore tile) at PF-2 (Interior) | ||
Construction of new waiting room at PF-1 | ||
Construction of new water booth (6 Nos) (3 at each PF) | 85 % | |
Provision of 03 escalators and 03 lifts (Foundation of 2 lifts in progress ) | ||
FOB work | 35% | |
| Electrical |
|
| Electrical works of TRD and general portion | 90 % |
| Provision of 3 lifts and 3 escalators | 55 % |
| Minimum Essential Amenities and facilities for divyangjan (Except telecom, lift and quick watering system) | 80 % |
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 85 % |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items | 85 % |
|
|
|
| Commercial |
|
| Provision of Furniture |
|
Important new additions and Improvement works planned (Talegaon)
Dehu Road (Estimated cost: 8.05 Cr)
Phase-I Works TDC: Soft- 31.10.2025
FOB- 30.03.2026
Current status
Physical Progress-12%
Dehu Road (NSG-3)–Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1 | Main Entry Gate | N/A |
Provision of New portico with entrance lobby extension |
| |
Provision of new toilet block at PF-1 | ||
Development of Circulating Area and parking | 65 % | |
Renovation of existing Booking office with entrance lobby after completion and extension of entrance lobby |
| |
COP at PF-1 & 2 | ||
PF Surface |
| |
•Improvement to Façade |
| |
•Augmentation of Seating Facilities and signages, Improvement to Illumination |
| |
Renovation of existing waiting room, SS office |
| |
| Electrical |
|
| Electrical works of TRD and general portion (DG Room completed) | 100 % |
| Provision of lifts and escalators |
|
| Minimum Essential Amenities and facilities for Divyangjan (Except telecom, lift and quick watering system) |
|
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 35% |
| Telecom, Expansion of information system to facilitate Divyangjan and other PA items | 35% |
| Commercial |
|
| Provision of Furniture |
|
Important new additions and Improvement works planned (Dehu road)
AKURDI (SG-3) Estimated Cost: 33.83 Cr.
�
�
Current status
Physical Progress- 50 %
Phase-I Works TDC: Soft- 30.09.2025
FOB- 31.03.2026
02 Escalator- 31.03.2026
AKURDI (SG-3) Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
| Construction of New Waiting Area(LHS &RHS SIDE) | |
Construction of Portico | ||
Construction of DG Room | 100 % | |
Construction of UGWT | 100 % | |
Main Entry Gate | 0 % | |
Construction of Parking/Circulation Area | 50 % | |
Construction of Public Plaza | 0 % | |
Renovation Work ( Existing Booking Office ) | 15 % | |
Construction of Water Booth 4 nos | 95 % | |
COP Work | ||
PF - 1 Flooring Work | ||
COP Work | 95 % | |
PF - 2 Flooring Work | 80 % | |
Construction of New FOB | ||
| Electrical |
|
| Electrical works of TRD and general portion. | 20% |
| Provision of lifts and escalators. |
|
| Minimum Essentials Amenities and facilities for divyangjan (Except telecom, lift and quick watering system). |
|
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 55% |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items. | 55% |
| Commercial |
|
| Provision of Furniture. |
|
Important new additions and Improvement works planned (Akurdi)
CHINCHWAD (SG-3) (Estimated cost: 20.44 Cr-)
Current status
Physical Progress- 55 %
Phase-I Works TDC:
Soft- 31.08.2025
FOB- only extension at 2nd Entry 31.03.2026
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
CHINCHWAD(SG-3) –Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1
| Provision of New Entrance lobby cum waiting lounge at main entry with portico (DN Side) | |
TOILET UNDER FOB | 80% | |
Construction of New RPF THANA | 100% | |
Construction of New OHE room | ||
