1 of 143

1

LUNAR LAPTOP

PROGRAM PROPOSAL

The Presenters:

Shiba ShivaPrakash

Prasanna Kumar

Jeyaraman

Gowtham Nageshwar Rao

Rugvedi Kesare

2 of 143

AGENDA

  • Present the Proposal for the LUNAR, which will take the place of the current MS B2 laptop.

​

  • To get approval to implement the Lunar Laptop program. 

2

3 of 143

Executive Summary

3

We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.

We have identified a comprehensive set of Program Plans required to successfully execute the program.

We have the right infrastructure, latest technology, correct tools, experienced & talented team

We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.

We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM

4 of 143

We Followed MS 8 Step Proven Process For LUNAR Program

​

​

4

Step 1:

Market Research and Company Requirements 

We have company's proven program plan to execute for MS LUNAR program

Step 2:

Product Plan 

Step 4:

Risk Analysis & Mitigation Plan with Monte Carlo Analysis

Step 3:

Finance Plan

With Risk Budget

Step 5:

Product Plan

Step 6:

Iterations

Step 7:

Best Value Solution 

Step 8:

Project Execution 

5 of 143

Executive Summary

5

We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.

We have identified a comprehensive set of Program Plans required to successfully execute the program.

We have the right infrastructure, latest technology, correct tools, experienced & talented team

We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.

We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM

6 of 143

6

We have analyzed company and market requirements to develop MS LUNAR

Requirement Analysis

Market Analysis

Competitor Analysis

MS LUNAR

We Clearly Understand The Market And Company Requirements To Develop MS LUNAR

7 of 143

7

MS B2 – Launched 2016

  • Launched for competing in MID-TIER.
  • Sales Reduced to 2.8M. By 2021.
  • Market Value 0.17%
  • Change in Segment Market Trends

MS B1 – Launched 2018

  • Launched for competing in PREMIUM Markets
  • Annual Sales increased to 5.5 M in 2021 
  •  Market value 0.29%

PHASING OUT MS B2 SALES AND LAUNCH NEW PRODUCT, MS LUNAR FOR MID-TIER SEGMENT IN 2025

MS B1 : 4.8% SEGMENT SHARE

MS B1: 0.21% TOTAL SHARE

MS: 0.47% TOTAL SHARE

DEMAND IN 2025 PEAKS

MID-TIER DEMAND in million

172.5

*FORECAST

We Analysed Current Market Share Of Millennium System

We have analysed the market share and our opportunity to get back our share in 2025!

Clear understanding of the Company & Market Requirements

80% Probability of success

Sales of 6 million units

30% to ROS

$475 per laptop (Wholesale Price)

Growth of market share from 5% to 10%

COMPANY REQUIREMENTS

7

8 of 143

8

We Have Performed Extensive Analysis Of The Market With Nielsen For Mid-tier Laptop Requirements

We have conducted detailed survey to understand market requirements and translated it into product features

Company & Market Requirements Market Survey & Requirements

GEOGRAPHIC

PRICE

DEMOGRAPHICS

FEATURES

COMPETITORS

Target Region: USA[1M], China[2M], India[2M], EUROPE[1M]

  • CHINA
  • INDIA
  • USA & EUROPE
  • $ 450 - 500 Wholesale price
  • Price Sensitive
  • AMD RYZEN 5 Processor
  • Long Battery life
  • 512 GB SSD

PRICE: $475

*Dealer’s Price

Target Market Segment:

 18-35 years of age

  • 65% age group between 18 - 30

​

High end Feature in Mid tier

Customer support & Warranty

  • LENOVO 
  • HP

Selling Points

Features to Delight Customers

High value to money

ANALYSIS

MS TEAM                 NIELSEN

RESULTING REQUIREMENTS

CHINA,INDIA

USA & EUROPE

450-500 WHOLESALE

TARGET AGE – 20 - 35

Smaller screen, attractive colors

Ideapad 3 & 5, pavilion 360

9 of 143

Executive Summary

9

We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.

We have identified a comprehensive set of Program Plans required to successfully execute the program.

We have the right infrastructure, latest technology, correct tools, experienced & talented team

We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.

We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM

10 of 143

10

We Offer Most Competitive Features Of The MS LUNAR​

MS LUNAR have features that will delight customers and the company

Product Plan >>> Competitive Features

POWERFUL PROCESSOR 

8GB DDR5 RAM

COMPACT AND TOP QUALITY DISPLAY

ALUMINIUM BODY

15 HOURS

512 GB SSD

MAJOR FEATURES DERIVED FROM OUR HIGH- END LAPTOP

  • TOUCH SCREEN

​

​

​

​

  • WIRELESS CHARGING

​

​

​

​

​

  • FINGERPRINT SENSOR

​

11 of 143

11

We Conducted Comparison With Major Competitor​s

Product Plan meet Requirements >>> Major Competitors

FEATURES

LENOVO

HP

MS LUNAR

PROCESSOR

INTEL i5

INTEL i5

AMD Ryzen 5

5000 X Series

​

BATTERY

11 HOURS

3.5 HOURS

UP TO 15 HOURS

​

DISPLAY

15” LCD DISPLAY

15” LCD DISPALY

15.6” LCD DISPLAY ANTI-GLARE

STORAGE

256 GB SSD

NO SSD

512 GB SSD

​

FINGERPRINT SECURITY

NO

NO

YES

​

RAM

4GB

8GB

8 GB

PROCESSOR IS BETTER AND ECONOMICAL

    LONGER BATTERY LIFE THAN COMPETITORS

MORE STORAGE THAN COMPETITORS. 

HIGHER PROCESSING SPEED THAN

COMPETITORS  

 MORE SAFE AND SECURE                 

Cost ($)

$ 500

$ 490

$ 475

Offering more at less price than our competitors

BETTER DISPLAY THAN COMPETITORS

We offer more value for money & quality than our competitors

12 of 143

12

Processor​

AMD Ryzen 5 (10th Generation)​

Operating System​

Windows 11 Home​

Display​

15.6" FHD (1920 x 1080) anti-glare, 250 nits​

Memory​

8 GB DDR5 3200MHz​

Battery ​

Up to 15 hrs (45Wh)​

Storage ​

512 GB PCIe SSD​

Ports/Slots ​

USB-C 3.2 Gen 1,USB-A 3.2 Gen 1,USB-A 2.0,HDMI​

Graphics​

Integrated Intel® UHD Graphics​

Dimensions (H x W x D)​

Starting at 19.9mm x 359.2mm x 236.5mm / 0.78" x 14.14" x 9.31" ​

Weight​

Starting at 1.7kg / 3.78lbs​

Color ​

Carbon Gray, Beige Mousse and Bluestone

Audio                  ​

2 x 1.5W speakers with Dolby Atmos Audio™​

Dual microphone​

Connectivity ​

802.11AX (2 x 2) & Bluetooth® 5.1​

Camera​

720p HD​

 

​

We Have Used Comprehensive Approach To Plan For Detailed Specification

We offer good Quality and competitive features in the mid tier​ laptop

Product Plan >>> Complete Specification

13 of 143

13

ONLINE MARKETING STRATEGIES

OFFLINE MARKETING STRATEGIES

  • NEWSPAPERS
  • MAGAZINES

PRINT MEDIA

  • FACEBOOK
  • YOUTUBE
  • INSTAGRAM

SOCIAL MEDIA

SEARCH ENGINE OPTIMIZATION

  • COMPANY WEBSITE
  • CUSTOMER DATABASE

WEBSITE AND EMAILS

STRATEGIC PARTNERS

SALES FORCE NETWORKING

We have proven marketing plan to approach our target customers.​

​

We Have A Solid And Proven Marketing Strategy In Place

​

Product Plan >>> Marketing Strategy

14 of 143

14

Social media marketing video clip

Product Plan >>> Marketing Strategy

15 of 143

15

  • MS B1 is targeted to Higher end of market whereas LUNAR is targeted at Mid tier.
  • Target Market, Customer requirements are different.
  • MS B1 has higher end configuration features that are not offered in Lunar.

Product Development

  • Utilize design, technology developed from MSB1

Profit Driving

  • Low costs due to utilization of MS B1 components suppliers and processes

Customer Loyalty

  • Delighting customers with new in tier features
  • High value for money product

Globalization

  • Using the existing sales & distribution channels of Millennium Systems

Competitive Advantage

  • No technology development costs
  • No new vendor selection

ADVANTAGES DOES NOT AFFECT MS B1

AND WE HAVE THE CONSENSUS FROM MS B1 TEAM

LUNAR has Distinctive Advantages Using MS B1 Technology

We are bringing High end market features from MS B1 to offer in mid-tier laptop MS LUNAR

Clear understanding of the Company & Market Requirements

16 of 143

16

We Have Opportunity To Meet The Market And Company Requirements

We have successfully analyzed requirements, market and competitive analysis and have developed the product that will delight customers and company. 

Product Plan meet Requirements

Requirement Analysis

Market Analysis

Competitor Analysis

MS LUNAR

17 of 143

Executive Summary

17

We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.

