1
LUNAR LAPTOP
PROGRAM PROPOSAL
The Presenters:
Shiba ShivaPrakash
Prasanna Kumar
Jeyaraman
Gowtham Nageshwar Rao
Rugvedi Kesare
AGENDA
2
Executive Summary
3
We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.
We have identified a comprehensive set of Program Plans required to successfully execute the program.
We have the right infrastructure, latest technology, correct tools, experienced & talented team
We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.
We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM
We Followed MS 8 Step Proven Process For LUNAR Program
4
Step 1:
Market Research and Company Requirements
We have company's proven program plan to execute for MS LUNAR program
Step 2:
Product Plan
Step 4:
Risk Analysis & Mitigation Plan with Monte Carlo Analysis
Step 3:
Finance Plan
With Risk Budget
Step 5:
Product Plan
Step 6:
Iterations
Step 7:
Best Value Solution
Step 8:
Project Execution
Executive Summary
5
We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.
We have identified a comprehensive set of Program Plans required to successfully execute the program.
We have the right infrastructure, latest technology, correct tools, experienced & talented team
We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.
We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM
6
We have analyzed company and market requirements to develop MS LUNAR
Requirement Analysis
Market Analysis
Competitor Analysis
MS LUNAR
We Clearly Understand The Market And Company Requirements To Develop MS LUNAR
7
MS B2 – Launched 2016
MS B1 – Launched 2018
PHASING OUT MS B2 SALES AND LAUNCH NEW PRODUCT, MS LUNAR FOR MID-TIER SEGMENT IN 2025
MS B1 : 4.8% SEGMENT SHARE
MS B1: 0.21% TOTAL SHARE
MS: 0.47% TOTAL SHARE
DEMAND IN 2025 PEAKS
MID-TIER DEMAND in million
172.5
*FORECAST
We Analysed Current Market Share Of Millennium System
We have analysed the market share and our opportunity to get back our share in 2025!
Clear understanding of the Company & Market Requirements
80% Probability of success
Sales of 6 million units
30% to ROS
$475 per laptop (Wholesale Price)
Growth of market share from 5% to 10%
COMPANY REQUIREMENTS
7
8
We Have Performed Extensive Analysis Of The Market With Nielsen For Mid-tier Laptop Requirements
We have conducted detailed survey to understand market requirements and translated it into product features
Company & Market Requirements Market Survey & Requirements
GEOGRAPHIC
PRICE
DEMOGRAPHICS
FEATURES
COMPETITORS
Target Region: USA[1M], China[2M], India[2M], EUROPE[1M]
PRICE: $475
*Dealer’s Price
Target Market Segment:
18-35 years of age
High end Feature in Mid tier
Customer support & Warranty
Selling Points
Features to Delight Customers
High value to money
ANALYSIS
MS TEAM NIELSEN
RESULTING REQUIREMENTS
CHINA,INDIA
USA & EUROPE
450-500 WHOLESALE
TARGET AGE – 20 - 35
Smaller screen, attractive colors
Ideapad 3 & 5, pavilion 360
Executive Summary
9
We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.
We have identified a comprehensive set of Program Plans required to successfully execute the program.
We have the right infrastructure, latest technology, correct tools, experienced & talented team
We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.
We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM
10
We Offer Most Competitive Features Of The MS LUNAR
MS LUNAR have features that will delight customers and the company
Product Plan >>> Competitive Features
POWERFUL PROCESSOR
8GB DDR5 RAM
COMPACT AND TOP QUALITY DISPLAY
ALUMINIUM BODY
15 HOURS
512 GB SSD
MAJOR FEATURES DERIVED FROM OUR HIGH- END LAPTOP
11
We Conducted Comparison With Major Competitors
Product Plan meet Requirements >>> Major Competitors
FEATURES | LENOVO | HP | MS LUNAR |
PROCESSOR | INTEL i5 | INTEL i5 | AMD Ryzen 5 5000 X Series |
BATTERY | 11 HOURS | 3.5 HOURS | UP TO 15 HOURS |
DISPLAY | 15” LCD DISPLAY | 15” LCD DISPALY | 15.6” LCD DISPLAY ANTI-GLARE |
STORAGE | 256 GB SSD | NO SSD | 512 GB SSD |
FINGERPRINT SECURITY | NO | NO | YES |
RAM | 4GB | 8GB | 8 GB |
PROCESSOR IS BETTER AND ECONOMICAL
LONGER BATTERY LIFE THAN COMPETITORS
MORE STORAGE THAN COMPETITORS.
HIGHER PROCESSING SPEED THAN
COMPETITORS
MORE SAFE AND SECURE
Cost ($)
$ 500
$ 490
$ 475
Offering more at less price than our competitors
BETTER DISPLAY THAN COMPETITORS
We offer more value for money & quality than our competitors
12
Processor | AMD Ryzen 5 (10th Generation) |
Operating System | Windows 11 Home |
Display | 15.6" FHD (1920 x 1080) anti-glare, 250 nits |
Memory | 8 GB DDR5 3200MHz |
Battery | Up to 15 hrs (45Wh) |
Storage | 512 GB PCIe SSD |
Ports/Slots | USB-C 3.2 Gen 1,USB-A 3.2 Gen 1,USB-A 2.0,HDMI |
Graphics | Integrated Intel® UHD Graphics |
Dimensions (H x W x D) | Starting at 19.9mm x 359.2mm x 236.5mm / 0.78" x 14.14" x 9.31" |
Weight | Starting at 1.7kg / 3.78lbs |
Color | Carbon Gray, Beige Mousse and Bluestone |
Audio | 2 x 1.5W speakers with Dolby Atmos Audio™ Dual microphone |
Connectivity | 802.11AX (2 x 2) & Bluetooth® 5.1 |
Camera | 720p HD |
We Have Used Comprehensive Approach To Plan For Detailed Specification
We offer good Quality and competitive features in the mid tier laptop
Product Plan >>> Complete Specification
13
ONLINE MARKETING STRATEGIES
OFFLINE MARKETING STRATEGIES
PRINT MEDIA
SOCIAL MEDIA
SEARCH ENGINE OPTIMIZATION
WEBSITE AND EMAILS
STRATEGIC PARTNERS
SALES FORCE NETWORKING
We have proven marketing plan to approach our target customers.
We Have A Solid And Proven Marketing Strategy In Place
Product Plan >>> Marketing Strategy
14
Social media marketing video clip
Product Plan >>> Marketing Strategy
15
Product Development
Profit Driving
Customer Loyalty
Globalization
Competitive Advantage
ADVANTAGES DOES NOT AFFECT MS B1
AND WE HAVE THE CONSENSUS FROM MS B1 TEAM
LUNAR has Distinctive Advantages Using MS B1 Technology
We are bringing High end market features from MS B1 to offer in mid-tier laptop MS LUNAR
Clear understanding of the Company & Market Requirements
16
We Have Opportunity To Meet The Market And Company Requirements
We have successfully analyzed requirements, market and competitive analysis and have developed the product that will delight customers and company.
Product Plan meet Requirements
Requirement Analysis
Market Analysis
Competitor Analysis
MS LUNAR
Executive Summary
17
We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.
We have identified a comprehensive set of Program Plans required to successfully execute the program.