Development of Circulating Area and parking on Main entry (DN Side) by demolishing existing RPF SETUP | ||
Extension of booking office with provision of OFC room, Electrical panel room, CBS room with toilet | ||
Renovation of existing Booking office | ||
Provision of new toilet Block at PF-1/2 | ||
Provision of new toilet Block at PF-3/4 | ||
Provision of 1 Lift and 1 escalator at main entrance | ||
Renovation of water booths and existing toilet | 0 % | |
Renovation of existing waiting room , SS office | 50% | |
Provision of 03 lift (01 each at PF 1 / 2 & 3 / 4 at 2nd entry) | ||
COP Work | ||
Platform surface improvement | 0% | |
| Electrical |
|
| Electrical works of TRD and general portion. |
|
| Provision of lifts and escalators. |
|
| Minimum Essential Amenities and facilities for Divyangjan (Except telecom, lift and quick watering system). |
|
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 85% |
| Telecom, Expansion of information system to facilitate Divyangjan and other PA items. | 75% |
| Commercial |
|
| Provision of Furniture |
|
Important new additions and Improvement works planned (Chinchwad)
PUNE - DAUND
SHIRUR CONSTITUENCY
(02- STATIONS)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
PA-LNL / SHIRUR | 1 | Hadapsar | 24.86 |
2 | Uruli | 12.86 | |
Total | 37.72 | ||
HADAPSAR
(Estimated cost: 24.86 Cr)
Current status
Overall Physical Progress- 55 %
Phase-I Works TDC: Soft- 15.12.2025� FOB & Skywalk– 15.12.25� 2 LIFT & 02 Escalator – 31.03.2026
�
SN | Scope | Progress |
PHASE-I | | |
1 | PF surface at PF no. 1, 2 & 3 | 60 % |
2 | PF 1 building A (reservation office, waiting room, dormitory) | |
| PF 1 building B (Existing building extension, RPF Post, child care room) | |
4 | Building C (VIP waiting room, upper class waiting, toilet block, RPF office) | |
5 | Building D parcel office | |
6 | COP | 90 % |
7 | FOB | |
HADAPSAR (NSG-6)–Scope of work (with TDC and overall progress)
HADAPSAR
(Estimated cost: 24.86 Cr in PH-53 under ABSS & 135.81 Cr. under PH-16)
Highlights of Planned works
URULI (NSG-5) (Estimated cost: 12.86 Cr)-
Current status
Overall Physical Progress- 96 %
Phase-I Works TDC: Soft- 31.03.26� FOB- NA
URULI (NSG-5) –Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1 | PF1- Construction of Parking Area | 75 % |
PF1- Construction of Portico | 80 % | |
Construction of front elvation | 90 % | |
Renovation of Existing booking area, Entrance lobby & waiting room | 95 % | |
Renovation of Waiting Area attached Toilet | 95 % | |
Construction of PF Toilet Block | 100 % | |
Construction of Water Booth | 90 % | |
COP & PF SURFACE | 100 % | |
Platform Flooring Work PF1 | 90 % | |
Cover Over Platform ( COP ) PF1 | 100 % | |
FOB ramp | 100% | |
Ramp work | 95 % | |
| Electrical |
|
| Electrical works of TRD and general portion. |
|
| Provision of lifts and escalators. |
|
| Minimum Essential Amenities and facilities for divyangjan (Except telecom, lift and quick watering system). |
|
| S & T |
|
| Provision of Pasanger Amanities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 70% |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items. | 70% |
| Commercial |
|
| Provision of Furniture. |
|
Important new additions and Improvement works planned (Uruli)
PUNE - DAUND
BARAMATI CONSTITUENCY
(02- STATIONS)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
PA-DAUND / BARAMATI | 1 | Kedgaon | 12.55 |
2 | Baramati | 11.40 | |
Total | 23.95 | ||
KEDGAON (NSG-5)(Estimated cost: 12.54 Cr)
Current status
Physical Progress- 100%
Phase-I Soft upgradation and COP work
completed on 28.02.2025, 12m FOB: -NA
Station Inaugurated on - 23.05.2025.