We have identified a comprehensive set of Program Plans required to successfully execute the program.

We have the right infrastructure, latest technology, correct tools, experienced & talented team

We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.

We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM

18 of 143

18

Financial Solution>> Company Requirements

80% Probability of success (POS)

Sales of 6 million units

30% Return on Sales (ROS)

$475 per laptop (Wholesale Price)

Growth of market share from 5% to 10%

COMPANY REQUIREMENTS

We have a Clear Understanding of Company Requirements to generate Solid Business Solution 

We have a laptop with better Capabilities and Features than our Competitors at a Lower Price 

Our Company Requirements Meet the desired goals to execute the Program Successfully 

19 of 143

Cost($) w/o HP

$ 98.78

$ 19.73

$ 25.96

$ 44.25

$ 25.87

$ 26.43

$ 18.45

$ 20.98

$ 25.92

$ 21.96

$ 14.00

$ 30.00

$ 369.33

​

​

MS Lunar Laptop Can Meet Unit Cost Requirement Of $332.5 After Tax

Financial Solution that will generate the required profit and a 30% ROS

Cost Element

Cost ($)

Program Cost ($).               

Hardware component

 $ 87.00

 $ 522,000,000

Management Reserve

 $ 19.94

 $ 119,640,000

Risk & Opportunities

 $23.96      

 $ 143,640,000

Development Cost

 $ 24.75   

 $ 118,500,000 

 Labor 

 $ 20.66   

 $ 93,960,000

Manufacturing 

 $ 20.80 

 $ 124,800,000

Packaging   

 $ 12.94   

 $ 47,640,000 

Procurement 

 $20.98    

 $ 125,880,000   

Advertisement 

 $25.92   

 $ 155,520,000

Customer Support 

 $20.85     

 $ 125,100,000

Warranty & Returns 

 $ 8.76

 $ 142,560,000

Miscellaneous 

 $30.74     

 $ 184,440,000

Total Cost Before Taxes 

 $317.3    

 $ 1, 903,800,000   

Tax

 $15.20 

$ 91,200,000

Total Cost After Taxes

 $332.5

$ 1,995,000,000

42% Savings

36% Savings

16% Savings

80% Savings

28% Savings

$52.00

Savings per Unit

$475

Wholesale Rate

Min 30% ROS

Risk Analysis

Cash Flow Model at 80% POS

18

$142.5 

Profit per Unit

We have a laptop with better Capabilities and Features than our Competitors at a Lower Price 

20 of 143

20

Target Units Sold

6,000,000

Unit Cost (Wholesale) 

$475 

Return of Sales 

30%

Cost per unit 

$332.50 

Sales Revenue

$2,850,000,000

COGS (Cost of Goods Sold)

$1,995,000,000

Tax Rate

25%

EBIT ( Earnings Before Interest & Tax)

$855,000,000

Tax

$213,750,000

NET PROFIT - AFTER TAX

$641,250,000

PRODUCTION:

6 million units

1.2 B

Program Cost

$146 M

Management Reserve

$19 M Total Risk & Opportunity Budget

We Have Developed A Comprehensive Cash Flow Model To Achieve A 30% Ros At 80% POS

We have a Solid Financial plan with a profit of 641M considering a Risk & Opportunity Budget at 30% ROS & 80%

Developing Business solution >> Financial Model with risk analysis

19

​

​

Replacement 

Units: 

70,050

​

21 of 143

21

Net Profit at 30% ROS

 $641,250,000 

Management Reserve

=$146,211,840

PHASES

TOTAL PHASE COST

       % ALLOCATION

Market Planning

$ 29,508,900

1.55%

Placement & Acceptance

$ 26,653,200

1.40%

Project Definition

$ 15,991,920

0.84%

Implementation

$ 365,719,980

19.21%

Launch & Closeout

$ 289,187,220

15.19%

Production

$ 634,726,920

33.34%

Customer Support

$ 395,800,020

20.79%

Management Reserve

$ 146,211,840

7.68%

Total Budget COST

$ 1,903,800,000

​

100.00%

Our Total Budget with 30% ROS

We Have A Required Phase-wise Budget To Be Successful & Provide A 30% ROS

We have developed a Risk Adjusted Phase-Wise Budget with MR 7.6% at 80% POS 

Developing Business solution >>> Financial Model with phase-wise budget allocation

20

Cost: 

$ 475/Unit

22 of 143

22

We Have Performed a Breakeven Analysis to Execute the Program at 30% ROS 

We have a successful Business Solution to achieve 30% ROS at 80% POS with Net Profit of $641 M  

Financial Plan Generated 30% ROS >>> NPV vs IRR

Break-even at 

Month 24

PRODUCTION RATE

21

80k​

22

280k​

23

560k​

24

700k​

Maximum Expense

$275,151,000

Project NPV

680,255,000 

Project IRR

9.56%

21

23 of 143

23

RISK IDENTIFICATION

    • Identification of risk in each phase.

RISK PRIORITIZATION

    • Probability of Risk
    • Impact of Risk($)
    • Risk Number
    • Prioritization of risk

MITIGATION

    • Risk mitigation plans
    • Mean mitigation budget

ANALYSIS

    • Crystal Ball and Sensitivity Analysis for the total risk mitigation budget

IMPLEMENTATION

    • Implementation of some Mitigation plans  to reduce the Risk Budget.
    • Crystal Ball analysis to get 80% POS

ITERATION

    • Iteration of MR values to get to a 80% POS for the risk budget as well as the Total program budget.

Detailed Risk & Opportunity mitigation planning with Monte Carlo Analysis is established

We have followed MS’ Proven Procedure for Conducting Risk & Opportunity Analysis

We have followed the Risk and Opportunity Analysis procedure to achieve 80% of POS

A solid  MS LUNAR design and business solution >>>  Risk Analysis Procedure

22

24 of 143

24

We have IDENTIFIED RISK and IMPLEMENTED BUDGET to achieve 80% POS !

We Have Identified Phase-wise Risks, Cost associated with it and implemented Budget to achieve desired POS

A solid MILLENIUM SYSTEMS design & business solution >>> Risk Tracking & Impact

23

25 of 143

25

We have performed a comprehensive analysis to IDENTIFY OPPORTUNITY and MITIGATE RISK at 80% POS !

We Have Identified Phase-wise Risks, Opportunities & Mitigation Plan To achieve desired POS

A solid MILLENIUM SYSTEMS design & business solution >>> Risk Tracking & Impact

23

26 of 143

26

PHASE

RISK

OPPORTUNITY

Software Failure

Manufacturing & Design Incompatibility

Inefficient Vendors

Over Allocation of Resources

Failed Market Research

Poor Access to Service Centers

Labor Strike

V

IV

III

II

I

VII

VI

Update to a more robust software

Optimize Manufacturing & Design Process

Enhance Procurement Process

Reduce the budgeted units/time allocation

Have Data Collected

Provide easy online services and 24*7 support

Improve relationship with labor workforce

$ 295,000

$ 400,000

$ 100,000

$3,545,000

$2,500,000

$8,800,000

$2,300,000

$17,940,000

$ 210,000

$ 300,000

$ 1,495,000

$ 995,000

$ 2,000,000

$ 1,000,000

$ 2,000,000

$8,000,000

Risk mitigation budget       

Opportunity implementation 

Budget

We have identified opportunities with a mitigation & implementation budget of 25M at 80% POS  

WE HAVE RISK MITIGATION & OPPORTUNITY BUDGET TO ACHIEVE 80% POS WITH ROS 30%

A solid MS LUNAR design & business solution >>Opportunity identification >> Risk & Opportunity budget

24

27 of 143

27

At 30% ROS

PROFIT: $641 M

80.00% POS

We have achieved 80% POS for Net Profit of $ 641 M at 30% ROS>> Successful Program

We Have Performed A Monte Carlo Analysis At 80% POS

Risk Mitigation & Opportunity projects for 80% POS >>> Monte Carlo Analysis

26

28 of 143

28

2. Comprehensive Cash Flow

 1. Unit Cost Requirement

3. Phase Wise Budget

4. Break Even Analysis

Coupled with the Risk Analysis, this gives us confidence in generating a 30% ROS

We Have Performed A Comprehensive Financial Analysis To Ensure We Meet The 80% POS, Starting With :-

Financial Plan Generated 30% ROS

27

29 of 143

29

Monte Carlo Analysis

Comprehensive analysis for the Risk & Opportunity was followed accordingly

We Have Done The Risk Mitigation & And Opportunities Analysis And Achieved An 80% Pos That Meets The Company Requirements

Risk Mitigation & Opportunity projects 80% POS

28

Phase-wise risks and costs

Risk Mitigation & Opportunity Implementation Plans

Risk & Opportunity Analysis

30 of 143

Executive Summary

30

We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.

We have identified a comprehensive set of Program Plans required to successfully execute the program.

We have the right infrastructure, latest technology, correct tools, experienced & talented team

We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.