We have the right infrastructure, latest technology, correct tools, experienced & talented team
We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.
We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM
18
Financial Solution>> Company Requirements
80% Probability of success (POS)
Sales of 6 million units
30% Return on Sales (ROS)
$475 per laptop (Wholesale Price)
Growth of market share from 5% to 10%
COMPANY REQUIREMENTS
We have a Clear Understanding of Company Requirements to generate Solid Business Solution
We have a laptop with better Capabilities and Features than our Competitors at a Lower Price
Our Company Requirements Meet the desired goals to execute the Program Successfully
Cost($) w/o HP |
$ 98.78 |
$ 19.73 |
$ 25.96 |
$ 44.25 |
$ 25.87 |
$ 26.43 |
$ 18.45 |
$ 20.98 |
$ 25.92 |
$ 21.96 |
$ 14.00 |
$ 30.00 |
$ 369.33 |
|
|
MS Lunar Laptop Can Meet Unit Cost Requirement Of $332.5 After Tax
Financial Solution that will generate the required profit and a 30% ROS
Cost Element | Cost ($) | Program Cost ($). |
Hardware component | $ 87.00 | $ 522,000,000 |
Management Reserve | $ 19.94 | $ 119,640,000 |
Risk & Opportunities | $23.96 | $ 143,640,000 |
Development Cost | $ 24.75 | $ 118,500,000 |
Labor | $ 20.66 | $ 93,960,000 |
Manufacturing | $ 20.80 | $ 124,800,000 |
Packaging | $ 12.94 | $ 47,640,000 |
Procurement | $20.98 | $ 125,880,000 |
Advertisement | $25.92 | $ 155,520,000 |
Customer Support | $20.85 | $ 125,100,000 |
Warranty & Returns | $ 8.76 | $ 142,560,000 |
Miscellaneous | $30.74 | $ 184,440,000 |
Total Cost Before Taxes | $317.3 | $ 1, 903,800,000 |
Tax | $15.20 | $ 91,200,000 |
Total Cost After Taxes | $332.5 | $ 1,995,000,000 |
42% Savings
36% Savings
16% Savings
80% Savings
28% Savings
$52.00
Savings per Unit
$475
Wholesale Rate
Min 30% ROS
Risk Analysis
Cash Flow Model at 80% POS
18
$142.5
Profit per Unit
We have a laptop with better Capabilities and Features than our Competitors at a Lower Price
20
Target Units Sold | 6,000,000 |
Unit Cost (Wholesale) | $475 |
Return of Sales | 30% |
Cost per unit | $332.50 |
Sales Revenue | $2,850,000,000 |
COGS (Cost of Goods Sold) | $1,995,000,000 |
Tax Rate | 25% |
EBIT ( Earnings Before Interest & Tax) | $855,000,000 |
Tax | $213,750,000 |
NET PROFIT - AFTER TAX | $641,250,000 |
PRODUCTION:
6 million units
1.2 B
Program Cost
$146 M
Management Reserve
$19 M Total Risk & Opportunity Budget
We Have Developed A Comprehensive Cash Flow Model To Achieve A 30% Ros At 80% POS
We have a Solid Financial plan with a profit of 641M considering a Risk & Opportunity Budget at 30% ROS & 80%
Developing Business solution >> Financial Model with risk analysis
19
Replacement
Units:
70,050
21
Net Profit at 30% ROS
$641,250,000
Management Reserve
=$146,211,840
PHASES | TOTAL PHASE COST | % ALLOCATION |
Market Planning | $ 29,508,900 | 1.55% |
Placement & Acceptance | $ 26,653,200 | 1.40% |
Project Definition | $ 15,991,920 | 0.84% |
Implementation | $ 365,719,980 | 19.21% |
Launch & Closeout | $ 289,187,220 | 15.19% |
Production | $ 634,726,920 | 33.34% |
Customer Support | $ 395,800,020 | 20.79% |
Management Reserve | $ 146,211,840 | 7.68% |
Total Budget COST | $ 1,903,800,000 | 100.00% |
Our Total Budget with 30% ROS
We Have A Required Phase-wise Budget To Be Successful & Provide A 30% ROS
We have developed a Risk Adjusted Phase-Wise Budget with MR 7.6% at 80% POS
Developing Business solution >>> Financial Model with phase-wise budget allocation
20
Cost:
$ 475/Unit
22
We Have Performed a Breakeven Analysis to Execute the Program at 30% ROS
We have a successful Business Solution to achieve 30% ROS at 80% POS with Net Profit of $641 M
Financial Plan Generated 30% ROS >>> NPV vs IRR
Break-even at
Month 24
PRODUCTION RATE
21 | 80k |
22 | 280k |
23 | 560k |
24 | 700k |
Maximum Expense
$275,151,000
Project NPV | 680,255,000 |
Project IRR | 9.56% |
21
23
RISK IDENTIFICATION
RISK PRIORITIZATION
MITIGATION
ANALYSIS
IMPLEMENTATION
ITERATION
Detailed Risk & Opportunity mitigation planning with Monte Carlo Analysis is established
We have followed MS’ Proven Procedure for Conducting Risk & Opportunity Analysis
We have followed the Risk and Opportunity Analysis procedure to achieve 80% of POS
A solid MS LUNAR design and business solution >>> Risk Analysis Procedure
22
24
We have IDENTIFIED RISK and IMPLEMENTED BUDGET to achieve 80% POS !
We Have Identified Phase-wise Risks, Cost associated with it and implemented Budget to achieve desired POS
A solid MILLENIUM SYSTEMS design & business solution >>> Risk Tracking & Impact
23
25
We have performed a comprehensive analysis to IDENTIFY OPPORTUNITY and MITIGATE RISK at 80% POS !
We Have Identified Phase-wise Risks, Opportunities & Mitigation Plan To achieve desired POS
A solid MILLENIUM SYSTEMS design & business solution >>> Risk Tracking & Impact
23
26
PHASE
RISK
OPPORTUNITY
Software Failure
Manufacturing & Design Incompatibility
Inefficient Vendors
Over Allocation of Resources
Failed Market Research
Poor Access to Service Centers
Labor Strike
V
IV
III
II
I
VII
VI
Update to a more robust software
Optimize Manufacturing & Design Process
Enhance Procurement Process
Reduce the budgeted units/time allocation
Have Data Collected
Provide easy online services and 24*7 support
Improve relationship with labor workforce
$ 295,000 |
$ 400,000 |
$ 100,000 |
$3,545,000 |
$2,500,000 |
$8,800,000 |
$2,300,000 |
$17,940,000 |
$ 210,000 |
$ 300,000 |
$ 1,495,000 |
$ 995,000 |
$ 2,000,000 |
$ 1,000,000 |
$ 2,000,000 |
$8,000,000 |
Risk mitigation budget
Opportunity implementation
Budget
We have identified opportunities with a mitigation & implementation budget of 25M at 80% POS
WE HAVE RISK MITIGATION & OPPORTUNITY BUDGET TO ACHIEVE 80% POS WITH ROS 30%
A solid MS LUNAR design & business solution >>Opportunity identification >> Risk & Opportunity budget
24
27
At 30% ROS
PROFIT: $641 M
80.00% POS
We have achieved 80% POS for Net Profit of $ 641 M at 30% ROS>> Successful Program
We Have Performed A Monte Carlo Analysis At 80% POS
Risk Mitigation & Opportunity projects for 80% POS >>> Monte Carlo Analysis
26
28
2. Comprehensive Cash Flow
1. Unit Cost Requirement
3. Phase Wise Budget
4. Break Even Analysis
Coupled with the Risk Analysis, this gives us confidence in generating a 30% ROS
We Have Performed A Comprehensive Financial Analysis To Ensure We Meet The 80% POS, Starting With :-
Financial Plan Generated 30% ROS
27
29
Monte Carlo Analysis
Comprehensive analysis for the Risk & Opportunity was followed accordingly
We Have Done The Risk Mitigation & And Opportunities Analysis And Achieved An 80% Pos That Meets The Company Requirements
Risk Mitigation & Opportunity projects 80% POS
28
Phase-wise risks and costs
Risk Mitigation & Opportunity Implementation Plans
Risk & Opportunity Analysis
Executive Summary
30
We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.