KEDGAON (NSG-5)–Scope of work (with TDC and overall progress)
Sr. No. | Scope | Physical Progress |
| Civil |
|
PH-1
| Main Entry Gate | 100% |
PF1- Construction of Compound Wall | 100% | |
PF1- Construction of Parking Area | 100% | |
PF1- Construction of Portico | 100% | |
Construction of front elevation | 100% | |
Renovation of Existing booking area, Entrance lobby & waiting room | 100% | |
Renovation of Waiting Hall | 100% | |
Construction of PF Toilet Block | 100% | |
Construction of Water Booth | 100% | |
PF SURFACE |
| |
PF-1 | 100% | |
PF-2 | 100% | |
Cover Over Platform ( COP ) |
| |
PF-1 | 100% | |
PF-2 | 100% | |
FOB ramp PF-1 | 100% | |
FOB ramp PF-2 | 100% | |
| Electrical |
|
| Electrical works of TRD and general portion. | 100 % |
| Provision of lifts and escalators. | 100 % |
| Minimum Essential Amenities and facilities for Divyangjan (Except telecom, lift and quick watering system) | 100 % |
| S & T |
|
| Provision of Pasanger Amanities like indicators, outdoor VDU, PA systems, Clocks with utility systems. | 100% |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items. | 100% |
| Commercial |
|
| Provision of Furniture. |
|
Important new additions and Improvement works planned (Kedgaon)
BARAMATI (NSG-5) (Estimated cost: 11.40 Cr)
Current status
Physical Progress- 82%
Phase-I Works TDC: Soft- 31.08.2025
FOB- NA
BARAMATI (NSG-5)–Scope of work (with TDC and overall progress)
Sr. No. | Scope | Progress |
| Civil |
|
PH-1 | Main Entry Gate | 80 % |
PF1- Construction of Compound Wall | 100 % | |
PF1- Construction of Parking Area | 75 % | |
PF1- Construction of Portico | 87 % | |
Construction of Verandah | 92% | |
Renovation of Existing booking area, Entrance lobby & waiting room | 77 % | |
Renovation of Waiting Area attached Toilet | 95% | |
Construction of Toilet Block | 100% | |
Construction of Septic Tank | 100% | |
Construction of Water Booth | 100% | |
Platform Flooring Work | 99% | |
Cover Over Platform ( COP ) | 100% | |
| Electrical |
|
| Electrical works of TRD and general portion |
|
| Provision of lifts and escalators | NA |
| Minimum Essential Amenities and facilities for divyangjan (Except telecom, lift and quick watering system) |
|
| S & T |
|
| Provision of Passenger Amenities like indicators, outdoor VDU, PA systems, Clocks with utility systems | 50% |
| Telecom, Expansion of information system to facilitate divyangjan and other PA items | 40% |
| Commercial |
|
| Provision of Furniture |
|
Important new additions and Improvement works planned (Baramati)
PUNE - KARAD
MADHA CONSTITUENCY
(02- STATIONS)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
PA-KRD MADHA | 1 | Wathar, | 7.97 |
2 | Phaltan | 0.76 | |
Total | 8.73 | ||
WATHAR (NSG-6) (Estimated cost: 7.97 Cr)
Current status
Physical Progress- 77%
Phase-I Works TDC:
Soft- 31.08.25
FOB- NA
WATHAR (NSG-6) Scope of work (with TDC and overall progress) | ||
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 55 % |
2 | Construction Of Compound Wall | 95 % |
3 | Construction Of Parking Area and Circulation Area | 80 % |
4 | Renovation of Existing Booking Office and Entrance Lobby | 90 % |
5 | Renovation of Portico | 90 % |
6 | Improvement of Façade |
|
7 | Improvement of Roof | 100% |
11 | Dismantling of Union Office | 100% |
12 | PF-1 Construction of new water booths |
|
13 | COP PF1 | 100 % |
14 | Improvement of Platform Surface PF1 | 85% |
Important new additions and Improvement works planned (Wathar)
Current status
Physical Progress- 100%
PHALTAN (Estimated cost: 0.92 Cr)
Phase-I Works TDC: Soft- 08.03.2025
FOB- NA
Important new additions and Improvement works planned (Phaltan)
PUNE - KARAD
SATARA CONSTITUENCY
