PROGRAM EVALUATION �AND �REVIEW TECHNIQUE (PERT)
Dr Adewale Abimbola, FHEA, GMICE.
Aim: Program Evaluation and Review Technique (PERT)
�Objectives: At the end of the lesson, the students should be able to:
Aim and Objectives
Introduction
Network Analysis
Figure 1. Nomenclature for compiling the Program Evaluation and Review Technique (March, 2017).
Figure 2. Nomenclature for compiling the Critical Path Method (March, 2017).
Definition – PERT
PERT uses probabilistic time estimates.
Definition – PERT Formula
PERT weighted average =
optimistic time + (4 X most likely time) + pessimistic time
6
Example: If the optimistic time = 8 days, most likely time = 10 days, and pessimistic time = 24 days
PERT weighted average =
8 + (4 X 10) + 24 = 12 days
6
Therefore, you would use 12 days on the network diagram instead of 10 days when using PERT.
Worked Example
Using the information in the table below;
All time in weeks.
Activity/Task | Optimistic (O) | Realistic (R) | Pessimistic (P) | PERT time t = (O + 4R + P) /6 (Expected duration) | predecessor |
A | 2 | 3 | 4 | | |
B | 1 | 2 | 3 | | A |
C | 3 | 5 | 7 | | A |
D | 2 | 5 | 8 | | C |
E | 3 | 4 | 5 | | B |
F | 8 | 10 | 18 | | D |
G | 3 | 3 | 9 | | D, E |
H | 6 | 6 | 12 | | F, G |
Worked Example: Solution
Activity/Task | Optimistic (O) | Realistic (R) | Pessimistic (P) | PERT time t = (O + 4R + P) /6 (Expected duration) | predecessor |
A | 2 | 3 | 4 | 3 | |
B | 1 | 2 | 3 | 2 | A |
C | 3 | 5 | 7 | 5 | A |
D | 2 | 5 | 8 | 5 | C |
E | 3 | 4 | 5 | 4 | B |
F | 8 | 10 | 18 | 11 | D |
G | 3 | 3 | 9 | 4 | D, E |
H | 6 | 6 | 12 | 7 | F, G |
All time in weeks.
Worked Example: Solution
2) Sketch the project network or logic.
Activity/Task | PERT time t = (O + 4R + P) /6 (Expected duration) | predecessor |
A | 3 | |
B | 2 | A |
C | 5 | A |
D | 5 | C |
E | 4 | B |
F | 11 | D |
G | 4 | D, E |
H | 7 | F, G |
All time in weeks.
Worked Example: Solution
3) Find the critical path and expected project completion time.
Importance – PERT
Self-assessment Task 1 – PERT
Using the information in the table below;
All time in days.
Activity/Task | Optimistic (O) | Realistic (R) | Pessimistic (P) | PERT time t = (O + 4R + P) /6 (Expected duration) | predecessor |
A | 12 | 15 | 18 | | |
B | 6 | 9 | 12 | | |
C | 9 | 12 | 15 | | A |
D | 6 | 9 | 18 | | B |
E | 18 | 30 | 36 | | B |
F | 9 | 12 | 15 | | A |
G | 36 | 36 | 42 | | C |
H | 42 | 48 | 54 | | D |
I | 6 | 12 | 18 | | A |
J | 3 | 6 | 9 | | H.G.E |
K | 3 | 6 | 9 | | F,J,I |
Self-assessment Task 2 – PERT
Using the information in the table below;
All time in weeks.
Activity/Task | Optimistic (O) | Realistic (R) | Pessimistic (P) | PERT time t = (O + 4R + P) /6 (Expected duration) | predecessor |
A | 1 | 2 | 4 | | - |
B | 3 | 5 | 7 | | - |
C | 9 | 11 | 15 | | A |
D | 6 | 9 | 11 | | B, G |
E | 8 | 10 | 13 | | C, D |
F | 1 | 3 | 7 | | D |
G | 3 | 6 | 9 | | A |
H | 4 | 4 | 5 | | E |
I | 2 | 5 | 9 | | - |
J | 3 | 6 | 9 | | I |
References/Bibliography