EVALUASI PENYERAPAN ANGGARAN DAN PROGNOSA
DESEMBER 2025
IKN Nusantara
Click to edit Master title style
PANTAUAN
AI DAN AO
Titik Nol Nusantara
REKAPITULASI PENYERAPAN AI 2025
AI TERBIT
AKI TERBIT
TERKONTRAK
TERBAYAR
SISA AKI
LUNCURAN
MURNI
TOTAL
10.805.224.957
10.895.538.311
10.383.616.461
10.436.872.594
53.256.133 |
10.776.519.268 |
10.829.775.401 |
53.256.133 |
10.333.404.749 |
10.386.660.882 |
0 |
50.211.712 |
50.211.712 |
58,97% |
99,73% |
99,40% |
100,00% |
99,52% |
0,00% |
0,48% |
0,48% |
Persentase “Terkontrak” terhadap AI Terbit
Persentase “ Terkontrak + Rencana” terhadap AI Terbit
Persentase “Terbayar” terhadap AKI Terbit
Persentase “Sisa Aki” terhadap AKI Terbit
Sumber data :
90.313.354 |
53.256.133 |
99,52% |
PANTAUAN REALISASI AI UP2D KALTIMRA 2025
JENIS ANGGARAN | PRK | AI | AKI | TERKONTRAK | % TERHADAP AI | SISA AI | TERBAYAR | % TERHADAP AKI | SISA AKI |
Luncuran | 2024.DKTU.4.001 | 90.313.354 | 53.256.133 | 53.256.133 | 58,97% | 37.057.221 | 53.256.133 | 100,00% | 0 |
Murni | 2025.DKTU.4.001 | 2.885.220.952 | 2.697.305.929 | 2.863.623.627 | 99,25% | 21.597.325 | 2.647.094.217 | 98,14% | 50.211.712 |
Murni | 2025.DKTU.4.001.8400 | 394.070.459 | 383.380.350 | 394.070.459 | 100,00% | 0 | 383.380.350 | 100,00% | 0 |
Murni | 2025.DKTU.4.002 | 6.658.535.900 | 6.656.466.182 | 6.656.466.182 | 99,97% | 2.069.718 | 6.656.466.182 | 100,00% | 0 |
Murni | 2025.DKTU.6.001 | 867.397.646 | 646.464.000 | 862.359.000 | 99,42% | 5.038.646 | 646.464.000 | 100,00% | 0 |
TOTAL | 10.895.538.311 | 10.436.872.594 | 10.829.775.401 | 99,40% | 65.762.910 | 10.386.660.882 | 99,52% | 50.211.712 | |
99,40% | | 99,52% |
TERKONTRAK TERHADAP AI | | TERBAYAR TERHADAP AKI |
Sumber data :
| Rencana Bayar Akumulatif | |
September | 7.932.059.668 | 74,09% |
Oktober | 9.223.793.696 | 86,16% |
November | 9.930.969.010 | 92,77% |
Desember | 10.436.872.594 | 97,49% |
RENCANA TERKONTRAK AI UP2D KALTIMRA 2025
JENIS ANGGARAN | PRK | AI | TERKONTRAK | RENCANA KONTRAK | KONTRAK+RENCANA | % KONTRAK+RENCANA | SISA KONTRAK+RENCANA |
Luncuran | 2024.DKTU.4.001 | 90.313.354 | 53.256.133 | 0 | 53.256.133 | 58,97% | 37.057.221 |
Murni | 2025.DKTU.4.001 | 2.885.220.952 | 2.863.623.627 | 0 | 2.863.623.627 | 99,25% | 21.597.325 |
Murni | 2025.DKTU.4.001.8400 | 394.070.459 | 394.070.459 | 0 | 394.070.459 | 100,00% | 0 |
Murni | 2025.DKTU.4.002 | 6.658.535.900 | 6.656.466.182 | 0 | 6.656.466.182 | 99,97% | 2.069.718 |
Murni | 2025.DKTU.6.001 | 867.397.646 | 862.359.000 | 0 | 862.359.000 | 99,42% | 5.038.646 |
TOTAL | 10.895.538.311 | 10.829.775.401 | 0 | 10.829.775.401 | 99,40% | 65.762.910 | |
| TOTAL RENCANA KONTRAK : | 0 | | |
PRK | URAIAN PEKERJAAN | NILAI FPP | RENCANA TERKONTRAK | PROGRESS RENCANA KONTRAK |
| | | | |
| | | | |
| | | | |
Sumber data :
Surat penugasan izin prinsip ai pengadaan fasilitas scada IKN tahun 2025
Sumber data :
Berdasarkan Surat No. 3471/DIS.01.01/F14000000/2025, PLN UP2D mendapatkan Izin Prinsip Anggaran Investasi untuk melakukan Pengadaan Fasilitasi SCADA di IKN Tahun 2025 dengan menggunakan SKKI UID Kaltimra Tahun 2025 No. 02/DIST DKTU/2025, PRK. 2025.DKTU.2.003 (Pembangunan Tahap 1 Jaringan Distribusi di Kawasan KIPP Ibukota Nusantara).