(03- STATIONS)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
PA-KRD / SATARA | 1 | Lonand, | 10.48 |
2 | Satara | 34.31 | |
3 | Karad | 12.51 | |
Total | 57.3 | ||
LONAND (Estimated cost: 10.47 Cr)
Current status
Physical Progress- 100%
Phase-I Works TDC: Soft- 28.02.2025
FOB- NA
LONAND (NSG-6) Scope of work (with TDC and overall progress) | ||
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 100% |
2 | Construction of Compound Wall | 100% |
3 | Construction of New portico | 100% |
4 | Construction of Circulation Area | 100% |
5 | Construction of Parking | 100% |
6 | Renovation of Booking Office and Entrance Lobby | 100% |
7 | PF-1 Construction of New Toilet block | 100 % |
8 | PF-1 Construction of Waiting Room | 100 % |
9 | PF-1 Improvement of new water booths | - |
10 | PF-2 Construction of New Toilet block | - |
11 | COP PF 1 | 100 % |
12 | COP PF 2 | 100 % |
13 | Improvement of Platform Surface PF1 | 100 % |
14 | Improvement of Platform Surface PF2 | 100 % |
Important new additions and Improvement works planned (Lonand)
SATARA (Estimated cost: 34.31 Cr)
Current status
Physical Progress- 55%
Phase-I Works TDC:
Soft- 30.09.2025
FOB- 28.02.2026
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
Sr. No. | Scope | Progress |
2 | Construction of Exit Gate | 95 % |
3 | Construction of New Portico | 92 % |
4 | Construction of Parking Area and Widening of Road | 82 % |
5 | Construction of Curtain Wall | 0 % |
6 | Construction of new TI Room | 80 % |
7 | Construction of VIP Waiting Room Extension | 85 % |
8 | Renovation of Booking Office | 5 % |
9 | Improvement of Façade |
|
10 | PF-1 Renovation of existing General class waiting room / SM Rest Room | 90 % |
11 | PF-1 Renovation of Entrance Lobby | 10 % |
12 | PF-1 Renovation of Upper-Class waiting room with Toilet Block | 100 % |
13 | PF-1 Renovation of Parcel Office | 0 % |
14 | PF-1 Renovation of Ladies waiting room with Toilet Block | 86 % |
15 | PF-1 Construction of New Toilet block | 90 % |
16 | PF-1 Development of new water booths | 0 % |
17 | PF-2&3 - Construction of New Toilet block | |
18 | PF-4&5 -Construction of Toilet Block |
|
19 | COP PF1 | 85 % |
20 | COP PF 2-3 | 23 % |
21 | Improvement of Platform Surface PF 1 | 15% |
22 | Improvement of Platform Surface PF 2-3 |
|
23 | Construction of Civil Works For Escalator |
|
24 | Construction of 12m wide FOB | 60 % |
SATARA (NSG-5) Scope of work (with TDC and overall progress)
Important new additions and Improvement works planned (Satara)
KARAD (NSG-5) (Estimated cost: 12.50 Cr)
Current status
Physical Progress- 66%
Phase-I Works TDC: Soft- 30.09.2025
FOB- NA
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 55 % |
2 | Construction of Compound Wall | 100 % |
3 | Construction of New Portico | 87 % |
4 | Construction of Parking Area | 90 % |
5 | Improvement of Façade |
|
6 | Improvement of Roof | 95% |
7 | PF-1 Renovation of existing General class waiting room | 100% |
8 | PF-1 Renovation of New Upper Class Waiting Room | 100 % |
9 | PF-1 Renovation of Booking Office |
|
10 | PF-1 Renovation of Existing Entrance lobby | 80 % |
11 | PF-1 Construction of New Toilet block |
|
12 | PF-1 Construction of new water booths |
|
13 | COP PF1 | 95% |
14 | Improvement of Platform Surface PF1 | 20% |
15 | Construction of Civil Works For Escalator |
|
KARAD (NSG-5) Scope of work (with TDC and overall progress)
Important new additions and Improvement works planned (Karad)
SANGLI CONSTITUENCY
(01- STATION)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
KRD-KOP / SANGLI | 1 | Sangli | 24.20 |
Total | 24.19 | ||
SANGLI (Estimated cost: 24.19 Cr)
Current status
Physical Progress- 61%
