1 of 1

Q] A work is completed by some workers in some days. If the number of workers exceeds by 25, the work completes 5 days earlier. If the number of workers is less by 50, then it takes 20 days more to complete that work. Then find the number of workers and days taken by them to complete that work.

Let the number of workers be x and

the days to complete the work be y.

Sol:

Total work done

(x + 25)

As per the 1st condition

(y – 5)

=

xy

xy

25y

125

5x

+

=

xy

x

5y

+

=

25

……(i)

As per the second condition

(x –50)

(y + 20)

=

xy

xy

50y

1000

+

20x

=

xy

20x

50y

=

1000

……(ii)

2x

5y

=

100

What do we need to find?

No. of workers

No. of days

Work done

2

5

2 × 5 = 10

3

6

3 × 6 = 18

x

y

x × y = xy

Let us take an example

If 2 workers work for 5 days

Total work done will be

If 3 workers work for 6 days

Total work done will be

Similarly If x workers work for y days

Total work done will be

25y

=

–5x

+

125

(dividing throughout by 5)

(dividing throughout by 10)

Here y has the same coefficient with different signs

Here y has the same coefficient with different signs

So let us add the two equations

If the number of workers exceeds by 25 means the new number of workers

= x + 25

Work gets completed 5 days earlier means number of days to required to complete the work = y - 5

Did the total work change??

No, it is a same and the total work done = xy

= xy

Adding equations (i) and (ii)

x

5y

+

=

25

2x

5y

=

100

x

=

125

Substituting x = 125 in equation (ii)

125

+

5y

5y

25

=

+

125

=

25

5y

150

=

y

30

=

Substitute the value of x in any of the two equations

The number of workers is 125

and the number of days to

complete the work is 30.