Basics of BESS
(Battery Energy Storage System) & Project Planning
Basic Terms in Energy Storage
Battery Pack
Cell
Liquid Cooling Unit
High Voltage Box
MV Skid containing PCS and Transformer
PCS (Power Conversion System)
Grid Following PCS
Grid following PCS (along with energy source) synchronizes its energy output with the grid’s voltage and frequency.
Grid following PCS track the grid angle and magnitude to inject or absorb active and reactive power.
Grid following PCS are dependent on the grid to provide a stable voltage and frequency and cannot operate in islanded or off-grid mode and does not support black start function.
Grid following PCS are popularly used in on-grid BESS projects.
Grid Forming PCS
Grid forming PCS (along with energy source) has the ability to provide voltage and frequency support to the grid during power outages.
Grid forming PCS can operate independently and help restore the grid after a blackout.
Grid forming PCS is a growing trend these days as the grid is working with more renewable energy.
MV/LV Transformer
measuring point after HV/MV Transformer.
Switchgear
View of a 100MW/200MWh BESS Project
View of a 50MW/100MWh using Sodium- ion
ngle Line Diagram
of a BESS Container
��Single Line Diagram of a BESS Project
Why BESS?
Business Opportunities
CAPEX, OPEX - Detailed Cost Structure
Capital Expenditure (CAPEX) Initial Investment Costs:
OPEX for Maintenance and Replacement Replacement/Maintenance Costs:
projects with more than cycles specified by manufacturer, specially for operation in high temperature areas.
battery cycling and calendar aging, depending on number of cycles per day.
lifetime due to increasing internal resistance of the cells with time. It takes the overall project RTE below 85% with time and attract penalties.
Financial Viability:
Regulatory Compliance:
Project Sustainability
Project Overview and Sizing Planning
BESS Degradation for 2 cycle per day for 12 years at 0.5C/0.5C with variable DoD, need to use 550MWh battery system for 250MW/500MWh project for measuring point at MV | | | |||||||
| | Our Battery Degradation Pattern | Energy after Conversion and Transmission Losses | Augmentation | | ||||
Time | Cycles | Degradation | Retention Capacity | Battery Capacity | Allowed Battery Degradation as per Project | Battery Discharge Energy Before Transmission and Conversion Losses | DoD of Battery including RTE reduction | Capacity Augmented | DC-DC RTE |
Beginning | 0 | 0.40% | 99.60% | 547.800 MWh | 100.00% | 516.529 MWh | 94.29% | | 94.00% |
After 1st Year | 730 | 4.29% | 95.31% | 524.205 MWh | 97.50% | 503.616 MWh | 96.27% | 10MWh Added end of year | 93.79% |
After 2nd Year | 1460 | 3.34% | 91.97% | 515.795 MWh | 95.00% | 490.702 MWh | 95.54% | | 93.58% |
After 3rd Year | 2190 | 2.82% | 89.15% | 499.860 MWh | 92.50% | 477.789 MWh | 96.17% | 10MWh Added end of year | 93.39% |
After 4th Year | 2920 | 2.61% | 86.54% | 495.133 MWh | 90.00% | 464.876 MWh | 94.64% | | 93.21% |
After 5th Year | 3650 | 2.55% | 83.99% | 480.418 MWh | 87.50% | 451.963 MWh | 94.99% | | 93.04% |
After 6th Year | 4380 | 2.49% | 81.50% | 466.130 MWh | 85.00% | 439.050 MWh | 95.26% | | 92.88% |
After 7th Year | 5110 | 2.43% | 79.07% | 452.245 MWh | 82.50% | 426.136 MWh | 95.43% | | 92.74% |
After 8th Year | 5840 | 2.38% | 76.69% | 438.645 MWh | 80.00% | 413.223 MWh | 95.54% | | 92.60% |
After 9th Year | 6570 | 2.26% | 74.43% | 425.717 MWh | 77.50% | 400.310 MWh | 95.49% | | 92.47% |
After 10th Year | 7300 | 2.22% | 72.21% | 413.020 MWh | 75.00% | 387.397 MWh | 95.38% | | 92.34% |
After 11th Year | 8030 | 2.19% | 70.02% | 400.506 MWh | 72.50% | 374.483 MWh | 95.20% | | 92.22% |
After 12th Year | 8760 | 2.19% | 67.83% | 388.001 MWh | 70.00% | 361.570 MWh | 94.99% | | 92.10% |
Real Data Provided by a BESS
Real Data Provided by a BESS
| | | |
BESS SoH Losses from Production to Project COD
until the project’s is commissioned and began operations.
capacity are used during BESS production to offset the cell capacity degradation from the time the cell is produced to the first 3 months after BESS is shipped.
BESS, capacity degradation goes below the BESS capacity rating. It is recommended to install and begin the project within 6 months of shipping.
after procuring the BESS, this additional SoH degradation must be factored in the project sizing calculation. | Month(s) | Degradation | |
FOB | 0.00% | ||
FOB+1 | 0.00% | ||
FOB+2 | 0.00% | ||
FOB+3 | 0.00% | ||
FOB+4 | 0.34% | ||
FOB+5 | 0.66% | ||
FOB+6 | 0.98% | ||
FOB+7 | 1.30% | ||
FOB+8 | 1.60% | ||
FOB+9 | 1.89% | ||
| |||
Round Trip Energy (RTE) Calculation at Measuring Point�Round trip calculation is done keeping the losses below in mind:
BESS Auxiliary Power Consumption
Aux components | Name | Voltage Standby Mode(W) | Maximum Operation Mode(W) | Emergency Mode(W) | |
Chiller | 380VAC | 70 | 35000 | 0 | |
Fire-fight system | 220VAC 3 | 30 | 30 | ||
Dehumidifier | 220VAC 0 | 400 | 0 | ||
Emergency exhaustfan | 220VAC 0 | 0 | 200 | ||
BAMS | 24VDC 10 | 10 | 10 | ||
Other 24V | 24VDC 3 | 5 | 3 | ||
Disconnector | 220VAC 0 | 0 | 0 | ||
Lamp | 220VAC 0 | 40 | 40 | ||
HV contactor | 220VAC 230 | 1650 | 80 | ||
Total | AC loading | / 303 | 37120 | 350 | |
DC loading | / 13 | 15 | 13 | ||
AC+DC loading | / 316 | 37135 | 363 | ||
Real Data Provided by a BESS