We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM

31 of 143

31

MPP

SOW

OBS-WBS MATRIX

IMP

EVMS

CRITICAL PATH

EVMS

WBS

OBS

We Have A Comprehensive Set Of Program Plans In Place To Successfully Execute The Proposed Program

We have all the detailed plans required in place to successfully execute the LUNAR project.

Identified a comprehensive set of Business Plans 

32 of 143

32

Identified a comprehensive set of Business Plans >>> Checklist Plan 

PLANS

PHASE1:

Marketing Research

PHASE2:

Placement& Acceptance

PHASE3:

Product Design

PHASE4:

Implementation

PHASE5:

Launch & Close-Out

PHASE6:

Production

PHASE7:

Customer Support

Master Program Plan

✔️

✔️

✔️

✔️

✔️

✔️

✔️

Work Breakdown Structure

✔️

✔️

✔️

✔️

✔️

✔️

✔️

Integrated Master Schedule

✔️

✔️

✔️

✔️

✔️

✔️

✔️

Critical Path

✔️

✔️

✔️

✔️

✔️

✔️

✔️

Organizational Breakdown Structure

✔️

✔️

✔️

✔️

✔️

✔️

✔️

Control Accounts

✔️

✔️

✔️

✔️

✔️

✔️

✔️

EVMS

✔️

✔️

✔️

✔️

✔️

✔️

✔️

WBS,OBS Matrix

✔️

✔️

✔️

✔️

✔️

✔️

✔️

Integrated Master Plan

​

✔️

✔️

✔️

✔️

✔️

✔️

✔️

We Have Developed A Checklist Of Plans To Successfully Execute The MS Lunar Program

We have all the detailed plans required in place to successfully execute the LUNAR project.

33 of 143

33

Program Plan with Management Tools >>> Master Program Plan

WE HAVE DEVELOPED A COMPREHENSIVE MASTER PROGRAM PLAN (MPP) For MS LUNAR Laptop Program

We have overall plan ready to execute ‘LUNAR’.

      LUNAR

34 of 143

34

Comprehensive set of plans >>> WBS

Phase-1

Market Research

Phase-2

Placement & Acceptance

Phase-3

Project Definition

Phase-4

Implementation

Phase-5

Launch & Closeout

Phase-6

Production

Phase-7

Customer Support

1.1    Management Authorises Phase ½ Limited Funding

1.2    Initial Business Case SWOT analysis

1.3    Opportunity objectives

1.4    Corporate Strategy Check 

1.5    Concept Brief and Conceptual Product Outline 

1.6    Business Case Refinement 1 1.7   Marketing & Product Plan

 1.8  Technical Recommendations

1.9 Customer Survey

1.10 Business Case Refinement2 

1.11 Realistic Technical Specifications

1.12 Financial Analysis 

1.13 Legal

1.14Business Model 

1.15 Phase 1 Goal Completion Date

​

​

​

​

​

2.1    Resource strategy product team

2.2    Control charts(WBS)

2.3    Technology, Architecture & Platform strategy

2.4    Solution lockdown for concept

2.5    Baseline feature descriptions

2.6    Budgetary estimates

2.7    Staffing plan

2.8    Product Life-cycle

2.9    Project Control(IMP,IMS)

2.10  Management Review/Decision to invest

3.1    Project business review

3.2    Staffing plan

3.3    Product technical specifications

3.4    Intellectual property review

3.5    Technical requirements allocation

3.6 Technical Requirements Allocation

3.7 Business / Manufacturing Requirements Allocation 

3.8 System Analysis, Modeling, and Simulation 

3.9   Product/system test strategy

3.10  Subcontractor

3.11  Manufacturing strategy

3.12  Program commitment statement

3.13  Management Involvement

3.14 Project Management Plan for Implementation Phase 

3.15  Sourcing

3.16  Supply chain logistics & distribution requirements

3.17 Phase 3 Goal Completion Date 

​

4.1   Subsystem specifications

4.2   Test specifications

4.3   Supply chain management

4.4   Subcontractors

4.5   Product/system

4.6   Critical design review(CDR)

4.7   Documentation & training

4.8   System test

4.9   Manufacturing systems & processes

4.10  Sourcing

4.11  Intellectual property review

4.12  Project plan

4.13  Manufacturing materials

4.14  Ready for field test

4.15  Manufacturing systems & processes

4.16  Sourcing

4.17  Prototype testing

4.18  Marketing artefacts

4.19  Ready for product rollout/deployment

4.20  Product/system

4.21 Phase 4 Goal Completion Date

​

5.1   Project staffing plan for launch and close-out phase

5.2   Intellectual property review

5.3 Manufacturing Systems and Processes

5.4   Sourcing

5.5   Cost management

5.6   Launch preparation activities

5.7   Training and documentation

5.8   Project business review

5.9   Project plan

5.10   Manufacturing engineering support

5.11  Warranty repair center

5.12 Phase 5 Goal Completion Date

​

6.1   Product/system

6.2   Manufacturing systems and processes

6.3 Sourcing 

6.4 Cost Management 

6.5 Final Business Review

6.6 LRIP 

6.7 FRP

6.8 Project Lessons Learned

6.9   Project Lessons learned

6.9 Retirement Plan Approved

6.10 Product Lessons Learned

7.1 Staffing Plan

7.2 E-Commerce Management

7.3 Call Center Operations

7.4 Back Logistics

7.5 Product Data Management

��

Work Breakdown Structure (Wbs) Developed To Meet The Requirements Of Sow Using A Phased Approach 

All criteria required to accomplish current phase must be reviewed and approved by program management prior to proceeding to the next phase

35 of 143

35

Integrated Master Schedule Has Been Developed For All Phases Of The Lunar Lifecycle (Example Phase 3)

All phases of the LUNAR lifecycle are defined. Schedule and required costs are identified and leveled.

36 of 143

36

Program Plan with Management Tools >>> Statement of Work

Statement Of Work Is Completely Defined And Identified​

Objective: Our Millennium Systems LUNAR laptop program is to become a leading Laptop in Mid-tier Market​

​

Scope of work:Program includes all planning, execution, implementation, and training ​

​

Period of performance: The period of performance for the MS LUNAR laptop program project is 48 months​

​

Schedule of milestones: START:Market Planning September 1st ,2022. END: Customer Service 2nd September, 2026​

​

Acceptance criteria: The acceptance of all deliverables will reside with MS Marketing Head​

​

 

​

SOW Example – Phase 1

SOW Methodology is defined and identified for each phase of the project​

37 of 143

37

Critical Path Has Been Determined For Each Phase �Of The Ms LUNAR Program (Example – Phase 4)

Critical Path for all phases of the LUNAR program have been identified.

38 of 143

38

We Have Developed The Organizational Breakdown Structure (OBS) For The LUNAR Program

Complete Organizational Breakdown Structure has been defined.

Marketing

Forecasting

Market Research

Public Relations

Content Development

Manufacturing

Inventory Procurement

Research & Development

Finance

Business Models

Accounting

Accounting And Billing

Administration

Hr

Knowledge Transfer

Project And Program Managemnt

Project Manager

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

39 of 143

39

Identified a comprehensive set of Business Plans >>> EVMS 

The MS LUNAR Earned Value Management System (EVMS) �Will Be Utilized

EVMS is used majorly in our project to keep track of our Project Goals and Checkpoints.

40 of 143

40

Program Plan with Management Tools >>> OBS & OBS-WBS Matrix

We Have Developed The Organizational Breakdown Structure (Obs)

For The MS LUNAR Program AND Have Developed The Wbs Vs Obs Matrix Which Has Been Linked And Cost Accounts Determined

Every task is tracked to a specific Cost Account from OBS/WBS Matrix

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

41 of 143

41

Program Plan with Management Tools >>> Integrated Master Plan

We Have Developed INTEGRATED MASTER PLAN (IMP) FOR THE MS LUNAR PROGRAM

Integrated master plan has been developed with entry and exit criteria, for each of the phases

42 of 143

42

Identified a comprehensive set of Business Plans 

MPP

SOW

OBS

WBS

IMP

IMS

CRITICAL PATH

EVMS

 ✓

✓

✓

✓

✓

✓

✓

WBS

OBS

✓

✓

We Have A Comprehensive Set Of Program Plans In Place To Successfully Execute The LUNAR Program 

We Have all the Detailed Plans Required in Place to Successfully Execute the LUNAR Project.

43 of 143

Executive Summary

43

We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.

We have identified a comprehensive set of Program Plans required to successfully execute the program.

We have the right infrastructure, latest technology, correct tools, experienced & talented team

We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.

We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM

44 of 143

44

Right Infrastructure, Latest Technology, Correct tools, Experienced Team

We Have The Right Resources In Place To Succeed

We are equipped with the necessary tools and procedures to be successful.

