1 of 10

MnDOT’s 2023 ATMA Experiences

Adam Wellner| Principal Project Manager (CAV-X)

mndot.gov/

2 of 10

mndot.gov

2

10/11/23

3 of 10

mndot.gov

3

10/11/23

4 of 10

Operations

  • MnDOT acquired the ATMA system from Kratos in April 2021
  • ATMA system was assigned to a maintenance shop and they were asked to test it.
    • This was in addition to existing work
    • At times communication about issues was not happening in a timely manner
  • For 2023 MnDOT hired (internal temporary positions) 2 employees to operate the ATMA system full time
    • Traveled the state supporting general maintenance operations
    • Operators were empowered to troubleshoot and work with Kratos to solve issues.

mndot.gov

5 of 10

Hardware Modifications�Follower Front Sensor Mounts

mndot.gov

5

10/11/23

6 of 10

Hardware Modifications�Antenna Rack

mndot.gov

6

10/11/23

7 of 10

Dash Display

mndot.gov

7

10/11/23

8 of 10

Other improvements

  • Durability of camera system, moving to MnDOT standard cameras
  • Turn Signal system – sperate lighting system
  • Winterization – decommissioning and recommissioning

  • Upcoming – Working on contracting
    • Design Workshop
    • 3 vehicle platoon

mndot.gov

8

10/11/23

9 of 10

Issues

  • Radio interference – Vermac controller?
  • Loosening tolerances?
  • Needing some higher speed movement “Deadheading”
  • Need to get cameras working again
  • Side Lidar issues
  • E-Stop brake actuator

mndot.gov

9

10/11/23

10 of 10

Other MnDOT Projects

  • Snow Plow Lane Guidance
  • ADAS in Snow Plow fleet
  • Connected workzone devices with automated 511 / WZDx event creation

mndot.gov

10