Phase-I Works TDC: Soft- 30.11.2025
FOB- 31.03.2026
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 96% |
2 | Construction of New Portico | 94% |
3 | Construction of Parking Area | 70% |
4 | Construction of Circulation Area | 75% |
5 | Construction of Compound Wall | PF No. 01 96% |
6 | Construction of Ramp |
|
7 | Construction of New Booking office | 100% |
8 | Improvement of Facade | 25% |
9 | PF-1 Renovation of existing General class waiting room | 75% |
10 | PF-1 Renovation of existing Upper Class waiting room With Male & Female Toilet Blocks | 90% |
11 | PF-1 Renovation Exisiting Entrance lobby | 5% |
12 | PF-1 Renovation of Existing VIP Lounge | 90% |
13 | PF-1 Renovation of Existing Male, Ladies and Divyangjan Toilet Block | 95 % |
14 | PF-1 Construction of Water Booth | 60% |
15 | COP- PF1 | 97 % |
16 | COP- PF2-3 | 25 % |
17 | Improvement of Platform Surface -PF1 | 95 % |
18 | Improvement of Platform Surface -PF 2-3 | - |
19 | Construction of Civil Works For Escalator | - |
20 | Construction of 12m wide FOB | 35 % |
SANGLI (NSG-5) Scope of work (with TDC and overall progress)
Important new additions and Improvement works planned (Sangli)
KARAD-KOLHAPUR
HATKANANGLE CONSTITUENCY
(01- STATION)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
MRJ-KOP / HATKANANGLE | 1 | Hathkanangle | 6.0 |
Total | 6.0 | ||
HATKANANGLE (NSG-5) (Estimated cost: 6.00 Cr)
Current status
Physical Progress- 67%
Phase-I : Soft TDC - 21.11.2025
FOB TDC - NA
Sr. No. | Scope | Progress |
1 | Construction of Entry Gate | 0 % |
2 | Construction of Retaining Wall | 100 & |
3 | Construction of New Portico | 100 % |
4 | Construction of Parking Area and Circulation Area | 80 % |
5 | Construction of Ramp |
|
6 | Construction of Staircase | 95 % |
7 | Construction of New Entrance Lobby | 80 % |
8 | Improvement of Façade | 25 % |
9 | PF-1 Renovation of Existing Booking Office and Existing Entrance Lobby |
|
10 | PF-1 Construction of New Toilet block | 85 % |
11 | PF-1 Construction of New Waiting Room | 85 % |
12 | COP- PF1 | 90 % |
13 | COP- PF 2 | 90 % |
14 | Improvement of Platform Surface PF1 | 75 % |
15 | Improvement of Platform Surface PF 2 | 95 % |
|
|
|
HATHAKANANGLE (NSG-5) Scope of work (with TDC and overall progress)
Important new additions and Improvement works planned (Hatkanangle)
KOLHAPUR (NSG-3) (Estimated cost: 43.03 Cr)
Current status
Physical Progress- 74%
Phase-I : Soft TDC - 21.11.2025
FOB TDC - 31.03.2026
Lift TDC - 31.03.2026
Escalator TDC - 31.03.2026
KARAD-KOLHAPUR
KOLHAPUR CONSTITUENCY
(01- STATION)
Section / Constituency | SN | Station | Estimated cost (Rs. in Cr.) |
KRD-KOP / KOLHAPUR | 1 | Kolhapur | 43.03 |
Total | 43.03 | ||
KOLHAPUR (NSG-3) Scope of work (with TDC and overall progress)
SN | Scope | Progress |
1 | Construction of Entry Gate | 80 % |
2 | Construction of Exit Gate | 75 % |
3 | Construction of new portico | 95 % |
4 | Construction of Parking Area and Circulation area | 30 % |
5 | Extension of Existing portico | 60 % |
6 | Construction of New Booking office | 95 % |
7 | Construction of Public Toilet Block | 70 % |
8 | Cover over existing pathway in front of existing building | 85 % |
9 | Main Station Building Roofing Work | 100 % |
10 | Removal of Union office | 80 % |
11 | PF-1 Renovation of existing General class waiting room |
|
12 | PF-1 Renovation of existing AC waiting room With Male & Female Toilet Blocks | 100 % |
13 | PF-1 Renovation of existing PRS | 67 % |
14 | PF-1 Renovation of Exsiting Entrance lobby. | 2 % |
15 | PF-1 Renovation of VIP Entrance lobby. | 60 % |
16 | PF-1 Improvement of Facade | 65 % |
17 | PF-1 Renovation of existing Ladies waiting room | 62 % |