NO |
1 |
2 |
3 |
4 |
5 |
6 |
NO KONTRAK | URAIAN PEKERJAAN | VENDOR |
PEKERJAAN INTEGRASI GD IKN PT PLN (Persero) UP2D Kaltimra | PT PATARA TEKNIK SOLUSINDO | |
PEKERJAAN PENGADAAN RECTIFIER DAN BATERAI KERING (VRLA) UNTUK PENGUATAN INFRASTRUKTUR IKN LOKASI 1 | PT CATUDAYA DATA PRAKASA | |
PEKERJAAN PENGADAAN RECTIFIER DAN BATERAI KERING (VRLA) UNTUK PENGUATAN INFRASTRUKTUR IKN LOKASI 2 | PT SYNTEK OTOMASI INDONESIA | |
PEKERJAAN PENGADAAN RECTIFIER DAN BATERAI KERING (VRLA) UNTUK PENGUATAN INFRASTRUKTUR IKN LOKASI 3 | PT JAGE MUARE ULAKAN | |
PEKERJAAN PENGADAAN RECTIFIER DAN BATERAI KERING (VRLA) UNTUK PENGUATAN INFRASTRUKTUR IKN LOKASI 4 | PT SWADAYA ENGINEERING | |
| ||
START DATE |
22/08/2025 |
02/12/2025 |
02/12/2025 |
02/12/2025 |
02/12/2025 |
|
END DATE |
21/09/2025 |
02/03/2026 |
02/03/2026 |
02/03/2026 |
02/03/2026 |
|
NILAI KONTRAK AKHIR |
#210045300 |
1.276.242.480 |
838.320.840 |
622.506.870 |
488.031.480 |
|
KETERANGAN |
TERBAYAR TRE-V/7200/20251020/0000016091 |
Pelaksanaan Pekerjaan |
Pelaksanaan Pekerjaan |
Pelaksanaan Pekerjaan |
Pelaksanaan Pekerjaan |
|
PRK 2025.DKTU.2.003 Pembangunan Tahap 1 Jaringan Distribusi di Kawasan KIPP Ibukota Nusantara
RAB |
#210045300 |
1.276.242.480 |
838.320.840 |
622.506.870 |
488.031.480 |
|
TARGET VS REALISASI TERBAYAR AI UP2D KALTIMRA 2025
PRK | MARET | APRIL | MEI | JUNI | JULI | AGUSTUS | SEPTEMBER | OKTOBER | NOVEMBER | DESEMBER |
2024.DKTU.4.001 | 44.371.716 | 52.928.680 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 |
2025.DKTU.4.001 | 0 | 0 | 0 | 38.349.178 | 138.511.790 | 151.156.113 | 431.699.578 | 1.498.982.947 | 2.191.469.824 | 2.697.373.409 |
2025.DKTU.4.001.8400 | 0 | 0 | 0 | 0 | 0 | 0 | 347.407.100 | 383.312.871 | 383.312.871 | 383.312.871 |
2025.DKTU.4.002 | 0 | 0 | 0 | 349.999.644 | 5.803.465.780 | 6.526.032.857 | 6.526.032.857 | 6.641.777.745 | 6.656.466.182 | 6.656.466.182 |
2025.DKTU.6.001 | 0 | 0 | 0 | 0 | 0 | 0 | 573.664.000 | 646.464.000 | 646.464.000 | 646.464.000 |
TOTAL RENCANA | 44.371.716 | 52.928.680 | 53.256.133 | 441.604.955 | 5.995.233.703 | 6.730.445.103 | 7.932.059.668 | 9.223.793.696 | 9.930.969.010 | 10.436.872.594 |
TARGET BAYAR (KOMULATIF)
PRK | MARET | APRIL | MEI | JUNI | JULI | AGUSTUS | SEPTEMBER | OKTOBER | NOVEMBER | DESEMBER |
2024.DKTU.4.001 | 44.371.716 | 52.928.680 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 | 53.256.133 |
2025.DKTU.4.001 | 0 | 0 | 0 | 38.349.178 | 138.511.790 | 151.156.113 | 431.699.578 | 1.498.982.947 | 2.193.380.310 | 2.647.094.217 |
2025.DKTU.4.001.8400 | 0 | 0 | 0 | 0 | 0 | 0 | 347.407.100 | 383.380.350 | 383.380.350 | 383.380.350 |
2025.DKTU.4.002 | 0 | 0 | 0 | 349.999.644 | 5.803.465.780 | 6.526.032.857 | 6.526.032.857 | 6.641.777.745 | 6.656.466.182 | 6.656.466.182 |
2025.DKTU.6.001 | 0 | 0 | 0 | 0 | 0 | 0 | 573.664.000 | 646.464.000 | 646.464.000 | 646.464.000 |
TOTAL REALISASI | 44.371.716 | 52.928.680 | 53.256.133 | 441.604.955 | 5.995.233.703 | 6.730.445.103 | 7.932.059.668 | 9.223.861.175 | 9.932.946.975 | 10.386.660.882 |
REALISASI BAYAR (KOMULATIF)
Sumber data :
Hingga 31 Agustus 2025
Terbayar Luncuran : Rp 53.256.133