Right Experience

Required Tools

Proven Processes

Right Infrastructure

Experienced and Available Talent

MS LUNAR

45 of 143

We have the right experience required to successfully implement the MS LUNAR program

45

Right Infrastructure, Latest Technology, Correct tools, Experienced Team

We Have Taken Advantage of Experience Gained from Previous Programs to Guide the Project in the Right Direction

MS B2 (previous Mid-tier Laptop)

MS B1 (Current High-end laptop)

Network of Suppliers and Distributors

Design Features

Customer Support Experience

Research and Development

Market Analysis

High-End Features

Project Team

​

Manufacturing Unit

​

The gains from our previous programs include:

Right Experience

Required Tools

Proven Processes

Right Infrastructure

Experienced and Available Talent

MS LUNAR

46 of 143

46

Right Infrastructure, Latest Technology, Correct tools, Experienced Team

We have PROVEN TOOLS Required to Successfully Implement the Program

We Have the Required and Proven Tools in Place!

    • Balsemic Mockups
    • Wireframe Sketcher
    • Axure

Design

    • Kaizen
    • Plan-Do-Check-Act (PDCA)
    • 5S
    • ISO 9000
    • Lean / Six Sigma

Manufacturing

    • Benchmarking
    • Failure Modes & Effects Analysis (FMEA)
    • Quality Function Deployment (QFD)
    • Total Quality Management (TQM)

Quality

    • Local Reseller Preliminary Customer Support
    • 24/7 MS Secondary Support
    • Existing Proven Customer Support Methodology from MS B2

Customer Support

Right Experience

Required Tools

Proven Processes

Right Infrastructure

Experienced and Available Talent

MS LUNAR

47 of 143

47

Right Infrastructure, Latest Technology, Correct tools, Experienced Team

We have the PROVEN PROCESS required to successfully implement the program

We Have a Robust Starting Point for this New Venture!!

Phase I

Market

Planning

Phase II

Placement &

Acceptance

Phase III

Project

Definition

Phase IV

Implementation

Phase V

Launch &

Closeout

Phase VI

Production

Phase VII

Customer Support

48 Months

We Have A Successful Proven Strategy In Place

All 7 Phases of Laptop Lifecycle Have been Carefully Evaluated and Accounted For!

Right Experience

Required Tools

Proven Processes

Right Infrastructure

Experienced and Available Talent

MS LUNAR

48 of 143

48

Right Infrastructure, Latest Technology, Correct tools, Experienced Team

We have the PROVEN INFRASTRUCTURE required to successfully implement & run the program

We Have the Appropriate Infrastructure to execute MS LUNAR program! 

Manufacturing

Texas, U.S.A

Customer Support

Colorado , U.S.A

Assembly

Texas, U.S.A

R & D

Colorado, U.S.A

Headquarters

Colorado, U.S.A

Right Experience

Required Tools

Proven Processes

Right Infrastructure

Experienced and Available Talent

MS LUNAR

49 of 143

49

Right Infrastructure, Latest Technology, Correct tools, Experienced Team

We have the PROVEN INFRASTRUCTURE required to successfully implement & run the program

We Will Leverage Existing Resources to Market Effectively, Optimize Cost, and Lower Risks! 

Right Experience

Required Tools

Proven Processes

Right Infrastructure

Experienced and Available Talent

MS LUNAR

Millennium Systems

Manufacturing Facilities

Assembling Facilities

Research & Development Center

Marketing Department

Marketing Strategy

Sales & Acquisitions

Vendors & Suppliers Department

Raw Materials, Parts & Spares

Distributors

Wholesalers

Headquarters

Warranty & Customer Support Centers

Administrative Department

50 of 143

50

Right Infrastructure, Latest Technology, Correct tools, Experienced Team

We have the talent required to successfully implement the program

We Have A Highly Experienced Team!

Right Experience

Required Tools

Proven Processes

Right Infrastructure

Experienced and Available Talent

MS LUNAR

Program Director: 

Viraj Patel

Deputy Program Director: 

Blake Lively

Project Manager:

Dileep Edara

Product Development Manager:

Shreya Reddy

Administrative manager:

Ravi Radadiya

Quality Control Manager:

Vigneshji

Finance Manager: 

Harshada Khatale

Marketing Manager:

Prateek Jat

Manufacturing Manager:

Shrey Sachan

20 years VP Product Development at IBM

10 years VP operations at Samsung

SAFe 4.0 Advanced Scrum Master

6 sigma certified

Organizational Structure For Phase 1

51 of 143

51

Right team in place with the right experience > Proven Processes 

We Have The Right Resources In Place To Succeed

We are equipped with the necessary tools and procedures to be successful.

Right Experience

Required Tools

Proven Processes

Right Infrastructure

Experienced and Available Talent

MS LUNAR

52 of 143

52

We have all the Required Resources and Processes in Place to Succeed!

Keys to MS LUNAR Success

  • We have a clear understanding of the requirements for the Lunar Laptop:
    • To delight the customer from a comprehensive market analysis
    • Lunar Laptop meets all market and company requirements
    •  We have better laptop capabilities than our competition and features at a lower price
  • We have a Solid Lunar Laptop Design and Business Solution
    • To make the required profit for the MS shareholders by achieving sales of 6 Million units in 48 months with 80% Probability of success, and achieving 30% ROS

53 of 143

53

We have all the Required Resources and Processes in Place to Succeed!

  • We have a Comprehensive Set of Integrated Program Plans in place
    • We have prepared the detailed plans to begin the program execution
    • All phases of LUNAR Laptop are understood and required resources are identified and leveled
  • We have the right Experience, Tools, Processes, Infrastructure, and Talent in place
    • We have taken advantage of experience gained from previous programs to guide the project in the right direction
    • Leveraged existing resources as needed to market effectively, optimize cost and lower risks

Keys to MS LUNAR Success

54 of 143

Executive Summary

54

We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.

We have identified a comprehensive set of Program Plans required to successfully execute the program.

We have the right infrastructure, latest technology, correct tools, experienced & talented team

We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.

We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM

55 of 143

55

We seek your approval today to begin the execution of the program

​

56 of 143

56

Back Up Slides

​

57 of 143

57

Table of Content of Story Board

CONTENT

SLIDE NO

1

2

3

4

5

6

7

8

9

10-11

12

13-16

17

18

19

20-21

22

23

24

25-26

27

28

29

30

58 of 143

58

Table of Content of Story Board

CONTENT

SLIDE NO

31

32

33

34

35

36

37

38

39

40

41

42

43

44-45

46

47

48-49

50

52-53

54

​

​

​

​

​

​

​

​

59 of 143

59

TABLE OF CONTENTS

SLIDE NO

60

61

62

63

72

77

80

81

82

83

84

85

88

89

90 

91 

92 

93

95

96

97

98

99

100

TABLE OF CONTENTS

SLIDE NO

102

104

105

106

108

109

110

111

113

114

115

116

125

127

134

136

137

141

142

 

 

 

 

 

 

 

 

 

 

60 of 143

  1. How many MS B2 Laptops are there in market?
  2. How many MS B1 Laptops are there in market?
  3. Is 7.5% Market share taken from the competitors or the market itself has grown? 
  4. Why would I buy a MS LUNAR laptop instead of a Lenovo Laptop?
  5. Who are going to buy MS LUNAR Laptop?
  6. What are the terms and conditions with our vendors?
  7. What have we been doing to market MS B1 Laptops in India and China? Do we have any experience there?  How do we intend to tackle those markets?
  8. How was the market research performed?
  9. How can we assure the quality of the product?

60

Product development Q&A

61 of 143

61

FINANCE

  1. How much % of sales are we expecting to get from each country for MS LUNAR Laptop? What if we don’t meet our sales?
  2. Sales Justifications
  3. Breakeven number of units to sell
  4. What will be the recurring and non-recurring costs?
  5. Is that built into the financial plan in detail?
  6. What’s built into the financials for repair and replace costs and risks?

RISK

  1. Effect of MS LUNAR on MS B1 Laptop
  2. Division of Resources for MS LUNAR laptop and MS B1 laptop
  3. Loss in market share
  4. How do we minimize technical risk?
  5. What is the highest risk in this project?
  6. Is this project taking the right amount of risk?
  7. How do we take advantage of the organizational learning that results from the risk management program and activities?

RISK AND FINANCE Q&A

62 of 143

62

PLANNING Q&A

  1. What does the production schedule look like? Is that built into the financial plan in detail?
  2. How can you assure the quality of your product?
  3. How did you obtain your customer feedback to feel assured about your production?
  4. How can you say that your interaction with other departments has been? Especially with the finance department since they work so closely with you?
  5. In every phase, how did you make sure your performance is on track?
  6. What does the pay-scale look like for various employees in your company?
  7. How many prototype laptops are built?

63 of 143

63

How many MS B1 laptops are there in market?

  • 13 Million total MS B1 Laptops in the market.
  • China has 45%  of 13 Million is 1.8 Million MS B1 Laptops
  • India has 17%  of 13 Million is 680,000 MS B1 Laptops
  • US has 15% of 13 Million is 0.6 Million MS B1 Laptops

Product development Q&A

How many MS B2 Laptops are there in market?