We have identified a comprehensive set of Program Plans required to successfully execute the program.
We have the right infrastructure, latest technology, correct tools, experienced & talented team
We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.
We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM
31
MPP
SOW
OBS-WBS MATRIX
IMP
EVMS
CRITICAL PATH
EVMS
WBS
OBS
We Have A Comprehensive Set Of Program Plans In Place To Successfully Execute The Proposed Program
We have all the detailed plans required in place to successfully execute the LUNAR project.
Identified a comprehensive set of Business Plans
32
Identified a comprehensive set of Business Plans >>> Checklist Plan
PLANS | PHASE1: Marketing Research | PHASE2: Placement& Acceptance | PHASE3: Product Design | PHASE4: Implementation | PHASE5: Launch & Close-Out | PHASE6: Production | PHASE7: Customer Support |
Master Program Plan | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ |
Work Breakdown Structure | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ |
Integrated Master Schedule | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ |
Critical Path | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ |
Organizational Breakdown Structure | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ |
Control Accounts | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ |
EVMS | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ |
WBS,OBS Matrix | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ |
Integrated Master Plan | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ | ✔️ |
We Have Developed A Checklist Of Plans To Successfully Execute The MS Lunar Program
We have all the detailed plans required in place to successfully execute the LUNAR project.
33
Program Plan with Management Tools >>> Master Program Plan
WE HAVE DEVELOPED A COMPREHENSIVE MASTER PROGRAM PLAN (MPP) For MS LUNAR Laptop Program
We have overall plan ready to execute ‘LUNAR’.
LUNAR
34
Comprehensive set of plans >>> WBS
Phase-1 Market Research | Phase-2 Placement & Acceptance | Phase-3 Project Definition | Phase-4 Implementation | Phase-5 Launch & Closeout | Phase-6 Production | Phase-7 Customer Support |
1.1 Management Authorises Phase ½ Limited Funding 1.2 Initial Business Case SWOT analysis 1.3 Opportunity objectives 1.4 Corporate Strategy Check 1.5 Concept Brief and Conceptual Product Outline 1.6 Business Case Refinement 1 1.7 Marketing & Product Plan 1.8 Technical Recommendations 1.9 Customer Survey 1.10 Business Case Refinement2 1.11 Realistic Technical Specifications 1.12 Financial Analysis 1.13 Legal 1.14Business Model 1.15 Phase 1 Goal Completion Date | 2.1 Resource strategy product team 2.2 Control charts(WBS) 2.3 Technology, Architecture & Platform strategy 2.4 Solution lockdown for concept 2.5 Baseline feature descriptions 2.6 Budgetary estimates 2.7 Staffing plan 2.8 Product Life-cycle 2.9 Project Control(IMP,IMS) 2.10 Management Review/Decision to invest | 3.1 Project business review 3.2 Staffing plan 3.3 Product technical specifications 3.4 Intellectual property review 3.5 Technical requirements allocation 3.6 Technical Requirements Allocation 3.7 Business / Manufacturing Requirements Allocation 3.8 System Analysis, Modeling, and Simulation 3.9 Product/system test strategy 3.10 Subcontractor 3.11 Manufacturing strategy 3.12 Program commitment statement 3.13 Management Involvement 3.14 Project Management Plan for Implementation Phase 3.15 Sourcing 3.16 Supply chain logistics & distribution requirements 3.17 Phase 3 Goal Completion Date | 4.1 Subsystem specifications 4.2 Test specifications 4.3 Supply chain management 4.4 Subcontractors 4.5 Product/system 4.6 Critical design review(CDR) 4.7 Documentation & training 4.8 System test 4.9 Manufacturing systems & processes 4.10 Sourcing 4.11 Intellectual property review 4.12 Project plan 4.13 Manufacturing materials 4.14 Ready for field test 4.15 Manufacturing systems & processes 4.16 Sourcing 4.17 Prototype testing 4.18 Marketing artefacts 4.19 Ready for product rollout/deployment 4.20 Product/system 4.21 Phase 4 Goal Completion Date | 5.1 Project staffing plan for launch and close-out phase 5.2 Intellectual property review 5.3 Manufacturing Systems and Processes 5.4 Sourcing 5.5 Cost management 5.6 Launch preparation activities 5.7 Training and documentation 5.8 Project business review 5.9 Project plan 5.10 Manufacturing engineering support 5.11 Warranty repair center 5.12 Phase 5 Goal Completion Date | 6.1 Product/system 6.2 Manufacturing systems and processes 6.3 Sourcing 6.4 Cost Management 6.5 Final Business Review 6.6 LRIP 6.7 FRP 6.8 Project Lessons Learned 6.9 Project Lessons learned 6.9 Retirement Plan Approved 6.10 Product Lessons Learned | 7.1 Staffing Plan 7.2 E-Commerce Management 7.3 Call Center Operations 7.4 Back Logistics 7.5 Product Data Management �� |
Work Breakdown Structure (Wbs) Developed To Meet The Requirements Of Sow Using A Phased Approach
All criteria required to accomplish current phase must be reviewed and approved by program management prior to proceeding to the next phase
35
Integrated Master Schedule Has Been Developed For All Phases Of The Lunar Lifecycle (Example Phase 3)
All phases of the LUNAR lifecycle are defined. Schedule and required costs are identified and leveled.
36
Program Plan with Management Tools >>> Statement of Work
Statement Of Work Is Completely Defined And Identified
Objective: Our Millennium Systems LUNAR laptop program is to become a leading Laptop in Mid-tier Market |
Scope of work:Program includes all planning, execution, implementation, and training |
Period of performance: The period of performance for the MS LUNAR laptop program project is 48 months |
Schedule of milestones: START:Market Planning September 1st ,2022. END: Customer Service 2nd September, 2026 |
Acceptance criteria: The acceptance of all deliverables will reside with MS Marketing Head |
SOW Example – Phase 1
SOW Methodology is defined and identified for each phase of the project
37
Critical Path Has Been Determined For Each Phase �Of The Ms LUNAR Program (Example – Phase 4)
Critical Path for all phases of the LUNAR program have been identified.
