Microtunneling Under an Active Runway at HIA
October 8, 2024
1
History of HIA
1918-1969 Air Force Base
1969-1998 Owned by Commonwealth PA
1969 1st Commercial Flight
1985 1st Cargo Operator
1998-Present Owned by SARAA
2024 Cargo - UPS, Fedex, DHL
Commercial - Allegiant, American, Delta, United, Frontier
Military – PA Air National Guard
$990M Economic Impact
10,001’ x 200’ Runway 13-31
1955
2
2
Project Development
Project Location
1985
2018
Terminal
Cargo
PA-ANG
RW 13-31
Susquehanna River
3
3
Apron Expansion – Aircraft Parking / Utilization
T/W G
T/L T
T/L H
T/L S
Apron Expansion
4
4
Drainage Outfall – Overview
5
5
Project Level Airfield Restraints
Project Area
6
6
Package 1 (Phase IV) – Drainage and New Outfall
R/W 13-31
Susquehanna River
Drainage and New Outfall
Conformed Documents
- 59 Plan Sheets
- 964 Page Spec. Manual
- 74 Pay Items
7
7
Package 1 – �Box Culvert Outfall and Flood Dike Reconstruction
Dike
Culvert
Airside
River
Endwall
ACB
ACB
Riprap Toe
Maintenance Pad
8
8
Package 1 – �Taxiway A Reconstruction
T/W A Pavement Section
Underdrain
SMGCS CL Lighting
9
9
Package 1 – �Microtunneling – Grouting and Tunnels
T/W A
R/W 13-31
Dike
T/W A
R/W 13-31
Dike
Microtunnel
Microtunnel
10
10
Package 1 – �Microtunneling – Geologic Conditions
T/W A
R/W 13-31
Dike
T/W A
R/W 13-31
Dike
River
Fill
Fill
Bedrock
11
11
Package 1 – �Site Access and Haul Routes
Susquehanna River
R/W 31
R/W 13
Gate 45
Gate 11
New Gates
Staging Areas
Stockpile
Haul Route
Haul Route Area with Crossing Restriction
R/W 31 LCA
R/W 13 LCA
R/W 31 GSCA
R/W 31 GSCA
T/W G
12
12
CSPP – Schedule and LDs
13
13
Package 1 – �CSPP – Phase 1
New AOA Gate
New Gate
New Road
Fence
Fence
Cargo Apron
T/W G
T/W G
T/L H
Terminal
T/L T
30 Calendar Days
14
14
Package 1 – �CSPP – Phase 2A & 2B
T/W G
T/W A
R/W 13-31
T/W F
T/W E
River
2A: 75 Calendar Days
2B: 26 Calendar Days
New Road
Drainage
Reconstruct T/W A
Jacking Pit
Receiving Pit
Outfall
2B
2A
Reconstruct Flood Dike
15
15
Package 1 – �CSPP – Phase 3
45 Calendar Days
T/W G
T/W A
R/W 13-31
T/W F
T/W E
River
Grout Zone
Grout Zone
Grout Zones
(Night-work only)
Nightly Closures
(12:01 to 5:29 AM)
16
16
Package 1 – �CSPP – Phase 4
90 Calendar Days
Nightly Closures
(12:01 to 5:29 AM)
T/W G
T/W A
R/W 13-31
T/W F
T/W E
River
Twin Microtunnels/
Drainage
17
17
Package 1 – �CSPP – Phase 5A & 5B
5A: 22 Calendar Days
5B: 10 Calendar Days
T/W G
T/W A
R/W 13-31
T/W F
T/W E
River
5B
5A
Drainage Connections and Close Pits
Remove Road and Restore Site
Remove Roads and Restore Site
18
18
Package 1 – �CSPP – Phase 6
10 Calendar Days
Drainage
Remove Road and Restore Site
T/W G
T/W A
R/W 13-31
T/W F
T/W E
T/W G
19
19
Package 1 – �CSPP – Phase 7
7 Calendar Days
Drainage
Disconnect/Store Fence
AOA Gate
Cargo Apron
T/W G
T/W G
T/L H
Terminal
T/L T
20
20
21
Microtunneling under an Active Runway at HIA
Questions?