1 of 17

December 7, 2021

Society of American Military Engineers

Internal Use

2 of 17

Avangrid Renewables Offshore Wind: Part of IBERDROLA Group’s Global Offshore Wind Portfolio

Capacity TBC

Operational

1.4GW

Construction

2.6GW

Pre-FID

3.4GW

Development

31GW

2

Offshore Wind – Avangrid Renewables

avangridrenewables.us

Internal Use

3 of 17

AVANGRID: $39 Billion in Assets with a Presence in 24 States

  • Third largest wind operator in the US 
  • Approx. 8 GW wind and solar in operation
  • Total offshore wind lease capacity approx. 5 GW

Wind

Solar

Thermal

Networks

3

Offshore Wind – Avangrid Renewables

avangridrenewables.us

Internal Use

4 of 17

Vineyard Wind Restructuring Agreement

4

Offshore Wind – Avangrid Renewables

avangridrenewables.us

Internal Use

5 of 17

534 Lease Area = New England Wind

Project Description

03

Park City Wind

Commonwealth Wind

534 Lease Area

Vineyard Wind 1

( 501 Lease Area)

    • Project capacity: 804 MW (51 to 54 WTGs)
    • Distance to shore: 19 mi from the SW corner of Martha’s Vineyard and 23 mi from Nantucket
    • Landing location: Barnstable, MA
    • POI: West Barnstable, MA - 345 kV� Transmission: Two (2) Circuits - 275 kV HVAC
    • Permitting status: Construction and Operations Plan (COP) submitted in July 2020, State permits (EFSB and MEPA) filed.
    • PPA: Eversource, United Illuminated Company Offtake/Term: 804 MW PPA/20 years

Commonwealth Wind (CWW) Parameters

    • Project capacity: 825 MW – 1,232 MW (52 to 77 WTGs)
    • Distance to shore: 22 mi from the SW corner of Martha’s Vineyard and 33 mi from Nantucket
    • Landing location: Barnstable, MA

New Bedford / Fairhaven, MA (alternate)

    • POI: West Barnstable, MA - 345 kV

Acushnet, MA - 115 kV

Transmission: Two (2) / Three (3) Circuits - 275 kV HVAC

    • Permitting status: Construction and Operations Plan (COP) submitted in July 2020 (together with PCW). State permits to be filed in 2022.
    • PPA: MA-III Solicitation Potential Award

Park City Wind (PCW) Parameters

5

Offshore Wind – Avangrid Renewables

avangridrenewables.us

Internal Use

6 of 17

Park City Wind Status

  • Reviewing geotechnical data collected for the cable landing, offshore route and substation – local fishing vessels used for offshore support
  • Launching tenders for all major packages of the project (WTGs, Main Electrical Equipment, Offshore Substation)
  • Federal permitting public comment period active

6

Offshore Wind – Avangrid Renewables

avangridrenewables.us

Internal Use

7 of 17

2021 main G&G surveys complete. Efforts on CWW to keep permitting timeline

Key Highlights: G&G Surveys

2021 Offshore & Onshore surveys for PCW and CWW

  • 2021 PCW Onshore and HDD Geotech
  • 2021 PCW & partial CWW Deep Geotech with Fugro:
    • Two vessels worked in the campaign
    • 76 locations surveyed, including the location for CWW OSS

  • 2021 PCW & CWW Geophysical with Fugro:
    • 200 kms of lines to cover gaps from VW1 alternates
    • 1800 kms of lines to cover the CWW alternate OECC corridor in federal waters

Ongoing and future 2022 Offshore and Onshore surveys

  • Ongoing benthic and shallow Geotech for CWW alternate corridor in federal waters with Fugro

  • Tendering process for the remaining Deep Geotech for CWW, CWW onshore and HDD Geotech and G&G for state waters

CWW Alternate OECC

PCW & CWW

Base Case OECC

08

OECC – Offshore Export Cable Corridor

7

Offshore Wind – Avangrid Renewables

avangridrenewables.us

Internal Use

8 of 17

WTG Foundations Package Update – Supply & Manufacturing

8

  • Scenarios Defined

    • Park City Wind

      • MP Foundations (bolted MP/TP)

    • Commonwealth Wind

      • Possible Foundation Concepts assumed

        • MPs (bolted MP/TP) –BASE CASE
        • Jackets – Suction Bucket
        • Jackets – Pin piled