38
We Have Developed The Organizational Breakdown Structure (OBS) For The LUNAR Program
Complete Organizational Breakdown Structure has been defined.
Marketing |
Forecasting |
Market Research |
Public Relations |
Content Development |
Manufacturing |
Inventory Procurement |
Research & Development |
Finance |
Business Models |
Accounting |
Accounting And Billing |
Administration |
Hr |
Knowledge Transfer |
Project And Program Managemnt |
Project Manager |
39
Identified a comprehensive set of Business Plans >>> EVMS
The MS LUNAR Earned Value Management System (EVMS) �Will Be Utilized
EVMS is used majorly in our project to keep track of our Project Goals and Checkpoints.
40
Program Plan with Management Tools >>> OBS & OBS-WBS Matrix
We Have Developed The Organizational Breakdown Structure (Obs)
For The MS LUNAR Program AND Have Developed The Wbs Vs Obs Matrix Which Has Been Linked And Cost Accounts Determined
Every task is tracked to a specific Cost Account from OBS/WBS Matrix
41
Program Plan with Management Tools >>> Integrated Master Plan
We Have Developed INTEGRATED MASTER PLAN (IMP) FOR THE MS LUNAR PROGRAM
Integrated master plan has been developed with entry and exit criteria, for each of the phases
42
Identified a comprehensive set of Business Plans
MPP
SOW
OBS
WBS
IMP
IMS
CRITICAL PATH
EVMS
✓
✓
✓
✓
✓
✓
✓
WBS
OBS
✓
✓
We Have A Comprehensive Set Of Program Plans In Place To Successfully Execute The LUNAR Program
We Have all the Detailed Plans Required in Place to Successfully Execute the LUNAR Project.
Executive Summary
43
We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.
We have identified a comprehensive set of Program Plans required to successfully execute the program.
We have the right infrastructure, latest technology, correct tools, experienced & talented team
We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.
We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM
44
Right Infrastructure, Latest Technology, Correct tools, Experienced Team
We Have The Right Resources In Place To Succeed
We are equipped with the necessary tools and procedures to be successful.
Right Experience
Required Tools
Proven Processes
Right Infrastructure
Experienced and Available Talent
MS LUNAR
We have the right experience required to successfully implement the MS LUNAR program
45
Right Infrastructure, Latest Technology, Correct tools, Experienced Team
We Have Taken Advantage of Experience Gained from Previous Programs to Guide the Project in the Right Direction
MS B2 (previous Mid-tier Laptop) | MS B1 (Current High-end laptop) |
Network of Suppliers and Distributors | Design Features |
Customer Support Experience | Research and Development |
Market Analysis | High-End Features |
Project Team | |
Manufacturing Unit | |
The gains from our previous programs include:
Right Experience
Required Tools
Proven Processes
Right Infrastructure
Experienced and Available Talent
MS LUNAR
46
Right Infrastructure, Latest Technology, Correct tools, Experienced Team
We have PROVEN TOOLS Required to Successfully Implement the Program
We Have the Required and Proven Tools in Place!
Design
Manufacturing
Quality
Customer Support
Right Experience
Required Tools
Proven Processes
Right Infrastructure
Experienced and Available Talent
MS LUNAR
47
Right Infrastructure, Latest Technology, Correct tools, Experienced Team
We have the PROVEN PROCESS required to successfully implement the program
We Have a Robust Starting Point for this New Venture!!
Phase I
Market
Planning
Phase II
Placement &
Acceptance
Phase III
Project
Definition
Phase IV
Implementation
Phase V
Launch &
Closeout
Phase VI
Production
Phase VII
Customer Support
48 Months
We Have A Successful Proven Strategy In Place
All 7 Phases of Laptop Lifecycle Have been Carefully Evaluated and Accounted For!
Right Experience
Required Tools
Proven Processes
Right Infrastructure
Experienced and Available Talent
MS LUNAR
48
Right Infrastructure, Latest Technology, Correct tools, Experienced Team
We have the PROVEN INFRASTRUCTURE required to successfully implement & run the program
We Have the Appropriate Infrastructure to execute MS LUNAR program!
Manufacturing
Texas, U.S.A
Customer Support
Colorado , U.S.A
Assembly
Texas, U.S.A
R & D
Colorado, U.S.A
Headquarters
Colorado, U.S.A
Right Experience
Required Tools
Proven Processes
Right Infrastructure
Experienced and Available Talent
MS LUNAR
49
Right Infrastructure, Latest Technology, Correct tools, Experienced Team
We have the PROVEN INFRASTRUCTURE required to successfully implement & run the program
We Will Leverage Existing Resources to Market Effectively, Optimize Cost, and Lower Risks!
Right Experience
Required Tools
Proven Processes
Right Infrastructure
Experienced and Available Talent
MS LUNAR
Millennium Systems
Manufacturing Facilities
Assembling Facilities
Research & Development Center
Marketing Department
Marketing Strategy
Sales & Acquisitions
Vendors & Suppliers Department
Raw Materials, Parts & Spares
Distributors
Wholesalers
Headquarters
Warranty & Customer Support Centers
Administrative Department
50
Right Infrastructure, Latest Technology, Correct tools, Experienced Team
We have the talent required to successfully implement the program
We Have A Highly Experienced Team!
Right Experience
Required Tools
Proven Processes
Right Infrastructure
Experienced and Available Talent
MS LUNAR
Program Director:
Viraj Patel
Deputy Program Director:
Blake Lively
Project Manager:
Dileep Edara
Product Development Manager:
Shreya Reddy
Administrative manager:
Ravi Radadiya
Quality Control Manager:
Vigneshji
Finance Manager:
Harshada Khatale
Marketing Manager:
Prateek Jat
Manufacturing Manager:
Shrey Sachan
20 years VP Product Development at IBM
10 years VP operations at Samsung
SAFe 4.0 Advanced Scrum Master
6 sigma certified
Organizational Structure For Phase 1
51
Right team in place with the right experience > Proven Processes
We Have The Right Resources In Place To Succeed
We are equipped with the necessary tools and procedures to be successful.
Right Experience
Required Tools
Proven Processes
Right Infrastructure
Experienced and Available Talent
MS LUNAR
52
We have all the Required Resources and Processes in Place to Succeed!
Keys to MS LUNAR Success
53
We have all the Required Resources and Processes in Place to Succeed!
Keys to MS LUNAR Success
Executive Summary
54
We have the right technical solutions that will meet the customer and the company requirements and business solutions with 80% POS to achieve 30% ROS.
We have identified a comprehensive set of Program Plans required to successfully execute the program.
We have the right infrastructure, latest technology, correct tools, experienced & talented team
We have a clear understanding of the requirements for MS LUNAR to delight the customer and to make the required profit for MS shareholders.
