MAYURBHANJ SCHOOL OF ENGINEERING, (MSE)
SATYA SWARUP DAS
LECTURER IN MECHANICAL ENGINEERING,
SUMMER 2022, 4TH SEMESTER,
SUBJECT: IE&M
TOPIC: PERT / CPM
PERT/CPM
Importance of PERT/CPM
CPM
Project Network
Drawing the project network (AOA)
A
1
2
3 days
This means activity A starts at node 1 and finishes at node 2 and it will takes three days
Determining the Critical Path
The project completion time is the maximum of the Earliest Finish Times at the Finish node.
Determining the Critical Path
Determining the Critical Path
Slack = (Latest Start) - (Earliest Start), or
= (Latest Finish) - (Earliest Finish).
A critical path is a path of activities, from the Start node to the Finish node, with 0 slack times.
Example: ABC Associates
Immediate
Activity Predecessor time (days)
A -- 6
B -- 4
C A 3
D A 5
E A 1
F B,C 4
G B,C 2
H E,F 6
I E,F 5
J D,H 3
K G,I 5
Example: network
A
B
C
D
E
F
G
H
I
J
K
1
2
3
4
5
6
7
6
4
3
5
1
4
2
6
5
3
5
0
6
9
13
19
18
23
23
18
20
13
9
6
0
ES
LF
Forward
Backward
Example: ABC Associates
Activity time ES EF LS LF Slack
A 6 0 6 0 6 0 *critical
B 4 0 4 5 9 5
C 3 6 9 6 9 0 *
D 5 6 11 15 20 9
E 1 6 7 12 13 6
F 4 9 13 9 13 0 *
G 2 9 11 16 18 7
H 6 13 19 14 20 1
I 5 13 18 13 18 0 *
J 3 19 22 20 23 1
K 5 18 23 18 23 0 *
EF = ES + t
LS = LF β t
Where t is the
Activity time
Slack = LF β EF
= LS - ES