  • 7 Million MS B2 Laptops in the market
  • China has 40%  of 5 Million is 2 Million MS B2 Laptops
  • India has 25%  of 5 Million is 1.25 Million MS B2 Laptops
  • US has 20% of 5 Million is 1 Million MS B2 Laptops
  • Europe has 15% of 5 Million is 0.75 Million MS B2 Laptops

64 of 143

Is 10% Market share taken from the competitors or the market itself has grown? 

  • The world market is growing, and we are expecting to increase our share from companies which are going down in market share (E.g: HP & LENOVO).

​

Why would I buy a MS LUNAR instead of a HP or a LENOVO ?

  • MS LUNAR Laptops are targeted for mid-tier users.
  • Added benefits of having more features for a lower price.
  • More value for “$”. 

64

Product development Q&A

65 of 143

65

Terms and Conditions For Vendors and Customers

For Suppliers

​

Terms: 

• Product quality upon delivery.

• Delivery on schedule.

• Prompt assistance and responses.

• Additional supplies for demand periods.

​

Conditions: 

• The product provided must be unique to MS.

• MS holds the option for contract renewal or rejection every three years.

• Obey the MS-written nondisclosure agreement.

For Clients

​

Terms: 

  • The product comes with a one-year warranty.
  • An extended warranty of one year is an option.
  • The first year of service is free.

​

Conditions: 

  • The warranty is only valid for technical issues.
  • Water damage and theft prevention is not covered by the warranty.
  • Within one month of purchase, buyers must register to receive an extended warranty.

What are the terms and conditions with our vendors Customers?

66 of 143

  • Collaterals

MS and the supplier have an agreement that, in the event that the supplier is unable to achieve quality criteria for its product, the supplier will promptly reimburse MS for 30% of the contract's cash, and MS will return the collateral once the standards are met. 20% of the collateral (or 6% of the overall contract) will be retained by MS for each month the provider is late meeting the quality level.

  • Termination

If a vendor violates a material term of the contract in terms of quality control or shipment delay that hinders the business's growth, MS has the authority to void the current contract agreement with the vendor.

If MS decides to cancel or modify the order, it will be responsible for paying 5% of the contract amount within the first year, 25% of the contract amount between years one and two, 60% of the contract amount between years two and three, and 100% of the contract amount if the modification is made after three years.

If MS must end the contract because of poor supplier quality or a delivery delay, then

66

Vendor/Supplier Agreements

67 of 143

Quality: The shipment should contain the correct documentation for the quality inspections that MS requires. Only when MS's internal quality inspection, which can involve testing the finished product, is successful will the consignment pass the quality procedure.

  • The primary responsible party for creating quality plans and quality inspection checklists will be MS. Vendor must follow the quality procedures that MS specifies, and if they are not followed, they will be penalized, and their contract may be terminated.

Delivery: Vendors must deliver the package by the stated date and time.

Vendor must notify MS in advance if there will be a shipment delay, and MS is free to choose alternative vendors to make up for the delay. Payment for the shipment will not be released until the vendor and buyer have agreed on a penalty for the delay; this amount will then be subtracted from the total amount due for that particular shipment.

Arbitration: MS and supplier industries agree to settle any disputes through binding arbitration rather than in court, with the caveat that small claims court may be used in certain circumstances.

67

Vendor/Supplier Agreements

68 of 143

Who are going to buy MS LUNAR Laptops ?

  • MS LUNAR Laptops are targeted to a specific demographic users (middle income, youths(18- 35 age group)) and offers all the benefits of a higher end Laptop.

68

Product development Q&A

69 of 143

MS will have standard Terms and Conditions with vendors containing the following samples pulled from the full T&Cs document.

6.0 PRICING; INVOICING; PAYMENT:

  6.1 Seller shall sell to Buyer the Goods or  Services shown on the face of the Order at the price �   specified.  All prices are inclusive of applicable freight charges and duties unless otherwise agreed.   

  6.2 Seller warrants that the prices charged for the Goods or Services are not higher than those charged �   to any other customer or Buyer site for Goods of like grade and quality in similar quantities or for �   similar Services performed by skilled personnel.

12.0 TERMINATION:

  12.1 Buyer may terminate the Order in whole or in part at any time in the manner specified in Section 12.3 upon the occurrence of certain events, including but not limited to:

  i. Default by Seller with respect to cost competitiveness, delivery, quality, failure to maintain technology, or other   obligation under the Order, or�   ii. Insolvency of Seller, filing by Seller of a voluntary petition in bankruptcy, filing of any involuntary petition to have Seller   declared bankrupt, provided the same is not vacated within thirty (30) days from the date of such filing, or the execution   by Seller of any assignment for the benefit of creditors.

15.0 RECALL/REPAIR CAMPAIGN:

  15.1 If Seller’s  Goods or  Services create or contribute to a component repair campaign or safety recall due to a component   defect, or non-compliance the Seller shall be liable for costs and damages resulting from a Recall only if the Recall results in   whole or in part from a failure of the Goods to conform to the warranties in Section 7 during the warranty period specified in   the Contract

69

Terms and conditions with vendors and our contract terms and conditions with our customers

70 of 143

What have we been doing to market MS B1 Laptops in India and China? Do we have any experience there?  How do we intend to tackle those markets?

Based on the worldwide success of MS B1 Laptops, we entered the Chinese and Indian market with MS LUNAR Laptops:

  • China:

China has strong manufacturing capabilities. But China does not have a fluctuating market and is not bound by WTO rules. Analyzing the Chinese market, we decided to market MS B1 as a trendy Laptop that is central to the American youth culture. Since American media has a worldwide influence on lifestyle and is emulated by Chinese users, we have captured 40% of the market.

  • India:

India does not have strong manufacturing capabilities but has extensive transportation and is well connected. India also has highest number of younger demographic users. Since the MS B1 Laptops caters well to this niche market, we believe, we have been extremely successful in India with a strong market share of 25%.

70

Product development Q&A

71 of 143

  • Both internal and external analysts and forecasting experts.
  • NIELSEN is the 3rd party consultant (for MS B1and MS B2)
  • Research was done independently.
  • 90% congruency in information from both external and internal.
  • In-line with product development strategies.

71

Product development Q&A

How was the market research performed?

72 of 143

72

73 of 143

73

TARGET SALES

6,000,000 UNITS

SELLING PRICE

$475

COST PER UNIT

$332.50

74 of 143

74

75 of 143

effect of MS LUNAR on MS B1

  • MS B1- Highly Innovative Product, Higher Segment aimed at brand development.
  • MS LUNAR– Premium budget product launched to attain a higher market share.
  • Production- Entire production line is reorganized so that possibility of error which might eventually lower the chance of risk.
  • Cannibalization effect is comparatively nil as both the products are targeted at different market segment.
  • Resource Allocation- Part subset of MS B1 as few of them are in harmony. Few of them are completely different/new as this is a budget laptop with premium qualities.

LOSS IN MARKET SHARE

  • Highest risk mitigation cost $9.9
  • Carrier federations one of the risk mitigation in U.S.
  • Approximately 60-70% sales are observed in the Asia-Pacific region. Low risk mitigation budget as Forex costs can be a positive effect.
  • Projected market share is high in terms of brand acceptance and product acceptance as the target market has been properly aimed for

RISK Q&A

75

76 of 143

division of resources for MS LUNAR and MS B1

  • Change to MS B1
  • Launched MS B1+ whose production is spread for 10 months
  • The current laptop, MS LUNAR production is spread over for 12 months and then 10 months before retirement.
  • Assembly line and production line gets minor changes so that quality is not compromised for the MS LUNAR.

HOW DO WE MINIMIZE TECHNICAL RISK?

  • We leverage technologies from the high-end model.
  • We use off-the-shelf products that have a proven track record.

​

WHAT IS THE HIGHEST RISK IN THIS PROJECT?

  • Failure in software/hardware will have the highest risk value of $317,300.

​

IS THIS PROJECT TAKING THE RIGHT AMOUNT OF RISK?

  • Yes, with over 30 risks identified in this project, the risk mitigation budget has been assigned to each risk to solve the problems when the occur. We have reached an 80% probability of success in this project.

​

HOW DO WE TAKE ADVANTAGE OF THE ORGANIZATIONAL LEARNING THAT RESULTS FROM THE RISK MANAGEMENT PROGRAM AND ACTIVITIES?

  • Management would review the most significant lessons learned from each major business event, surprise and disaster and how it has responded to these findings. These lessons learned will be included in the next project to avoid repeating the same mistake.

76

RISK Q&A

77 of 143

What does the production schedule look like? Is that built into the financial plan in detail?

During the initial phase of the production, we will be using LRIP (Low – Rate Initial Production) and progressively move forward to the FRP (Full rate Production) while the production is in progress. As per our calculations the LRIP would be present for the 2 months period and after that FRP for 10 months to produce 6 million units

​

How can you assure the quality of your product?

We would be doing the FLT*, Certification testing and R&D testing. The R&D testing will be comprising of the following attributes: -

1) Temperature Test

2) Humidity Test

3) Hardware Testing

4) Wifi & Bluetooth Frequency testing

5) Camera test – ISO 100 to ISO 1600

6) Climate Test

7) Thermal shock Test

8) Battery test

We will also make sure that the Laptop is PTCRB, FMPL and AQL certified before entering the market.