We seek your APPROVAL today to begin the EXECUTION OF THE PROGRAM
55
We seek your approval today to begin the execution of the program
56
Back Up Slides
57
Table of Content of Story Board
CONTENT | SLIDE NO |
1 | |
2 | |
3 | |
4 | |
5 | |
6 | |
7 | |
8 | |
9 | |
10-11 | |
12 | |
13-16 | |
17 | |
18 | |
19 | |
20-21 | |
22 | |
23 | |
24 | |
25-26 | |
27 | |
28 | |
29 | |
30 |
58
Table of Content of Story Board
CONTENT | SLIDE NO |
31 | |
32 | |
33 | |
34 | |
35 | |
36 | |
37 | |
38 | |
39 | |
40 | |
41 | |
42 | |
43 | |
44-45 | |
46 | |
47 | |
48-49 | |
50 | |
52-53 | |
54 | |
| |
| |
| |
| |
59
TABLE OF CONTENTS | SLIDE NO |
60 | |
61 | |
62 | |
63 | |
72 | |
77 | |
80 | |
81 | |
82 | |
83 | |
84 | |
85 | |
88 | |
89 | |
90 | |
91 | |
92 | |
93 | |
95 | |
96 | |
97 | |
98 | |
99 | |
100 |
TABLE OF CONTENTS | SLIDE NO |
102 | |
104 | |
105 | |
106 | |
108 | |
109 | |
110 | |
111 | |
113 | |
114 | |
115 | |
116 | |
125 | |
127 | |
134 | |
136 | |
137 | |
141 | |
142 | |
|
|
|
|
|
|
|
|
|
|
60
Product development Q&A
61
FINANCE
RISK
RISK AND FINANCE Q&A
62
PLANNING Q&A
63
How many MS B1 laptops are there in market?
Product development Q&A
How many MS B2 Laptops are there in market?
Is 10% Market share taken from the competitors or the market itself has grown?
Why would I buy a MS LUNAR instead of a HP or a LENOVO ?
64
Product development Q&A
65
Terms and Conditions For Vendors and Customers
For Suppliers
Terms:
• Product quality upon delivery.
• Delivery on schedule.
• Prompt assistance and responses.
• Additional supplies for demand periods.
Conditions:
• The product provided must be unique to MS.
• MS holds the option for contract renewal or rejection every three years.
• Obey the MS-written nondisclosure agreement.
For Clients
Terms:
Conditions:
What are the terms and conditions with our vendors Customers?
MS and the supplier have an agreement that, in the event that the supplier is unable to achieve quality criteria for its product, the supplier will promptly reimburse MS for 30% of the contract's cash, and MS will return the collateral once the standards are met. 20% of the collateral (or 6% of the overall contract) will be retained by MS for each month the provider is late meeting the quality level.
If a vendor violates a material term of the contract in terms of quality control or shipment delay that hinders the business's growth, MS has the authority to void the current contract agreement with the vendor.
If MS decides to cancel or modify the order, it will be responsible for paying 5% of the contract amount within the first year, 25% of the contract amount between years one and two, 60% of the contract amount between years two and three, and 100% of the contract amount if the modification is made after three years.
If MS must end the contract because of poor supplier quality or a delivery delay, then
66
Vendor/Supplier Agreements
Quality: The shipment should contain the correct documentation for the quality inspections that MS requires. Only when MS's internal quality inspection, which can involve testing the finished product, is successful will the consignment pass the quality procedure.
Delivery: Vendors must deliver the package by the stated date and time.
Vendor must notify MS in advance if there will be a shipment delay, and MS is free to choose alternative vendors to make up for the delay. Payment for the shipment will not be released until the vendor and buyer have agreed on a penalty for the delay; this amount will then be subtracted from the total amount due for that particular shipment.
Arbitration: MS and supplier industries agree to settle any disputes through binding arbitration rather than in court, with the caveat that small claims court may be used in certain circumstances.
67
Vendor/Supplier Agreements
Who are going to buy MS LUNAR Laptops ?
68
Product development Q&A
MS will have standard Terms and Conditions with vendors containing the following samples pulled from the full T&Cs document.
6.0 PRICING; INVOICING; PAYMENT:
6.1 Seller shall sell to Buyer the Goods or Services shown on the face of the Order at the price � specified. All prices are inclusive of applicable freight charges and duties unless otherwise agreed.
6.2 Seller warrants that the prices charged for the Goods or Services are not higher than those charged � to any other customer or Buyer site for Goods of like grade and quality in similar quantities or for � similar Services performed by skilled personnel.
12.0 TERMINATION:
12.1 Buyer may terminate the Order in whole or in part at any time in the manner specified in Section 12.3 upon the occurrence of certain events, including but not limited to:
i. Default by Seller with respect to cost competitiveness, delivery, quality, failure to maintain technology, or other obligation under the Order, or� ii. Insolvency of Seller, filing by Seller of a voluntary petition in bankruptcy, filing of any involuntary petition to have Seller declared bankrupt, provided the same is not vacated within thirty (30) days from the date of such filing, or the execution by Seller of any assignment for the benefit of creditors.
15.0 RECALL/REPAIR CAMPAIGN:
15.1 If Seller’s Goods or Services create or contribute to a component repair campaign or safety recall due to a component defect, or non-compliance the Seller shall be liable for costs and damages resulting from a Recall only if the Recall results in whole or in part from a failure of the Goods to conform to the warranties in Section 7 during the warranty period specified in the Contract
69
Terms and conditions with vendors and our contract terms and conditions with our customers
What have we been doing to market MS B1 Laptops in India and China? Do we have any experience there? How do we intend to tackle those markets?
Based on the worldwide success of MS B1 Laptops, we entered the Chinese and Indian market with MS LUNAR Laptops:
China has strong manufacturing capabilities. But China does not have a fluctuating market and is not bound by WTO rules. Analyzing the Chinese market, we decided to market MS B1 as a trendy Laptop that is central to the American youth culture. Since American media has a worldwide influence on lifestyle and is emulated by Chinese users, we have captured 40% of the market.
India does not have strong manufacturing capabilities but has extensive transportation and is well connected. India also has highest number of younger demographic users. Since the MS B1 Laptops caters well to this niche market, we believe, we have been extremely successful in India with a strong market share of 25%.
70
Product development Q&A
71
Product development Q&A
How was the market research performed?
72
73
TARGET SALES | 6,000,000 UNITS |
SELLING PRICE | $475 |
COST PER UNIT | $332.50 |
74
effect of MS LUNAR on MS B1
LOSS IN MARKET SHARE
RISK Q&A
75
division of resources for MS LUNAR and MS B1
HOW DO WE MINIMIZE TECHNICAL RISK?
WHAT IS THE HIGHEST RISK IN THIS PROJECT?
IS THIS PROJECT TAKING THE RIGHT AMOUNT OF RISK?
HOW DO WE TAKE ADVANTAGE OF THE ORGANIZATIONAL LEARNING THAT RESULTS FROM THE RISK MANAGEMENT PROGRAM AND ACTIVITIES?
76
RISK Q&A
What does the production schedule look like? Is that built into the financial plan in detail?
During the initial phase of the production, we will be using LRIP (Low – Rate Initial Production) and progressively move forward to the FRP (Full rate Production) while the production is in progress. As per our calculations the LRIP would be present for the 2 months period and after that FRP for 10 months to produce 6 million units
How can you assure the quality of your product?
We would be doing the FLT*, Certification testing and R&D testing. The R&D testing will be comprising of the following attributes: -
1) Temperature Test
2) Humidity Test
3) Hardware Testing
4) Wifi & Bluetooth Frequency testing
5) Camera test – ISO 100 to ISO 1600
6) Climate Test
7) Thermal shock Test
8) Battery test
We will also make sure that the Laptop is PTCRB, FMPL and AQL certified before entering the market.