Terbayar Murni : Rp 6.677.188.970
Total Terbayar : Rp 6.730.445.103
Siap Bayar Unit : Rp 212.578.465
Proses VIP : Rp 573.664.000
Siap Bayar VIP : Rp 394.070.459
Total Prognosa Terbayar : Rp 7.978.723.027
Hingga 10 Juli 2025
Terbayar Luncuran : Rp 53.256.133
Terbayar Murni : Rp 421.816.147
Total Terbayar : Rp 475.072.280
Siap Bayar Unit : Rp 2.157.464.633
Proses VIP : Rp 3.199.730.284
VIP Menunggu Bayar : Rp 1.292.248.365
Total Prognosa Terbayar : Rp 7.124.515.562
KOMITMEN BAYAR BULAN DESEMBER 2025
SIAP BAYAR : Berkas di UP2D siap untuk diupload di VIP (belum terupload VIP)
PROSES VIP : berkas sudah di VIP tapi belum lolos verifikator pusat
SIAP BAYAR VIP : berkas sudah di VIP dan sudah lolos verifikator pusat, menunggu pembayaran
SIAP BAYAR UNIT | 0 |
PROSES VIP | 17.511.709 |
SIAP BAYAR VIP | 0 |
TERBAYAR | 488.391.875 |
TOTAL | 505.903.584 |
Sumber data :
PRK | URAIAN KONTRAK | TERMIN BAYAR | JENIS | RP RENCANA | SIAP BAYAR UNIT | PROSES VIP | SIAP BAYAR VIP | KETERANGAN |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Samarinda-Sangatta Zona 1 #3 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | Tagihan Tanpa Pajak | 11.061.987 | ✅ | ✅ | ❌ | Revisi berkas vendor - AKI kurang |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Berau-Kaltara #1 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | Tagihan Tanpa Pajak | 11.244.572 | ✅ | ✅ | ✅ | Terbayar |
2025.DKTU.4.001 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #1_UP3 Balikpapan PT.PLN (Persero) UP2D Kaltimra | 1 | Tagihan Tanpa Pajak | 44.018.571 | ✅ | ✅ | ✅ | Terbayar |
2025.DKTU.4.001 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #2_UP3 Kaltara PT.PLN (Persero) UP2D Kaltimra | 1 | Tagihan Tanpa Pajak | 356.965.714 | ✅ | ✅ | ✅ | Terbayar |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Balikpapan #4 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | Tagihan Tanpa Pajak | 6.449.722 | ✅ | ✅ | ❌ | Revisi berkas vendor - AKI kurang |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Kaltara-Nunukan #2 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 1 | PPN & PPh | 28.975.701 | ✅ | ✅ | ✅ | Terbayar |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Balikpapan #4 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 1 | PPN & PPh | 17.182.694 | ✅ | ✅ | ✅ | Terbayar |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Samarinda-Sangatta Zona 1 #3 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 1 | PPN & PPh | 29.470.222 | ✅ | ✅ | ✅ | Terbayar |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Samarinda-Sangatta Zona 2 #3 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | PPN & PPh | 534.401 | ✅ | ✅ | ✅ | Terbayar |
| | | | | | | | |
RENCANA BAYAR DESEMBER 2025 (505.903.584)
Sumber data :
60 | 2025.DKTU.4.001 | 0009.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Samarinda-Sangatta Zona 1 #3 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | 11.061.987 |
61 | 2025.DKTU.4.001 | 0006.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Berau-Kaltara #1 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | 11.244.572 |