*FLT – Factory level testing

77

PLANNING Q&A

78 of 143

How did you obtain your customer feedback to feel assured about your production?

The following are the methods we undertook to get the customer feedback to feel assured about our production:

1) Questionnaires

2) Surveys

3) Focus Groups Interviews

4) Observation

5) Experiments

6) Field trials

How can you say that your interaction with other departments has been? Especially with the finance department since they work so closely with you?

To obtain the budget from the finance department and translating it to the project activities we worked like a cross – functional organization. Our Program lead communicated with the chief financial officer and the allocated budget was delineated to various phase.

78

PLANNING Q&A

79 of 143

In every phase, how did you make sure your performance is on track?

After the Planning has been authorized and the Execution has started, systems engineering will assure the Controlling. Planned date slacks and padding time are allotted to cope with contingencies and conditions in order to complete the project on schedule.

What does the pay-scale look like for various employees in your company?

Every employee group has a different pay scale depending on the variety of skill sets they possess and how crucial they are to the execution of the program.

How many prototype laptops are built?

The majority of the testing will only be done for the hardware and software integration as many of the components in the previous MS laptop have already been evaluated. The LUNAR laptop's numerous features, which the consumers have prioritized, will be tested using 700 prototypes that will be produced. The cost of creating and testing prototypes has been included to the project's development budget.

79

PLANNING Q&A

80 of 143

80

We Have Analyzed The Current Market Hold Scenario

  • 6 Key players majorly dominate the market share; they occupy almost 79% of the market share.
  • MS is one of the players in the “others” category. 
  • Exploring the international market share will prove to be an advantage for MS.

Current market share (Competitors analysis)

81 of 143

81

GEOGRAPHIC SEGMENT IDENTIFIED: USA,EUROPE, CHINA AND INDIA.

GEOGRAPHIC

MARKET SURVEY RESULTS

81

82 of 143

82

CONSUMER REQUIREMENTS (Feature Analysis)

Our product plan is based on customer focused development strategy

Majority is opting for smaller screen

Half of the users choose to buy a laptop of price ranging 450$-550$

Customers are looking for a longer battery life & larger storage space

NIELSEN’s Analysis Report on customer requirements

82

83 of 143

Customer Surveys

  • Past and current MS customers
  • Demographic Information
  • Current price of laptop
  • Feature expectations

​

Vendor Surveys

  • Current distribution trends
  • Their customer's preferences
  • Contract modifications required
  • New contracts

​

NIELSEN HOLDINGS PERFORMED CUSTOMER AND VENDOR SURVEYS

Survey enables MS to build a LAPTOP that the customer wants

83

84 of 143

  • Brand recognition for trustworthy goods 
  • Established Customer service and infrastructure.
  • Existing Manufacturing and Distribution.
  • Innovation and Design.
  • Expanding market for midrange laptops. 
  • Growing advertising for laptops. 
  • Escalating need for high-quality goods.
  • Rapid technological change.
  • Price wars with other competitors.
  • Competitors may launch better 
  • featured laptops.
  • Due to the reduction in MS B2's popularity, competitors have gained customers.

STRENGTH

WEAKNESS

OPPORTUNITY

THREATS

SWOT Analysis

84

85 of 143

Distribution Strategy

Pre-launch and Launch

Growth

Maturity

Decline

to maintain sales levels and allow product sales to occur naturally

to maintain  sales growth  in order to  achieve  desired sales quantities.

follow the trend until the inevitable drop in sales

​

​

​

  • generating buzz to incorporate upcoming product
  • advertising using desirable keywords

85

86 of 143

86

Distribution Strategy

Pre-launch and Launch

Growth

Maturity

Decline

to keep up distribution levels and manage in accordance with market demands

For complete availability of merchandise at sites of sale and adhere as closely as you can to the ultimate users

To distribute product inventories in preparation for exhaustion

​

​

​

Ahead of launch dates, to guarantee that the product is available in the sales channels

86

87 of 143

87

Distribution Strategy

Objective

87

PRE-LAUNCH & LAUNCH

    • To guarantee product availability in retail locations before launch dates

GROWTH

    • to make sure that the product is always available at the point of sale and to be as near the customers as possible

MATURITY

    • To keep up distribution levels and manage in accordance with market demands.

DECLINE

    • To distribute product inventory in anticipation of exhaustion.�
  • Distributors and Wholesalers are the two main distribution networks.
  • Representatives are sent to them in order to obtain their orders and sign agreements.
  • Deals with businesses who operate chain stores all around the nation for special benefits like free travel tickets and the assurance of a long-term business alliance
  • Redistribution of inventory to exhausted markets in accordance with the achievement of sales targets and pulled demand in each market.
  • distribution conferences and promotions.
  • supermarkets, department stores, and neighborhood shops
  • Free merchandise for distributors, including t-shirts, pencils, watches

87

88 of 143

88

PACKAGING WITH PURPOSE:

PROTECTION

SAFETY

ATTRACTIVENESS

SUSTAINABILITY

Should protect the product from humidity, light, heat & other external factors

Consumer safety information must be mentioned in order to cause no harm to the customer

Purpose to standout in the market to enhance sales and increase interest on the product

  • Carbon footprint
  • Re-usability
  • Recyclability 

PRODUCT PACKAGING

PACKAGING IS AS IMPORTANT AS THE PRODUCT ITSELF

88

89 of 143

Promotional Strategy

Our Promotional Strategy Will Meet the Program Plan Requirements

Promotional Strategy

Our Promotional Strategy Will Meet the Program Plan Requirements

89

90 of 143

WE HAVE DEVELOPED BETTER MARKETING PLAN THAN PREVIOUS PROGRAM

Our marketing plan covers all major economy

  • Produce and sell 6 million laptops. 
  • We will use both direct and indirect methods for marketing.
  • Direct sales and Franchised outlets for selling laptops both locally and internationally.

​

​

MS LUNAR PRODUCT LINE

Distributors

Major Retailers

Small Dealers/Retailers

Franchised In-Country Major Outlet Distributors

India

Retailers

Europe & USA

Retailers

China

Retailers

Direct Sales/Marketing Team

*Direct customer – Distributors; *Indirect Customer – Retailers; *Final Customer – Consumer

90

91 of 143

91

WE HAVE COVERED ALL CORNERS OF MARKET USING OUR ADVERTISING STRATEGY

The objective of advertising campaign is to create awareness.

Use social media advertising on platforms such as YouTube and Facebook to play our advertisements.

Target places with high footfalls such as shopping malls, stadiums, amusement parks.

Our Advertisement would look like on of these

Better advertising strategy to connect with potential customers

92 of 143

92

Why is LUNAR going to be the face of the MS & How?​

MS B1

Major Drawback: Overheating issues reported from users

Major Highlight: Can perform Multiple High performance tasks at the same time.

MS B2

Major Drawback: Battery dying quickly

Major Highlight: Expandable RAM & 512SSD disk space

​

​

​

​

MS LUNAR

Upcoming all the Challenges encountered with MS B2 & B1 and taking demanding features from MS which worked in the market by adding new

FACE OF THE COMPANY​

BEST EVER MULTI-TASKING LAPTOP IN MID-RANGE SEGMENT​

92

93 of 143

We Have A Competitive Warranty Plan

We have created Warranty details

  • Details of Millennium System’s WB Program
  • Price: $117 as an extended warranty for 1 year 
  • Deductible: $95
  • Coverage Length: 1 year
  • Number of Replacements Allowed: 2 
  • Time to add the program: within 30 days of purchase 

​

  • Type of Replacement: A Laptop that is new or equivalent to new in both performance and reliability.
  • Replacement Time: For the fastest service, bring the MS WB into the Millennial System’s Store. Convenient service at any local repair shop. Mail-in service is also available. 
  • Cancellation Policy: Buyer can cancel at any time for any reason. If they cancel within 30 days, they will receive a full refund less the value of any service provided. After 30 days, they will receive a pro-rata refund of 10% or the pro-rata amount, whichever is less. 

​

93

94 of 143

We Have A Competitive Warranty Plan

We have created Warranty details

Type of warranty 

  • Warranty coverages 

​

​

​

​

  • Extended warranty

​

​

  •  Replacement
  • Claim amount
  • Covered incidents

Details

  • Plan covers

       i. Mechanical malfunction

      ii. Electrical malfunctions

     iii. Battery

     iv. Technical support(complimentary)

  • $117 for one year.                    

       i. Deductible $95.                      

      ii. Replacement allowed 2 times

  •  New or equivalent to new laptop
  • $1500/claim
  • Loss, theft, physical or liquid damage.

