WOODS & CREEK RESTORATION�
August 2026 to Spring 2027
Current Conditions
Invasives choking out the sun needed for native growth
Undercut banks making trails unsafe
Sidewalk floods 2025
Stream not connected to floodplain
Vertical streambanks
Culvert restricts water flow
How has the creek changed over time?
What to do?
Ask the Woods & Creek Subcommittee!
Here’s what they said:
Use natural restorative techniques, following the Dept. of Natural Resources Toolkit for stream stabilization and restoration practices.
THEY SAY DO THIS!
…NOT THAT!
Meet 🡪
Photo taken September 18, 2025
The Environmental Science Team at Snyder Engineering was hired to design a master plan.
Creek Restoration Design
Master Plan Goals
Remove invasive species:
Hired Prairie Fire Restoration through September 2026.
Stabilize streambanks:
Regrade to 1:3 slope, install root wads using downed trees in critical section of the creek.
Increase flood capacity:
Remove culvert and sidewalk and install a 70’ bridge over a gentler sloping, more naturally flowing stream with benches to collect water overflow in high rain events.
Master Plan Remediation Strategies
Improve water quality:
Create benches and revegetate streambanks to filter out sediments, build 3 bioretention cells to capture stormwater runoff, and slow down water velocity by reconnecting the floodplain to the stream and creating more rock riffles.
Repurpose downed trees:
Use trees to install root wads for creek stabilization and to build nature playscapes in the woods.
Restore the woods and trail system with Genus Landscaping:
Create new trails in the woods and along the creek with two
creek crossings, plant native grasses, woodland seed mixes and trees and improve trail accessibility for all members.
Remediation Strategies, cont’d.
Rock riffles slow down the water velocity.
Excavator inserts tree trunk into the stream bank by its roots.
Root wads are inserted into the stream bank.
Creek Restoration Design
Revegetate slopes by live staking
stream banks.
Effects of stabilization
Stable stream banks help prevent future erosion.
Excavator!�Coming in August 2026 � parking lot access disrupted�Coming in September Bridge!
What is the creek going to look like?
What happens after the stream restoration?
Short-term Impact
Long-term Benefit
How will we engage in the woods and creek as a congregation?
Meet Genus Landscaping!
Genus Landscaping
Project Ideas
More Possibilities: Playground and Patio
Grant Funding:�
IDALS 50/50 Match Grant Awarded $212,000 (Exact amount to be negotiated in June)
Our 50% portion is up to $106,000.
Grant Applications Submitted:
Was this Amos Emery’s original vision to be the front of the church? YES!