62 | 2025.DKTU.4.001 | 0018.KR/DAN.01.03/F14050000/2025 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #1_UP3 Balikpapan PT.PLN (Persero) UP2D Kaltimra | 1 | 44.018.571 |
63 | 2025.DKTU.4.001 | 0017.KR/DAN.01.03/F14050000/2025 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #2_UP3 Kaltara PT.PLN (Persero) UP2D Kaltimra | 1 | 356.965.714 |
64 | 2025.DKTU.4.001 | 0007.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Balikpapan #4 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | 6.449.722 |
65 | 2025.DKTU.4.001 | 0008.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Kaltara-Nunukan #2 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 1 | 28.975.701 |
66 | 2025.DKTU.4.001 | 0007.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Balikpapan #4 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 1 | 17.182.694 |
67 | 2025.DKTU.4.001 | 0009.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Samarinda-Sangatta Zona 1 #3 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 1 | 29.470.222 |
68 | 2025.DKTU.4.001 | 0010.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Samarinda-Sangatta Zona 2 #3 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | 534.401 |
Tagihan Tanpa Pajak | 429.740.566 |
Tagihan Tanpa Pajak | |
Tagihan Tanpa Pajak | |
Tagihan Tanpa Pajak | |
Tagihan Tanpa Pajak | |
PPN & PPh | 76.163.018 |
PPN & PPh | |
PPN & PPh | |
PPN & PPh |
NO | PRK | NO KONTRAK | URAIAN KONTRAK | TERMIN BAYAR | NILAI TAGIHAN |
KETERANGAN | RENCANA BAYAR DESEMBER |
RENCANA BAYAR JANUARI 2026
Sumber data :
69 | 2025.DKTU.4.001 | 0008.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Kaltara-Nunukan #2 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | 10.876.363 |
70 | 2025.DKTU.4.001 | 0018.KR/DAN.01.03/F14050000/2025 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #1_UP3 Balikpapan PT.PLN (Persero) UP2D Kaltimra | 2 | 2.316.767 |
71 | 2025.DKTU.4.001 | 0017.KR/DAN.01.03/F14050000/2025 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #2_UP3 Kaltara PT.PLN (Persero) UP2D Kaltimra | 2 | 18.787.670 |
72 | 2025.DKTU.6.001 | 0025.SPK/DAN.01.01/F14050000/2025 | Pengadaan Alat Uji Sarana Pemeliharaan Kubikel PT PLN (Persero) UP2D Kaltimra | 1 | 191.582.500 |
73 | 2025.DKTU.4.001 | 0006.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Berau-Kaltara #1 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | 1.576.665 |
74 | 2025.DKTU.4.001 | 0009.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Samarinda-Sangatta Zona 1 #3 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | 1.551.064 |
75 | 2025.DKTU.4.001 | 0007.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Balikpapan #4 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | 904.352 |
76 | 2025.DKTU.4.001 | 0018.KR/DAN.01.03/F14050000/2025 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #1_UP3 Balikpapan PT.PLN (Persero) UP2D Kaltimra | 1 | 6.172.095 |
77 | 2025.DKTU.4.001 | 0017.KR/DAN.01.03/F14050000/2025 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #2_UP3 Kaltara PT.PLN (Persero) UP2D Kaltimra | 1 | 50.052.203 |
Tagihan Tanpa Pajak | 283.819.679 |
Tagihan Tanpa Pajak | |