18 | PF-1 Construction of New Toilet block | 95 % |
19 | PF-1 Construction of new water booths | 0 % |
20 | PF-2&3 Construction of New Toilet block | 95 % |
21 | COP - PF1 | 95 % |
22 | COP - PF2-3 |
|
23 | Improvement of Platform Surface PF1 (Work done as per Instruction) | 10 % |
24 | Improvement of Platform Surface PF2-3 | 100 % |
25 | Construction of 12m wide FOB | 35 % |
PH-2 |
| 5% |
| - |
Important new additions and Improvement works planned (Kolhapur)
PUNE Division : Traffic Facility Works GM’s power
SN | Name of work | Year / Last San. Cost | Allocation/ Exec. Agency | ESP | SIP | Tender Status | CRS | Status | ||
Engg. | S&T | Elect. | ||||||||
1 | Hadapsar - Development of satellite terminal. Work transferred from construction department to GSU in 2022. Scope: Extn. of PF 1 & 2 and additional 3rd PF, 2 Common loops for RBPC trains. New EI. | 2016-17 135.81 Cr. (Rev.) | DF(3), RRSK & EBR(S) GSU/PA TDC: Dec.’24 Rev.1: June’25 | 25.5.21 Rev. 31.8.23 | 26.8.21 Rev. 20.4.24
| Awarded | Awarded | Awarded | Under process | 1) CRS has raised queries regarding availability of 1in 8.5 turnouts on passenger loop lines. Accordingly, the yard plan has been reviewed and the turnouts on common loop line no.2 and 3 has been proposed with 1 in 12 turnouts. The loop line no. 4 turnouts could not be changed to 1in 12 due to non-availability of sufficient CSL. PCE’s approval for the same has been obtained. 2) Track of two stabling lines of approx. 500m was laid and linking is pending for land acquisition. 3) Revised Final ESP has been approved by headquarters and send for CRS sanction. 4) Possession of 9 out of 10 land parcels (survey numbers) has been received from the State Authority (SDO, Pune). Possession of the remaining land parcel is currently under process. 5) 90% work of station building is completed. FOB work is in progress. |
PUNE Division : Traffic Facility Works GM’s power
SN | Name of work | Year / Last San. Cost | Allocation/ Exec. Agency | ESP | SIP | Tender Status | CRS | Status | ||
Engg. | S&T | Elect. | ||||||||
2 | LONI: Development of Goods shed with acquisition of land for increase of circulating area and in length of Goods line with shunting neck. Scope: Extension of Goods Shed & Goods siding lines and provision of Shunting Neck. Work transferred from construction department to GSU in 2022. | 2022-23 47.1 Cr. | CAP GSU/PA TDC: Dec.’24 Rev.1: To be fixed | 23.05.23 Rev. 20.09.23 | 20.10.23 Rev. 02.05.24 | Awarded | Awarded | Awarded | Under preparation |
|
Daund Estimated cost: 44.17 Cr
Current status
Physical Progress- 51%
Phase-I : Soft TDC – 31.12.2025
FOB TDC - 31.03.2026
Escalator TDC - 31.03.2026
Renovation works: Renovation to existing quarters.
Important new additions and Improvement works planned (Daund)
AHMEDNAGAR (Estimated cost: 30.92 Cr)
Current status
Overall Physical Progress- 56 %
Phase-I Works TDC: Soft- 30.07.2025
FOB- 31.03.2026
Important new additions and Improvement works planned (Ahmednagar)
KOPARGAON (Estimated cost: 29.94 Cr)
Current status
Overall Physical Progress- 56 %
Phase-I Works TDC: Soft- 30.06.2025
FOB- 31.03.2026
Provision of 2 nos. retiring rooms for passengers, widening of platform 1 towards DD end for 45 m., improvement to drainage was also done.
Important new additions and Improvement works planned (KOPARGAON)
BELAPUR (Estimated cost: 31.96 Cr)
Current status
Overall Physical Progress- 46%
Phase-I Works TDC: Soft- 31.12.2025
FOB- 31.03.2026
Provision of 2 nos. retiring rooms for passengers, extension of platform 1 towards DD end for 150 m., improvement to drainage was also done.
Important new additions and Improvement works planned (BELAPUR)