Park City Wind

Key Activities & Next Steps

Rest of Zone

Max Wt = 2400t

Max L = 95m

Max Dia = 12m

Max Wt = 2700t

Max L = 95m

Max Dia = 13m

Internal Use

9 of 17

New England Wind WTG staging port in Salem being developed

Key Highlights: Salem Port

AGR/VW partnership with Crowley

  • Crowley to purchase the site, perform due diligence and site improvements
  • AGR/VW to be anchor tenant for up to 10 years

Investment:

  • Prospective Acquisition & Buildout Cost: $180 million.
  • Significant direct investment from Crowley of up to $70 million for site acquisition and redevelopment.
  • Balance of the investment potentially from public sources

08

Site attributes:

  • Property was previously a coal-fired power plant replaced with Salem natural gas plant
  • 42 acres for upland storage
  • Deep water berth
  • No height restrictions for jack-up vessels

9

Offshore Wind – Avangrid Renewables

avangridrenewables.us

Internal Use

10 of 17

Project Description

Location:

  Due east of Corolla, NC and�  southeast of Virginia Beach, VA

Wind Energy Area:

 100% site control under lease agreement with BOEM (signed in 2017).

Lease Area

 Total area: 122,405 acres

Site

Control:

  Landfall:  Easement discussion with City

  Route:  Non-exclusive Franchise Agreement

  Substation:  30-acre option agreement with VBDA

Capacity:

 ~800 MW  

 (Total area potential ~2,500MW)

Permitting:

  In process: site assessment studies, marine geophysical and geotechnical surveys,

 and preliminary engineering incorporated into Construction and Operations Plan

 (submitted  to Bureau of Ocean Energy Management in December 2020).  

COD:

 2026

Inter-connection:

  Birdneck- Landstown 230 kV

  In queue with PJM – in Facility Study phase

Internal Use

11 of 17

Lease awarded and executed

Kitty Hawk given exclusive rights to develop lease area for offshore wind development

Site Assessment Plan approved

Construction and Operations

Plan submitted for first project

BOEM anticipated to start their Environmental Review under NEPA

Initiate state approval process

All necessary permits, authorizations and approvals received for construction and operation

Construction anticipated to start mid-2020s with first power mid-late 2020s

Operation period is anticipated to be 25+ years

PROJECT TIMELINE

Internal Use

12 of 17

Milestones

July 2021

Notice of Intent �Issued by BOEM

April 2021

FAST41 Dashboard

December 2020

Construction and Operations Plan Submitted

Internal Use

13 of 17

$2 Billion

impact in Virginia and

North Carolina’s future

over the next decade.

$1.5 Billion in Construction Activities and Sales

~800 Jobs Annually

$390 Million in Net Household Earnings

$100 Million in Tax Revenue

ECONOMIC IMPACT

Internal Use

14 of 17

  • Engineering services
  • Geotechnical and geophysical services
  • Wind turbines
  • Foundation design and construction
  • Substation design and construction (onshore and offshore)
  • Cable and transmission line design and construction (onshore and offshore)
  • SCADA design and construction
  • Port and vessel services
  • Operations and maintenance
  • Other services (i.e. FAA lighting, drones, avian detection, marine mammal detection, etc.)

Through the project life cycle (development, construction and operations) jobs are anticipated to fall under the following categories:

JOBS

Internal Use

15 of 17

15

Internal Use

16 of 17

Website and Resources

KITTYHAWKOFFSHORE.COM

Community Information

Fishing Community

kittyhawkoffshore.com/fishing

  • Close coordination with commercial and recreational fishing communities
  • Meteorological buoy (access to real-time data)

Military Community

kittyhawkoffshore.com/military

Workforce Development

Mid-Atlantic Wind Training Alliance

Economic Development

kittyhawkoffshore.com/vendors

  • Market engagement initiative to qualify vendors for future procurements

    • Project Updates Fact Sheets
    • Videos Resources

LinkedIn & Facebook

Kitty Hawk Offshore Wind

Twitter

@kittyhawkwind

Instagram

@kittyhawkoffshore

Internal Use

17 of 17

Ashley McLeod

Stakeholder Engagement Director

249 Central Park Ave.

Virginia Beach, VA

757-748-7084

Ashley.mcleod@avangrid.com

Christopher Morris, PE

Director of Offshore Engineering

125 High Street

Boston, MA

617-794-9907

Christopher.morris@avangrid.com

Internal Use