Tagihan Tanpa Pajak | |
Tagihan Tanpa Pajak | |
PPN & PPh | |
PPN & PPh | |
PPN & PPh | |
PPN & PPh | |
PPN & PPh |
NO | PRK | NO KONTRAK | URAIAN KONTRAK | TERMIN BAYAR | NILAI TAGIHAN |
KETERANGAN | RENCANA BAYAR JANUARI |
RENCANA BAYAR fEBRUARI 2026
Sumber data :
78 | 2025.DKTU.4.001 | 0008.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Kaltara-Nunukan #2 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 2 | 1.525.036 |
79 | 2025.DKTU.4.001 | 0018.KR/DAN.01.03/F14050000/2025 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #1_UP3 Balikpapan PT.PLN (Persero) UP2D Kaltimra | 2 | 324.846 |
80 | 2025.DKTU.4.001 | 0017.KR/DAN.01.03/F14050000/2025 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #2_UP3 Kaltara PT.PLN (Persero) UP2D Kaltimra | 2 | 2.634.326 |
81 | 2025.DKTU.6.001 | 0025.SPK/DAN.01.01/F14050000/2025 | Pengadaan Alat Uji Sarana Pemeliharaan Kubikel PT PLN (Persero) UP2D Kaltimra | 1 | 24.312.500 |
PPN & PPh | 28.796.708 |
PPN & PPh | |
PPN & PPh | |
PPN & PPh |
NO | PRK | NO KONTRAK | URAIAN KONTRAK | TERMIN BAYAR | NILAI TAGIHAN |
KETERANGAN | RENCANA BAYAR FEBRUARI |
REALISASI TERBAYAR KOMULATIF AI UP2D KALTIMRA 2025
PRK | MARET | APRIL | MEI | JUNI | JULI | AGUSTUS | SEPTEMBER | OKTOBER | NOVEMBER | DESEMBER |
2024.DKTU.4.001 | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% |
2025.DKTU.4.001 | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 98% |
2025.DKTU.4.001.8400 | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% |
2025.DKTU.4.002 | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% |
2025.DKTU.6.001 | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% |
TOTAL | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% | 100% |
REALISASI BAYAR TERHADAP TARGET (KOMULATIF)
Sumber data :
PROGRESS PEKERJAAN AI UP2D KALTIMRA 2025
Sumber data :
NO PRK | NO KONTRAK | DESKRIPSI PEKERJAAN | TANGGAL | VOLUME | PROGRESS | ||
AWAL | AKHIR | TARGET | REALISASI | ||||
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Samarinda-Sangatta Zona 1 #3 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 14/03/2025 | 08/01/2026 | 6 | 6 | 100% | |
2025.DKTU.4.001 | 0010.KR/DAN.01.03/F14050000/2025 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Samarinda-Sangatta Zona 2 #3 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 14/03/2025 | 28/11/2025 | 3 | 3 | 100% |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Kaltara-Nunukan #2 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 14/03/2025 | 28/11/2025 | 7 | 7 | 100% | |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Balikpapan #4 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 14/03/2025 | 08/01/2026 | 6 | 6 | 100% | |
2025.DKTU.4.001 | Pengadaan Aksesoris Non MDU dan Jasa Pemasangan Keypoint_Tersebar_Berau-Kaltara #1 pada Lokasi PT PLN (Persero) UP2D KALTIMRA | 14/03/2025 | 28/11/2025 | 8 | 8 | 100% | |
2025.DKTU.4.001 | Pengadaan Aksesoris Pengadaan Material Non MDU konektor dan skun PT PLN (Persero) UP2D KALTIMRA | 24/03/2025 | 21/04/2025 | 1 | 1 | 100% | |
2025.DKTU.4.001 | Pengadaan Material Non MDU pembesian & arde PT PLN (Persero) UP2D KALTIMRA | 20/03/2025 | 07/06/2025 | 1 | 1 | 100% | |