*FLT – Factory level testing
77
PLANNING Q&A
How did you obtain your customer feedback to feel assured about your production?
The following are the methods we undertook to get the customer feedback to feel assured about our production:
1) Questionnaires
2) Surveys
3) Focus Groups Interviews
4) Observation
5) Experiments
6) Field trials
How can you say that your interaction with other departments has been? Especially with the finance department since they work so closely with you?
To obtain the budget from the finance department and translating it to the project activities we worked like a cross – functional organization. Our Program lead communicated with the chief financial officer and the allocated budget was delineated to various phase.
78
PLANNING Q&A
In every phase, how did you make sure your performance is on track?
After the Planning has been authorized and the Execution has started, systems engineering will assure the Controlling. Planned date slacks and padding time are allotted to cope with contingencies and conditions in order to complete the project on schedule.
What does the pay-scale look like for various employees in your company?
Every employee group has a different pay scale depending on the variety of skill sets they possess and how crucial they are to the execution of the program.
How many prototype laptops are built?
The majority of the testing will only be done for the hardware and software integration as many of the components in the previous MS laptop have already been evaluated. The LUNAR laptop's numerous features, which the consumers have prioritized, will be tested using 700 prototypes that will be produced. The cost of creating and testing prototypes has been included to the project's development budget.
79
PLANNING Q&A
80
We Have Analyzed The Current Market Hold Scenario
Current market share (Competitors analysis)
81
GEOGRAPHIC SEGMENT IDENTIFIED: USA,EUROPE, CHINA AND INDIA.
GEOGRAPHIC
MARKET SURVEY RESULTS
81
82
CONSUMER REQUIREMENTS (Feature Analysis)
Our product plan is based on customer focused development strategy
Majority is opting for smaller screen
Half of the users choose to buy a laptop of price ranging 450$-550$
Customers are looking for a longer battery life & larger storage space
NIELSEN’s Analysis Report on customer requirements
82
Customer Surveys
Vendor Surveys
NIELSEN HOLDINGS PERFORMED CUSTOMER AND VENDOR SURVEYS
Survey enables MS to build a LAPTOP that the customer wants
83
STRENGTH
WEAKNESS
OPPORTUNITY
THREATS
SWOT Analysis
84
Distribution Strategy
Pre-launch and Launch
Growth
Maturity
Decline
to maintain sales levels and allow product sales to occur naturally
to maintain sales growth in order to achieve desired sales quantities.
follow the trend until the inevitable drop in sales
85
86
Distribution Strategy
Pre-launch and Launch
Growth
Maturity
Decline
to keep up distribution levels and manage in accordance with market demands
For complete availability of merchandise at sites of sale and adhere as closely as you can to the ultimate users
To distribute product inventories in preparation for exhaustion
Ahead of launch dates, to guarantee that the product is available in the sales channels
86
87
Distribution Strategy
Objective
87
PRE-LAUNCH & LAUNCH
GROWTH
MATURITY
DECLINE
87
88
PACKAGING WITH PURPOSE:
PROTECTION
SAFETY
ATTRACTIVENESS
SUSTAINABILITY
Should protect the product from humidity, light, heat & other external factors
Consumer safety information must be mentioned in order to cause no harm to the customer
Purpose to standout in the market to enhance sales and increase interest on the product
PRODUCT PACKAGING
PACKAGING IS AS IMPORTANT AS THE PRODUCT ITSELF
88
Promotional Strategy
Our Promotional Strategy Will Meet the Program Plan Requirements
Promotional Strategy
Our Promotional Strategy Will Meet the Program Plan Requirements
89
WE HAVE DEVELOPED BETTER MARKETING PLAN THAN PREVIOUS PROGRAM
Our marketing plan covers all major economy
MS LUNAR PRODUCT LINE
Distributors
Major Retailers
Small Dealers/Retailers
Franchised In-Country Major Outlet Distributors
India
Retailers
Europe & USA
Retailers
China
Retailers
Direct Sales/Marketing Team
*Direct customer – Distributors; *Indirect Customer – Retailers; *Final Customer – Consumer
90
91
WE HAVE COVERED ALL CORNERS OF MARKET USING OUR ADVERTISING STRATEGY
The objective of advertising campaign is to create awareness.
Use social media advertising on platforms such as YouTube and Facebook to play our advertisements.
Target places with high footfalls such as shopping malls, stadiums, amusement parks.
Our Advertisement would look like on of these
Better advertising strategy to connect with potential customers
92
Why is LUNAR going to be the face of the MS & How?
MS B1
Major Drawback: Overheating issues reported from users
Major Highlight: Can perform Multiple High performance tasks at the same time.
MS B2
Major Drawback: Battery dying quickly
Major Highlight: Expandable RAM & 512SSD disk space
MS LUNAR
Upcoming all the Challenges encountered with MS B2 & B1 and taking demanding features from MS which worked in the market by adding new
FACE OF THE COMPANY
BEST EVER MULTI-TASKING LAPTOP IN MID-RANGE SEGMENT
92
We Have A Competitive Warranty Plan
We have created Warranty details
93
We Have A Competitive Warranty Plan
We have created Warranty details
Type of warranty
Details
i. Mechanical malfunction
ii. Electrical malfunctions
iii. Battery
iv. Technical support(complimentary)
i. Deductible $95.
ii. Replacement allowed 2 times
94
We Have A Competitive Warranty Plan
Warranty CALCULATIONS
95
Sigma Performance Levels – One to Six Sigma | |||
Sigma Level | Defect for 6mil | Cost of defective Laptops | Warranty cost per laptop |
1 | 4,140,000 | $ 621,000,000.00 | $103.50 |
2 | 1,851,222 | $ 277,683,300.00 | $46.28 |
3 | 400,842 | $ 60,126,300.00 | $20.02 |
4 | 70,050 | $ 5,589,000.00 | $8.76 |
5 | 5000 | $ 209,700.00 | $3.23 |
6 | 1000 | $ 3,000.00 | $0.00 |
Warranty Cost Per Unit = $8.76
Provide two replacements = 2 x 8.76 = $17.52
A warranty cost of $17.52 have been added indirectly to the unit cost requirement
We Have A Competitive Warranty Plan
Warranty FINE PRINT
96
Insurance Agreement
97
98
Customer Support Plan
99
Mockups
Wireframe Sketcher
DESIGN
Kaizen
Plan-Do-Check-Act (PDCA)
5S
ISO 9000
Lean / Six Sigma
Manufacturing
Benchmarking
Failure Modes & Effects Analysis (FMEA)
Quality Function Deployment (QFD)
Total Quality Management (TQM)
Quality
Local Reseller Preliminary Customer Support
24/7 MS Secondary Support
Existing Proven Customer Support Methodology from MS.
