1 of 9

ERP Modernization

Program Review

BAC Meeting

April 29 2026

2 of 9

Executive Summary

All program spending is bond funded (2020 and 2025)

Program continues to be on track

Current focus is on:

  • Contract approvals
  • Detailed planning for summer and early fall work
  • Mitigating internal resource constraints

3 of 9

Program Objectives: �Digital Transformation

A tightly coordinated multi-year program to redesign how

people, processes, and technology work together to

streamline work and unlock better outcomes.

The opportunity is to devote more time, resources,

and energy toward student learning and success.

The challenge is to build efficient workflows,

driven by meaningful data using modern tools,

that result in better decision-making across PPS.

3

This transformation will be enabled by the implementation of a new ERP that best serves PPS for the long-term

We do not currently have the tools - technology, processes, data - that are required to run a modern K-12 district

4 of 9

Scope of Impact:

Business Functions

  • 8,000+ system users
  • 1,000’s of vendors & contractors
  • 100’s of reporting requirements
  • $2B budget to manage

5 of 9

Vendor Summary

Function / Responsibility

Vendor

Details

Contract Holder

Program Management

Plante Moran

Responsible for scope, timeline, budget

Plante Moran

Change Management

Percipio

Responsible for the strategy, plan and execution that drives PPS staff adoption of the new ways of working

Percipio

Business Process Design

Workday + Accenture + Meridian

Partnering with PPS business leads, build the processes that modernize PPS functional operations

Meridian

System Configuration & Test Cycles

Workday + Accenture + Meridian

Based on the new business process design, configure the Workday platform to optimize for PPS use both short term and long term

Meridian

Post Deployment Support for 12 months

Workday + Meridian

Managed service to ensure PPS has a stable platform after go-live as well as best prepare us to support ourselves moving forward

Meridian

Workday User Licenses for 10 years

Workday + Meridian

PPS’s use of the new ERP platform through the end of FY35-36

Meridian

6 of 9

Contract Details

Contract

Contract Holder

Original Proposal Cost

Final

Cost

ERP - Implementation SOW

Meridian

$19.8M

$14.9M

Workday Order Form - 10 years of licenses

Meridian

$13.8M

$12.9M

Change Management SOW

Percipio

$2.2M

$3.5M

Program Management SOW

Plante Moran

$1.7M

$1.5M

EUNA Licenses (10 yrs)

EUNA

Est. $1.4M

$1.4M

EUNA Implementation SOW

EUNA

$0

$29K

DebtBook Licenses (10 yrs)

DebtBook

Est. $1M

$967K

DebtBook Implementation SOW

DebtBook

$0

$9K

Application Mgmt Support (post deployment support)

Meridian

$525K

$525K

TOTAL

$40.4M

$35.7M

7 of 9

Next Steps - Contracts

  1. Meridian contracts - Implementation SOW and Workday licensing (10 years)
    • Those contracts represent $28M or 78% of the planned contract spend
    • On track to be submitted end of this week per timeline for inclusion on May 12 consent agenda
  2. Program Mgmt (Plante Moran) and Change Mgmt (Percipio)
    • Both SOW’s already with PPS ready for signature
    • Represents $3M or 14% of spend
  3. Remaining contracts (EUNA, DebtBook, post deployment support)
    • In total, less than $3M or 8% of the planned contract spend
    • Presented as Not To Exceed for review via board memo

8 of 9

Program Phases

& Tentative Dates

Business Process Alignment

Aligns PPS’s current processes with Workday standards, identify gaps, and build consensus before designing the Workday platform.

Detailed Planning *

Establish governance, timelines, and resource alignment to ensure a structured and disciplined deployment.

Architect & Configure

Design and build the Workday solution based on PPS requirements, using best practices and pre-built accelerators.

Hypercare

Provide intensive post-go-live support to stabilize the system, resolve issues quickly, and ensure user adoption.

Test & Train

Validate the solution through multiple testing cycles to ensure accuracy, usability, and readiness for deployment.

Deployment

Prepare for and executes go-live(s), including final data validations, training, and communications to support a smooth transition.

June - October

October

November ‘26 - September ‘27

Oct ‘27 - Jan ‘28*

Feb - April ‘28

*Timeline may change based on Detailed Planning phase

9 of 9

Appendix