2025.DKTU.4.001 | Pengadaan Material Non MDU cover PT PLN (Persero) UP2D KALTIMRA | 25/03/2025 | 17/05/2025 | 1 | 1 | 100% | |
2025.DKTU.4.001 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #1_UP3 Balikpapan PT.PLN (Persero) UP2D Kaltimra | 24/04/2025 | 24/01/2026 | 1 | 1 | 100% | |
2025.DKTU.4.001 | Pekerjaan Jasa Bongkar Pasang Kubikel pada Gardu Hubung (GH)_Tersebar #2_UP3 Kaltara PT.PLN (Persero) UP2D Kaltimra | 23/04/2025 | 20/01/2026 | 12 | 12 | 100% | |
2025.DKTU.4.001 | Pengadaan Modem untuk Integrasi SCADA PT PLN (Persero) UP2D Kaltimra | 03/06/2025 | 02/08/2025 | 30 | 30 | 100% | |
2025.DKTU.4.001 | Pengadaan Alat Uji Circuit Breaker Ringan dan Portable Guna Kehandalan Otomasi Kubikel Pada PT PLN (Persero) UP2D Kaltimra | 28/05/2025 | 26/08/2025 | 1 | 1 | 100% | |
2025.DKTU.4.001 | Integrasi RTU GH Sedadap PT PLN (Persero) UP2D Kaltimra | 28/05/2025 | 27/07/2025 | 1 | 1 | 100% | |
2025.DKTU.4.001 | Pengadaan Alat Uji Baterai Smart Record Untuk Otomasi Report Pada PT PLN (Persero) UP2D Kaltimra | 13/06/2025 | 12/08/2025 | 1 | 1 | 100% | |
2025.DKTU.4.001 | PENGADAAN LOAD BREAK SWITCH TAHUN 2025 | 24/12/2025 | 24/03/2026 | 0 | 0 | #DIV/0! | |
2025.DKTU.4.001 | PENGADAAN LIGHTNING ARRESTER TAHUN 2025 | 24/12/2025 | 23/04/2026 | | | | |
NO PRK | NO KONTRAK | DESKRIPSI PEKERJAAN | TANGGAL | VOLUME | PROGRESS | ||
AWAL | AKHIR | TARGET | REALISASI | ||||
2025.DKTU.4.002 | 0005.KR/DAN.01.03/F14050000/2025 | Pengadaan dan Pemasangan Radio Komunikasi Digital Bontang | 12/03/2025 | 25/06/2025 | 13 | 13 | 100% |
2025.DKTU.4.002 | 0004.KR/DAN.01.03/F14050000/2025 | Pengadaan dan Pemasangan Radio Komunikasi Digital Berau | 12/03/2025 | 25/06/2025 | 15 | 15 | 100% |
2025.DKTU.4.002 | 0003.KR/DAN.01.03/F14050000/2025 | Pengadaan dan Pemasangan Radio Komunikasi Digital Sei Fatimah Nunukan | 12/03/2025 | 11/05/2025 | 2 | 2 | 100% |
2025.DKTU.4.002 | 0031.KR/DAN.01.01/F14050000/2025 | Pengadaan Radio Komunikasi Handy Talky PT PLN (Persero) UP2D Kaltimra | 29/08/2025 | 28/09/2025 | 5 | 5 | 100% |
NO PRK | NO KONTRAK | DESKRIPSI PEKERJAAN | TANGGAL | VOLUME | PROGRESS | ||
AWAL | AKHIR | TARGET | REALISASI | ||||
2025.DKTU.6.001 | 0003.PJ/DAN.01.01/F14050000/2025 | Pengadaan Rectifier Dan Baterai Pada PT PLN (Persero) UP2D Kaltimra | 20/05/2025 | 18/08/2025 | 7 | 7 | 100% |
2025.DKTU.6.001 | 0025.SPK/DAN.01.01/F14050000/2025 | Pengadaan Alat Uji Sarana Pemeliharaan Kubikel PT PLN (Persero) UP2D Kaltimra | 15/10/2025 | 29/12/2025 | 1 | 1 | 100% |
MONITORING MDU AI UP2D KALTIMRA 2025
Sumber data :
MATERIAL MDU | TOTAL | KETERANGAN | GUDANG MATERIAL TIBA | KENDALA | |||||||
ONSITE | BELUM ONSITE | UP2D | BPP | SMD | NST | BRU | BTG | KTA | |||
LBS | 22 | 22 | 0 | 0 | 2 | 8 | 0 | 4 | 1 | 7 | |
LBS 3 WAY | 3 | 3 | 0 | 0 | 2 | 1 | 0 | 0 | 0 | 0 | |
Recloser | 5 | 5 | 0 | 0 | 1 | 0 | 0 | 3 | 0 | 1 | |
Lightning Arrester | 189 | 189 | 0 | 189 | 0 | 0 | 0 | 0 | 0 | 0 | |
Isolator Polymer | 90 | 90 | 0 | 90 | 0 | 0 | 0 | 0 | 0 | 0 | |
Cubicle | 12 | 12 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 12 | |
FCO | 60 | 60 | 0 | 60 | 0 | 0 | 0 | 0 | 0 | 0 | |