Customer Support
�
PROVEN PRODUCT PLAN FOR MS LUNAR
Take we have proven process and tools required to successfully implement the program away
99
100
FINANCIAL GOALS
100
We have various Warranty OPTIONS
We Have A Competitive Warranty Plan
| DELL | HP | LENOVO | MS WB |
Price (over 2 years) | $210 | $195 | $177 | $117 |
Deductible per claim | $161 | $149 | $119 | $95 |
Repair at local service centers | NO | NO | NO | YES |
Complementary technical support | YES | YES | NO | YES |
Covers any working laptop, old or new from MS | NO | NO | NO | NO |
Loss & theft protection | NO | YES | NO | YES |
101
Warranty OPTIONS
We Have A Competitive Warranty Plan
Plan Features (per device) | DELL | HP | LENOVO | MS WB |
Next day replacement | ✔ | ✔ | ✔ | ✔ |
Accidental damage coverage | ✔ | ✔ | ✔ | ✔ |
Data backup | ✔ | ✔ | | |
Remote tech support | ✔ | ✔ | ✔ | ✔ |
On-site tech support (at buyer's location) | ✔ | | | ✔ |
Claims per year allowed | 3 | 2 | 3 | 2 |
Loss and theft protection | | ✔ | | ✔ |
Plan Cost | $33.99/mo | $32.99/mo | $32.99/mo | $29.99/mo |
Deductible | up to $161 | up to $149 | up to $119 | up to $95 |
* $65 fee for three or more claims
102
103
We Have A Competitive Warranty Plan
We have done Warranty CALCULATIONS
What the Plan Covers
104
We Have A Competitive Warranty Plan
We have done Warranty CALCULATIONS
What the Plan Covers
We Have A Competitive Warranty Plan
Warranty ANALYSIS
| DELL | HP | Lenovo | MS LUNAR |
Warranty Price | $210 | $195 | $177 | $117 |
105
106
WE HAVE PERFORMED THE SENSITIVITY ANALYSIS TO DETERMINE THE RELATION BETWEEN NET INCOME VS MR
Our What-If Analysis shows that it is not worth removing the MR for a delta increase of 4.97% with net profit of $641M at 30% ROS.
106
107
Hardware Component | Vendor | Make /Buy | Cost ($) |
CPU | BroadCom | | 6.95 |
Screen | Lenovo | BUY | 5.25 |
Top Panel | ASUS | BUY | 5.35 |
Base Panel | ASUS | BUY | 6.35 |
RAM | Kingston Technology | BUY | 6.00 |
Display | Millennium Systems | MAKE | 9.65 |
Wireless Card | BroadCom | BUY | 5.00 |
Cooling Fan | Thermal take Technology | BUY | 5.50 |
Battery | Dynapac | BUY | 7.00 |
Keyboard | Dell | BUY | 5.00 |
Trackpad | Lenovo | BUY | 4.00 |
Power Connector cable | BroadCom | BUY | 6.50 |
Hard Drive | Kingston Technology | BUY | 7.00 |
Video Card | Intel | BUY | 7.45 |
Total | | | 87.00 |
MAKE OR
BUY
WE HAVE DETAILED ANALYSIS ON MAKE VS BUY
We have based our decision on firm bids with contracts ready to be signed
107
108
| PER UNIT MAKE | | TOTAL MAKE | BUY |
Purchase Price | 10.5 | | 0 | 63,000,000 |
Direct Material | 5 | | 30,000,000 | |
Direct Labor | 2.5 | | 15,000,000 | |
Variable overhead | 1.05 | | 6,300,000 | |
Fixed Overhead | 1.10 | | 6,600,000 | |
Total Cost | 9.65 | | $57,900,000 | $63,000,000 |
We have decided to manufacture display for 6,000,000 Units
$0.85 Per Unit less to MAKE than BUY
108
109
Comprehensive Cash Flow
Unit Cost Requirement
Phase-wise Budget Allocation
Impact of MR on ROS
Break Even Analysis
COMPREHENSIVE FINANCIAL ANALYSIS MODEL TO ENSURE THE POS OF 80%
109
110
WE HAVE ANALYZED THE RECURRING VS NON-RECURRING COSTS TO DETERMINE PROJECT STATISTICS
OUR RECURRING COSTS ARE 3% HIGHER THAN THE PREVIOUS PROPOSALS EXPENSES, DUE TO THE ADDED EMPHASIS SUPPORT AND INCREASE IN PRODUCTION COSTS BASED ON CURRENT EXTERNAL SCENARIOS.
111
WE HAVE THE BUDGET REQUIRED TO BE SUCCESSFUL AND PROVIDE A 30% ROS
Replacement laptops are considered and are a part of the production schedule
Cumulative Production Over 48 Months
112
RISK | PROBABILITY | PRIORITY | RISK BUDGET ALLOCATION | MITIGATION PLAN |
Market Share Loss | 0.25 | Moderate | $ 73,77225.00 | Finding the right target market and compiling proper survey data |
Understating Competitor's Product | 0.2 | Low | $ 5901780.00 | Compiling data on weakness and strong attributes of competitor |
Overlooking Customer Concerns | 0.22 | Moderate | $ 6491958.00 | Gathering feedback of customer via social media, email, phone, etc. |
Misleading Information | 0.3 | Moderate | $ 8852670.00 | Finding the right target market & verifying (doublechecking) the info |
Inappropriate Analysis | 0.2 | Low | $ 5901780.00 | Finding the right target market and compiling proper survey data |
TOTAL | | | $ 29508900.00 | |
PHASE 1 – RISK MITIGATION(Market Planning)
We have effectively allocated budget to Mitigate Risk for Phase 1
112
113
RISK | PROBABILITY | PRIORITY | RISK BUDGET ALLOCATION | MITIGATION PLAN |
Reduction/Increment in the Budget | 0.24 | Moderate | $ 6396768.00 | Calculating accurately total cost of project, management reserve & budget reserve |
Uneven Resource Allocation | 0.4 | High | $ 10661280.00 | Balance the resource plan after every phase |
Unsatisfied Customers | 0.25 | Moderate | $ 6663300.00 | Gathering feedback of customer via social media, email, phone, etc. |
Lack of Financial Planning | 0.24 | Moderate | $ 6396768.00 | Keeping extra management & budget reserve |
Change in the Product Life Cycle | 0.05 | Low | $ 1332660.00 | Plan the schedule according to change |
Total | | | $ 26653200.00 | |
PHASE 2 – RISK MITIGATION (Placement & Acceptance)
We have effectively allocated budget to Mitigate Risk for Placement & Acceptance
113
1. Risk and Opportunity Analysis
2. Risk and opportunity categorization
4. Risk & Opportunity Budget
3. Risk Mitigation & Opportunity Implementation Plans
5. Financial Analysis Tools
STEPS FOR RISK MITIGATION & OPPORTUNITIES ANALYSIS TO ACHIEVE THE POS OF 80% THAT MEETS THE COMPANY’S REQUIREMENTS
114
115
PREVIOUS PRODUCTS | RISK MITIGATION BUDGET ($) |
MS B0 | $28,796,600 |
MS B1 | $27,728,415 |
MS B2 | $26,250,630 |
LUNAR 2022 | |
115
We are taking full advantage of the low tax rate for our project!
Risk Mitigation Budget = $17,940,000
Opportunity Budget = $8,000,000
Total Mitigation Budget = $25,940,000
We are confident because our comprehensive risk analysis resulted in a low-risk program compared to others to prove that we have better opportunity to achieve 80% POS
We Have A Better Risk Mitigation & Opportunity Implementation Budget !
Low-Risk Budget Program compared to our Competitors
116
We have Explored, Evaluated, and Conducted analysis on various Risks for the Program.
HIGH RISK |
Loss in market share |
30% profit is not attained |
Budget reduction |
Delay in critical path |
Software failure |
MEDIUM RISK |
Failed Market Research |
Customer Choosing a different Product |
Insufficient Vendors |
Manufacturing & Design Incompatibility |
Product Launch Delay |
Defective Products |
Unsatisfied Customers |
LOW RISK |
Change in taxes and cost |
Shorter Product Life Cycle |
Improper Capacity, Capability Assessment |
Under Estimation of Design Budget |
Loss of Inventory Resources |
Raw Materials Supply Delay |
Poor Access to Service centers |
Based on the past experiences and the future demand
We have Explored, Evaluated, and Conducted Analysis on various Risks for the Program.
WE HAVE IDENTIFIED PHASEWISE RISK, CATEGORISED AND PRIORITISED THEM
116
117
67.17% POS
Program Budget without MR
Monte Carlo Analysis for Probability of Success W/O MR
A good MR is required to meet the business Goals
117
118
98.27% POS
Monte Carlo Analysis for Probability of Success
Our Cash Flow model is strong and justified
118
Monte Carlo Analysis For Phase 1
119
Monte Carlo Analysis For Phase 2
120
Monte Carlo Analysis For Phase 3
121
Monte Carlo Analysis For Phase 4
122
Monte Carlo Analysis For Phase 5
Monte Carlo Analysis For Phase 5
123
Monte Carlo Analysis For Phase 6
124
Monte Carlo Analysis For Phase 7
125
IMS phases
126
127
IMS phases
127
Critical Path for Phase 1
128
129
Critical Path for Phase 2
129
130
Critical Path for Phase 3
130
131
Critical Path for Phase 4
131
132
Critical Path for Phase 5
132
133
Critical Path for Phase 6
133
134
Critical Path for Phase 7
134
135
Phase 1 Gantt Chart
PHASE WISE GANTT CHART ANALYSIS TO KEEP A TRACK OF THE PROJECT.
135
136
Phase 2 Gantt Chart
PHASE WISE GANTT CHART ANALYSIS TO KEEP A TRACK OF THE PROJECT.
136
137
Marketing
MANUFACTURING
Finance
Accounting
Project and Program Management
Planning and Scheduling
Quality Assurance and Control
Customer Service
Complete Organizational Breakdown Structure has been Defined
we have developed the organizational breakdown structure (obs)
for the MS LUNAR program
Complete Organizational Breakdown Structure has been Defined
137
WBS PHASEs
138
Phase-1 Market Resources |
1.1 Market Research |
1.2 Initial Business Case SWOT |
1.3 Opportunity Objective |
1.4 Corporate Strategy Check |
1.5 Concept Brief and Conceptual Product Outline |
1.6 Business Case Refinement 1 |
1.7Marketing & Product Plan |
1.8 Technical Recommendations |
1.9 Customer Survey |
1.10 Business Case Refinement2 |
1.11Realistic Technical Specifications |
1.12 Financial Analysis |
1.13 Legal |
1.14Business Model |
1.15 Phase 1 Goal Completion Data |
Phase-2 Placement And Acceptance |
2.1 Resource Strategy Product Team |
2.2 Control Charts (WBS) |
2.3 Technology, Architecture & Platform Strategy |
2.4 Solution Lockdown for the Concept (Conceptual Design) |
2.5 Baseline Feature Descriptions |
2.6 Budgetary Estimates |
2.7 Staff Planning |
2.8 Product Life - Cycle |
2.9 Project Control (IMP, IMS) |
2.10 Management Review / Decision to invest |
139
PHASE 3 Project Definition |
3.1 Project Business Review |
3.2 Staff Planning |
3.3 Product Technical Specification |
3.4 Intellectual Property Review |
3.5 Preliminary Design Review (PDR) |
3.6 Technical Requirements Allocation |
3.7 Business / Manufacturing Requirements Allocation |
3.8 System Analysis, Modeling, and Simulation |
3.9 Product / System Test Strategy |
3.10 Sub Contractor |
3.11 Manufacturing Strategy |
3.12 Program Commitment Statement |
3.13 Management Involvement |
3.14 Project Management Plan for Implementation Phase |
3.15 Sourcing |
3.16 Supply Chain logistics and distribution |
3.17 Phase 3 Goal Completion Date |
PHASE 4 Implementation |
4.1 Subsystem Specifications |
4.2 Test Specifications |
4.3 Supply Chain Management |
4.4 Subcontractors |
4.5 Product / System |
4.6 Critical Design Review (CDR) |
4.7 Documentation and Training |
4.8 System Test |
4.9 Manufacturing Systems and Processes |
4.10 Sourcing |
4.11 Intellectual Property Review |
4.12 Project Plan |
4.13 Manufacturing Materials |
4.14 Ready for Field Test |
4.15 Manufacturing Systems and Processes |
4.16 Sourcing |
4.17 Prototype Testing |
4.18 Marketing Artifacts |
4.19 Ready for Product Rollout |
4.20 Product / Systems |
4.21 Phase 4 Goal Completion Date |
140
PHASE 5 Launch and Support |
5.1 Project Staffing Plan for launch and close - out phase |
5.2 Intellectual Property Review |
5.3 Manufacturing Systems and Processes |
5.4 Sourcing |
5.5 Cost Management |
5.6 Launch preparation activities |
5.7 Training and Documentation |
5.8 Project Business Review |
5.9 Project Plan |
5.10 Manufacturing Engineering Support |
5.11 Warranty Repair Center |
5.12 Phase 5 Goal Completion Date |
PHASE 6 PRODUCTION |
6.1 Product / System |
6.2 Manufacturing Systems and Processes |
6.3 Sourcing |
6.4 Cost Management |
6.5 Final Business Review |
6.6 LRIP |
6.7 FRP |
6.8 Project Lessons Learned |
6.9 Retirement Plan Approved |
6.10 Product Lessons Learned |
PHASE 7 Customer Support |
7.1 Staffing Plan |
7.2 E-Commerce Management |
7.3 Call Center Operational |
7.4 Back Logistics |
7.5 Product Data Management |
141
142
we have developed the wbs vs obs matrix which has been linked and cost accounts Determined
Every task is tracked to a specific Cost Account from OBS/WBS Matrix
142
143
We have summarized top level program plan which shows an overall picture of what our project timeline looks like.
PHASES | MONTHS | START DATE | END DATE |
Market Planning | 0-4 | 09-01-2022 | 01-30-2023 |
Placement & Acceptance | 5-8 | 01-31-2023 | 07-06-2023 |
Project Definition | 9-11 | 07-07-2023 | 10-17-2023 |
Implementation | 12-21 | 10-18-2023 | 04-25-2024 |
Launch & Closeout | 22-24 | 04-25-2024 | 08-23-2024 |
Production | 24-48 | 08-26-2024 | 01-22-2026 |
Customer Support | 24-48 | 08-29-2024 | 09-02-2026 |
PHASEWISE PROJECTED SCHEDULE
143