​

94

95 of 143

We Have A Competitive Warranty Plan

Warranty CALCULATIONS

95

Sigma Performance Levels – One to Six Sigma

Sigma Level

Defect for 6mil

Cost of defective Laptops

Warranty cost per laptop

1

4,140,000

 $  621,000,000.00 

$103.50 

2

1,851,222

 $  277,683,300.00 

$46.28 

3

400,842

 $    60,126,300.00 

$20.02 

4

70,050

 $       5,589,000.00 

$8.76

5

5000

 $          209,700.00 

$3.23

6

1000

 $              3,000.00 

$0.00 

Warranty Cost Per Unit = $8.76

 Provide two replacements = 2 x 8.76  = $17.52

A warranty cost of $17.52 have been added indirectly to the unit cost requirement

96 of 143

We Have A Competitive Warranty Plan

Warranty FINE PRINT

  • Two claims within any consecutive 12-month period with a maximum replacement value of $1,500 per claim. Claim limits apply to claims for loss, theft, and physical or liquid damage
  • Buyer can purchase additional coverage for $29.99/month per device. The buyer will receive 2 more shared claims for the account per additional line covered.
  • Same-day screen repair available in Millennium Systems stores. 
  • Replacement Equipment: Replacement equipment may be a new or refurbished device or a comparable model.
  • Covered Incidents: Loss, theft, physical or liquid damage, and mechanical and electrical breakdown (malfunction) due to defects in material workmanship or normal wear and tear. 
  • Cancellation Policy: You may cancel your optional coverage at any time and receive a prorated refund of your monthly charge.

​

96

97 of 143

  • • "Freight Insurance Corporation is obligated to pay for the amount of the freight valued by Millennial Systems in case the product is destroyed during shipment." 
  • "Insurance will only pay for the defective items' freight charges for returned freight that is damaged," 
  • "There is an MS-Protection plan available. For an additional annual registration fee of $39, the plan offers a full product replacement in the event that the product is damaged.

Insurance Agreement

97

98 of 143

  • The customer service strategy is as follows:
  • Constantly checking the Mail-Box and E-Mail account to address the recommendations and complaints of the Customers. A dedicated 24x7 hotline at the Houston Call Center.
  • Every cell laptop has an IMEI number to enable warranty service without an invoice.
  • Service Centers are located in all renowned districts, and they receive regular training to deliver the best service possible.

98

Customer Support Plan

99 of 143

99

 Mockups

Wireframe Sketcher

DESIGN

Kaizen

Plan-Do-Check-Act (PDCA)

5S

ISO 9000

Lean / Six Sigma

Manufacturing

Benchmarking

Failure Modes & Effects Analysis (FMEA)

Quality Function Deployment (QFD)

Total Quality Management (TQM)

Quality

Local Reseller Preliminary Customer Support

24/7 MS Secondary Support

Existing Proven Customer Support Methodology from MS. 

Customer Support

�

PROVEN PRODUCT PLAN FOR MS LUNAR

Take we have proven process and tools required to successfully implement the program away

99

100 of 143

100

  • Determine the sound financial solution that will generate desired profit and ROS of 30%

​

  • Identify Risks, Opportunities & Mitigations analysis required to achieve the POS of 80% for the program

​

FINANCIAL GOALS

100

101 of 143

We have various Warranty OPTIONS

We Have A Competitive Warranty Plan

​

DELL

HP

LENOVO

MS WB

Price (over 2 years)

$210

$195

$177

$117

Deductible per claim

$161

$149

$119

$95

Repair at local service centers

NO

NO

NO

YES

Complementary technical support

YES

YES

NO

YES

Covers any working laptop, old or new from MS

NO

NO

NO

NO

Loss & theft protection

NO

YES

NO

YES

101

102 of 143

Warranty OPTIONS

We Have A Competitive Warranty Plan

Plan Features (per device)

DELL

HP

LENOVO

MS WB

Next day replacement

✔

✔

✔

✔

Accidental damage coverage

✔

✔

✔

✔

Data backup

✔

✔

​

​

Remote tech support

✔

✔

✔

✔

On-site tech support (at buyer's location)

✔

​

​

✔

​

Claims per year allowed

3

2

3

2

Loss and theft protection

​

✔

​

✔

Plan Cost

$33.99/mo

$32.99/mo

$32.99/mo

$29.99/mo

Deductible

up to $161

up to $149

up to $119

up to $95

* $65 fee for three or more claims

​

102

103 of 143

103

We Have A Competitive Warranty Plan

We have done Warranty CALCULATIONS

What the Plan Covers

​

  • Mechanical Malfunction: YES 
  • Electrical Malfunction: YES 
  • Battery: YES, if depletion is 50% or more from original specification 
  • Service Cost: Labor is included. 
  • Complementary technical support

​

104 of 143

104

We Have A Competitive Warranty Plan

We have done Warranty CALCULATIONS

What the Plan Covers

​

  • Mechanical Malfunction: YES 
  • Electrical Malfunction: YES 
  • Battery: YES, if depletion is 50% or more from original specification 
  • Service Cost: Labor is included. 
  • Complementary technical support

​

105 of 143

We Have A Competitive Warranty Plan

Warranty ANALYSIS

​

DELL

HP

Lenovo

MS LUNAR

Warranty Price

$210

$195

$177

$117

105

106 of 143

106

WE HAVE PERFORMED THE SENSITIVITY ANALYSIS TO DETERMINE THE RELATION BETWEEN NET INCOME VS MR

Our What-If Analysis shows that it is not worth removing the MR for a delta increase of 4.97% with net profit of $641M at 30% ROS.

106

107 of 143

107

​

​

Hardware Component

Vendor

Make /Buy

Cost ($)

CPU

BroadCom

​

6.95

Screen 

Lenovo

BUY

5.25

Top Panel

ASUS

BUY

5.35

Base Panel

ASUS

BUY

6.35

RAM

Kingston Technology 

BUY

6.00

Display

Millennium Systems 

MAKE

9.65

Wireless Card

BroadCom

BUY

5.00

Cooling Fan

Thermal take Technology 

BUY

5.50

Battery 

Dynapac

BUY

7.00

Keyboard

Dell

BUY

5.00

Trackpad

Lenovo 

BUY

4.00

Power Connector cable

BroadCom

BUY

6.50

Hard Drive

Kingston Technology 

BUY

7.00

Video Card

Intel

BUY

7.45

Total

​

​

87.00

MAKE OR

BUY

WE HAVE DETAILED ANALYSIS ON MAKE VS BUY

We have based our decision on firm bids with contracts ready to be signed

107

108 of 143

108

​

PER UNIT MAKE

​

TOTAL MAKE

BUY

Purchase Price

10.5

​

​

0

63,000,000

Direct Material 

5

​

30,000,000

​

Direct Labor

2.5

​

15,000,000

​

Variable overhead

1.05

​

6,300,000

​

Fixed Overhead

1.10

​

6,600,000

​

Total Cost

9.65

​

$57,900,000

$63,000,000

We have decided to manufacture display for 6,000,000 Units

$0.85 Per Unit less to MAKE than BUY

108

109 of 143

​

​

​

109

​

Comprehensive Cash Flow

​

Unit Cost Requirement

​

Phase-wise Budget Allocation

​

Impact of MR on ROS

​

Break Even Analysis

​

COMPREHENSIVE FINANCIAL ANALYSIS MODEL TO ENSURE THE POS OF 80%

109

110 of 143

110

WE HAVE ANALYZED THE RECURRING VS NON-RECURRING COSTS TO DETERMINE PROJECT STATISTICS

OUR RECURRING COSTS ARE 3% HIGHER THAN THE PREVIOUS PROPOSALS EXPENSES, DUE TO THE ADDED EMPHASIS SUPPORT AND INCREASE IN PRODUCTION COSTS BASED ON CURRENT EXTERNAL SCENARIOS.

111 of 143

111

WE HAVE THE BUDGET REQUIRED TO BE SUCCESSFUL AND PROVIDE A 30% ROS

Replacement laptops are considered and are a part of the production schedule

Cumulative Production Over 48 Months

112 of 143

112

RISK

PROBABILITY

PRIORITY

 RISK BUDGET ALLOCATION 

MITIGATION PLAN

Market Share Loss

0.25

Moderate

 $      73,77225.00 

Finding the right target market and compiling proper survey data

Understating Competitor's Product

0.2

Low

 $      5901780.00 

Compiling data on weakness and strong attributes of competitor

Overlooking Customer Concerns 

0.22

Moderate

 $      6491958.00 

Gathering feedback of customer via social media, email, phone, etc.

Misleading Information

0.3

Moderate

 $   8852670.00 

Finding the right target market & verifying (doublechecking) the info

Inappropriate Analysis

0.2

Low

 $      5901780.00 

Finding the right target market and compiling proper survey data

TOTAL

​

​

 $   29508900.00 

​

PHASE 1 – RISK MITIGATION(Market Planning)

We have effectively allocated budget to Mitigate Risk for Phase 1

112

113 of 143

113

RISK

PROBABILITY

PRIORITY

 RISK BUDGET ALLOCATION 

MITIGATION PLAN

Reduction/Increment in the Budget

0.24

Moderate

 $        6396768.00 

Calculating accurately total cost of project, management reserve & budget reserve

Uneven Resource Allocation

0.4

High

 $        10661280.00 

Balance the resource plan after every phase

Unsatisfied Customers

0.25

Moderate

 $        6663300.00 

Gathering feedback of customer via social media, email, phone, etc.

Lack of Financial Planning

0.24

Moderate

 $        6396768.00 

Keeping extra management & budget reserve

Change in the Product Life Cycle

0.05

Low

 $        1332660.00 

Plan the schedule according to change

Total

​

​

 $     26653200.00 

​

PHASE 2 – RISK MITIGATION (Placement & Acceptance)

We have effectively allocated budget to Mitigate Risk for Placement & Acceptance

113

114 of 143

​

​

​

1. Risk and Opportunity Analysis

​

2. Risk and opportunity categorization

​

​

4. Risk & Opportunity Budget

​

​

3. Risk Mitigation & Opportunity Implementation Plans

​

​

5. Financial Analysis Tools

​

STEPS FOR RISK MITIGATION & OPPORTUNITIES ANALYSIS TO ACHIEVE THE POS OF 80% THAT MEETS THE COMPANY’S REQUIREMENTS

114

115 of 143

115

PREVIOUS PRODUCTS

RISK MITIGATION BUDGET ($)

MS B0

$28,796,600

MS B1

$27,728,415

MS B2

$26,250,630

LUNAR 2022

​

115

We are taking full advantage of the low tax rate for our project!

 Risk Mitigation Budget = $17,940,000

 Opportunity Budget =  $8,000,000

Total Mitigation Budget = $25,940,000

We are confident because our comprehensive risk analysis resulted in a low-risk program compared to others to prove that we have better opportunity to achieve 80% POS 

We Have A Better Risk Mitigation & Opportunity Implementation Budget !

Low-Risk Budget Program compared to our Competitors

116 of 143

116

We have Explored, Evaluated, and Conducted analysis on various Risks for the Program.

HIGH RISK

Loss in market share

30% profit is not attained

Budget reduction

Delay in critical path

Software failure

MEDIUM RISK

Failed Market Research

Customer Choosing a different Product

Insufficient Vendors

Manufacturing & Design Incompatibility

Product Launch Delay

Defective Products

Unsatisfied Customers

LOW RISK

Change in taxes and cost

Shorter Product Life Cycle

Improper Capacity, Capability Assessment

Under Estimation of Design Budget

Loss of Inventory Resources

Raw Materials Supply Delay

Poor Access to Service centers

Based on the past experiences and the future demand

We have Explored, Evaluated, and Conducted Analysis on various Risks for the Program.

WE HAVE IDENTIFIED PHASEWISE RISK, CATEGORISED AND PRIORITISED THEM

116

117 of 143

117

67.17% POS

Program Budget without MR

Monte Carlo Analysis for Probability of Success W/O MR

A good MR is required to meet the business Goals

117

118 of 143

118

98.27% POS

Monte Carlo Analysis for Probability of Success

Our Cash Flow model is strong and justified

118

119 of 143

Monte Carlo Analysis For Phase 1

119

120 of 143

Monte Carlo Analysis For Phase 2

120

121 of 143

Monte Carlo Analysis For Phase 3

121

122 of 143

Monte Carlo Analysis For Phase 4

122

123 of 143

Monte Carlo Analysis For Phase 5

Monte Carlo Analysis For Phase 5

123

124 of 143

Monte Carlo Analysis For Phase 6

124

125 of 143

Monte Carlo Analysis For Phase 7

125

126 of 143

IMS phases 

126

127 of 143

127

IMS phases 

127

128 of 143

Critical Path for Phase 1

128

129 of 143

129

Critical Path for Phase 2 

129

130 of 143

130

Critical Path for Phase 3

130

131 of 143

131

Critical Path for Phase 4

131

132 of 143

132

Critical Path for Phase 5 

132

133 of 143

133

Critical Path for Phase 6

133

134 of 143

134

Critical Path for Phase 7 

134

135 of 143

135

Phase 1 Gantt Chart

PHASE WISE GANTT CHART ANALYSIS TO KEEP A TRACK OF THE PROJECT.

135

136 of 143

136

Phase 2 Gantt Chart

PHASE WISE GANTT CHART ANALYSIS TO KEEP A TRACK OF THE PROJECT.

136

137 of 143

137

Marketing

MANUFACTURING

Finance

Accounting

Project and Program Management

Planning and Scheduling

Quality Assurance and Control

Customer Service

Complete Organizational Breakdown Structure has been Defined

we have developed the organizational breakdown structure (obs)

for the MS LUNAR program

Complete Organizational Breakdown Structure has been Defined

137

138 of 143

WBS PHASEs

138

139 of 143

Phase-1 Market Resources

​

 1.1 Market Research

 1.2 Initial Business Case SWOT

 1.3 Opportunity Objective

 1.4 Corporate Strategy Check 

 1.5 Concept Brief and Conceptual Product Outline 

 1.6 Business Case Refinement 1 

 1.7Marketing & Product Plan 

 1.8 Technical Recommendations 

 1.9 Customer Survey

1.10 Business Case Refinement2 

1.11Realistic Technical Specifications

1.12 Financial Analysis 

1.13 Legal

1.14Business Model 

1.15 Phase 1 Goal Completion Data

Phase-2 Placement And Acceptance 

2.1 Resource Strategy Product Team 

2.2 Control Charts (WBS)

2.3 Technology, Architecture & Platform Strategy

2.4 Solution Lockdown for the Concept (Conceptual Design)

2.5 Baseline Feature Descriptions

2.6 Budgetary Estimates

2.7 Staff Planning

2.8 Product Life - Cycle 

2.9 Project Control (IMP, IMS)

2.10 Management Review / Decision to invest

139

140 of 143

PHASE 3 Project Definition

3.1 Project Business Review

3.2 Staff Planning

3.3 Product Technical Specification

3.4 Intellectual Property Review

3.5 Preliminary Design Review (PDR)

3.6 Technical Requirements Allocation

3.7 Business / Manufacturing Requirements Allocation 

3.8 System Analysis, Modeling, and Simulation 

3.9 Product / System Test Strategy 

3.10 Sub Contractor

3.11 Manufacturing Strategy

3.12 Program Commitment Statement

3.13 Management Involvement

3.14 Project Management Plan for Implementation Phase 

3.15 Sourcing

3.16 Supply Chain logistics and distribution 

3.17 Phase 3 Goal Completion Date 

PHASE 4 Implementation

4.1 Subsystem Specifications 

4.2 Test Specifications

4.3 Supply Chain Management

4.4 Subcontractors 

4.5 Product / System

4.6 Critical Design Review (CDR) 

4.7 Documentation and Training 

4.8 System Test

4.9 Manufacturing Systems and Processes

4.10 Sourcing

4.11 Intellectual Property Review 

4.12 Project Plan 

4.13 Manufacturing Materials

4.14 Ready for Field Test 

4.15 Manufacturing Systems and Processes

4.16 Sourcing 

4.17 Prototype Testing

4.18 Marketing Artifacts

4.19 Ready for Product Rollout

4.20 Product / Systems 

4.21 Phase 4 Goal Completion Date

140

141 of 143

PHASE 5 Launch and Support

5.1 Project Staffing Plan for launch and close - out phase 

5.2 Intellectual Property Review

5.3 Manufacturing Systems and Processes

5.4 Sourcing 

5.5 Cost Management

5.6 Launch preparation activities

5.7 Training and Documentation

5.8 Project Business Review

5.9 Project Plan 

5.10 Manufacturing Engineering Support

5.11 Warranty Repair Center

5.12 Phase 5 Goal Completion Date

PHASE 6 PRODUCTION

6.1 Product / System

6.2 Manufacturing Systems and Processes

6.3 Sourcing 

6.4 Cost Management 

6.5 Final Business Review

6.6 LRIP 

6.7 FRP

6.8 Project Lessons Learned

6.9 Retirement Plan Approved

6.10 Product Lessons Learned

PHASE 7 Customer Support

7.1 Staffing Plan 

7.2 E-Commerce Management

7.3 Call Center Operational

7.4 Back Logistics

7.5 Product Data Management

141

142 of 143

142

 

​

we have developed the wbs vs obs matrix which has been linked and cost accounts Determined

Every task is tracked to a specific Cost Account from OBS/WBS Matrix

142

143 of 143

143

We have summarized top level program plan which shows an overall picture of what our project timeline looks like.

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

​

PHASES​

MONTHS​

START DATE​

END DATE​

Market Planning​

0-4​

09-01-2022​

01-30-2023​

Placement & Acceptance​

5-8​

01-31-2023​

07-06-2023​

Project Definition​

9-11​

07-07-2023​

10-17-2023​

Implementation​

12-21​

10-18-2023​

04-25-2024​

Launch & Closeout​

22-24​

04-25-2024​

08-23-2024​

Production​

24-48​

08-26-2024​

01-22-2026​

Customer Support​

24-48​

08-29-2024​

09-02-2026​

PHASEWISE PROJECTED SCHEDULE

143