Connector dan Skun | 757 | 757 | 0 | 757 | 0 | 0 | 0 | 0 | 0 | 0 | |
Pembesian dan ARDE | 256 | 256 | 0 | 256 | 0 | 0 | 0 | 0 | 0 | 0 | |
Cover MDU | 273 | 273 | 0 | 273 | 0 | 0 | 0 | 0 | 0 | 0 | |
PROGRESS MONITORING MDU AI UP2D KALTIMRA 2025
Sumber data :
STATUS | JENIS MDU | PABRIKAN (PT) | VARIAN MDU | VOLUME | RUPIAH NILAI KR | BATAS WAKTU | UP3 BPP | UP3 SMD | UP3 BTG | UP3 BRU | UP3 KTA | UP3 NST | UP2D KTKU | TOTAL | |
ONSITE | LBS | PT Prima Mitrainti Sejati | Motorized + RTU | 12 | 1.343.791.530 | 23 Mei 2025 | 2 | 4 | 1 | 2 | 3 | | | 12 | |
ONSITE | Lightning Arrester | PT Insindo Inti Abadi | Polymer 24 kV | 189 | 801.990.360 | 8 Juni 2025 | | | | | | | 189 | 189 | |
ONSITE | LBS | PT Arlisco Elektrika Perkasa | Motorized + RTU | 10 | 1.121.874.780 | 12 Juni 2025 | | 4 | | 2 | 4 | | | 10 | |
ONSITE | Isolator Polymer | PT Gunabangsa Teknik Industri | Dead End Polymer | 90 | 258.940.199 | 29 Agustus 2025 | | | | | | | 90 | 90 | |
ONSITE | Cubicle | PT Arlisco Elektrika Perkasa | Fully GIS CBOG Motorized | 10 | 2.305.720.860 | 11 September 2025 | | | | | 10 | | | 10 | |
ONSITE | Cubicle | PT Arlisco Elektrika Perkasa | Fully GIS Metering | 2 | 2.305.720.860 | 11 September 2025 | | | | | 2 | | | 2 | |
ONSITE | Recloser | PT Prima Mitrainti Sejati | with RTU | 3 | 594.057.711 | 20 Juli 2025 | | | | 2 | 1 | | | 3 | |
ONSITE | Recloser | PT Ines | with RTU | 2 | 394.601.624 | 24 Juni 2025 | 1 | | | 1 | | | | 2 | |
ONSITE | FCO | PT Duta Terang Rubberindo | 24 kV | 60 | 691.989.583 | 26 Mei 2025 | | | | | | | 60 | 60 | |
ONSITE | Connector dan Skun | PT SERAMBI GAYO SENTOSA | | 757 | 38.874.509 | 21 April 2025 | | | | | | | 757 | 757 | |
ONSITE | Pembesian dan ARDE | PT ELECTRA INTI PERKASA | | 256 | 85.761.621 | 7 Juni 2025 | | | | | | | 256 | 256 | |
ONSITE | Cover MDU | PT SERAMBI GAYO SENTOSA | | 273 | 26.519.983 | 17 Mei 2025 | | | | | | | 273 | 273 | |
ONSITE | LBS Three Way | PT Duta Terang Rubberindo | Three Way | 1 | 355.244.400 | 29 September 2025 | 1 | | | | | | | 1 | |
ONSITE | LBS Three Way | PT Entec Electric Indonesia | Three Way | 2 | 710.488.800 | 10 Oktober 2025 | 1 | 1 | | | | | | 2 |
Terima Kasih
REKAPITULASI PENYERAPAN Ao 2025
21.661.254.184 |
AO TERBIT
AKO TERBIT
TERKONTRAK
RENCANA KONTRAK
TERBAYAR
MURNI
21.566.258.221
21.566.258.221
TERKONTRAK + RENCANA
Persentase “Terkontrak” terhadap AO Terbit
Persentase “Rencana Terkontrak” terhadap AO Terbit
Persentase “ Terkontrak + Rencana” terhadap AO Terbit
Persentase “Terbayar” terhadap AKO Terbit
0 |
21.283.112.662 |
21.661.254.184 |
98,93% |
0,00% |
97,20% |
98,93% |
Sumber data :
PANTAUAN REALISASI AO UP2D KALTIMRA 2025
98,93% |
TERKONTRAK TERHADAP AO |
Sumber data :
97,20% |
TERBAYAR TERHADAP AKO |
PANTAUAN REALISASI AO UP2D KALTIMRA 2025
Sumber data :
DESKRIPSI ANGGARAN | PRK | AO | AKO | TERKONTRAK | % TERHADAP AO | SISA AO | TERBAYAR | % TERHADAP AKO | SISA AKO |
PRK.7256.25.10.02.01.001 | 1.104.740.413 | 1.104.740.413 | 1.099.900.134 | 99,56% | 4.840.279 | 1.013.123.518 | 91,71% | 91.616.895 | |
LAYANAN KOMUNIKASI / APN UNTUK OPERASI PERALATAN DISTRIBUSI (AMR) | PRK.7256.25.10.02.01.002 | 3.538.432.000 | 3.538.432.000 | 3.343.095.223 | 94,48% | 195.336.777 | 3.343.105.223 | 94,48% | 195.326.777 |
PEMELIHARAAN FASILITAS MASTER STATION & KOMUNIKASI REALTIME & KOMUNIKASI DATA | PRK.7256.25.10.02.01.003 | 1.331.218.882 | 1.331.218.882 | 1.331.218.882 | 100,00% | 0 | 1.331.218.882 | 100,00% | 0 |
PEMELIHARAAN PERALATAN MODEM DAN SISTEM RADIO KOMUNIKASI | PRK.7256.25.10.02.01.004 | 4.053.242.100 | 4.053.242.100 | 4.053.238.226 | 100,00% | 3.874 | 3.978.868.226 | 98,17% | 74.373.874 |
PEMELIHARAAN RUTIN RTU DAN PERIPHERAL | PRK.7256.25.10.02.01.005 | 1.847.648.234 | 1.847.648.234 | 1.847.648.234 | 100,00% | 0 | 1.843.964.144 | 99,80% | 3.684.090 |
PEMELIHARAAN SISTEM PROTEKSI, METER DAN KEYPOINT (RECLOSER, LBS, FI, FS DAN ASS) | PRK.7256.25.10.02.01.006 | 1.582.339.228 | 1.582.339.228 | 1.568.558.667 | 99,13% | 13.780.561 | 1.367.968.661 | 86,45% | 214.370.567 |
LAYANAN JARINGAN SCADA DISTRIBUSI | PRK.7256.25.10.02.01.007 | 5.089.726.656 | 5.089.726.656 | 5.089.726.656 | 100,00% | 0 | 5.089.726.656 | 100,00% | 0 |
PEMELIHARAAN GEDUNG GARDU HUBUNG & PEMBUMIAN | PRK.7256.25.10.02.02.008 | 1.492.258.998 | 1.492.258.998 | 1.472.399.382 | 98,67% | 19.859.616 | 1.459.668.572 | 97,82% | 32.590.426 |
PEKERJAAN PENUNJANG DISTRIBUSI | PRK.7256.25.10.02.02.009 | 656.506.250 | 656.506.250 | 656.338.083 | 99,97% | 168.167 | 656.338.083 | 99,97% | 168.167 |
SPPD PEMELIHARAAN DISTRIBUSI | PRK.7256.25.10.02.02.010 | 705.353.680 | 705.353.680 | 705.341.062 | 100,00% | 12.618 | 705.341.062 | 100,00% | 12.618 |
SISTEM PENGELOLAAN STOCK MATERIAL GUDANG DAN BENGKEL DISTRIBUSI | PRK.7256.25.10.02.02.011 | 124.791.780 | 124.791.780 | 124.791.780 | 100,00% | 0 | 124.791.780 | 100,00% | 0 |
PENGADAAN PERALATAN K3L UNTUK GH, KEYPOINT DAN KANTOR | PRK.7256.25.12.00.01.012 | 150.000.000 | 150.000.000 | 149.993.190 | 100,00% | 6.810 | 149.993.190 | 100,00% | 6.810 |
MELAKSANAKAN KEGIATAN PENDUKUNG KONDISI IKLIM KERJA | PRK.7256.25.12.00.01.013 | 30.000.000 | 30.000.000 | 29.942.250 | 99,81% | 57.750 | 29.942.250 | 99,81% | 57.750 |
MELAKSANAKAN KEGIATAN SOSIALISASI INTERNAL DAN EKSTERNAL | PRK.7256.25.12.00.01.014 | 30.000.000 | 30.000.000 | 29.981.100 | 99,94% | 18.900 | 29.981.100 | 99,94% | 18.900 |
PEMBUATAN SISTEM KEBAKARAN, KEDARURATAN, DAN KEAMANAN | PRK.7256.25.12.00.01.015 | 134.000.000 | 134.000.000 | 133.995.315 | 100,00% | 4.685 | 133.995.315 | 100,00% | 4.685 |
MELAKSANAKAN KEGIATAN SIMULASI & REFRESH DAMKAR TANGGAP DARURAT DAN KEGIATAN BULAN K3 NASIONAL | PRK.7256.25.12.00.01.016 | 26.000.000 | 26.000.000 | 25.086.000 | 96,48% | 914.000 | 25.086.000 | 96,48% | 914.000 |
TOTAL | 21.896.258.221 | 21.896.258.221 | 21.661.254.184 | 98,93% | 235.004.037 | 21.283.112.662 | 97,20% | 613.145.559 | |
RENCANA TERKONTRAK Ao UP2D KALTIMRA 2025
Sumber data :
| TOTAL RENCANA KONTRAK : | 0 | | |
PRK | URAIAN PEKERJAAN | RP FPP | RENCANA TERKONTRAK | PROGRESS RENCANA KONTRAK |
PRK.7256.25.10.02.01.002 | Pembayaran Indosat M2M Managed Connectivity Periode Bulan Desember 2025 | | JANUARI | Rencana Januari 2026 |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |