1 of 8

Projects - Summary

Major Systems

$450,000

5 HVAC Systems

Safety/Security

$166,000

Fire Detection System, Emergency Action Plan

Smaller Systems

$368,300

Organ, Leaks, Parking Lot, Repairs

Contingency

$199,000

Unplanned,

Inflation

Potential Reach Out Projects

$219,000

9 Projects

Update North Lawn Area, Parlor

Family Bathrooms

Prior Gift -$30,000

2025 Scheduled $388,300

2026 Scheduled $330,000

2027 Scheduled $240,000

2028 Scheduled $150,000

2025-28 Contingency $199,000

2026-28 Reach Projects $219,000

​

Total 2025-2028 $1,496.300

Gift

$30,000

Parlor Update

Technology

$124,000

Streaming, WiFi, A/V

1/10

St Paul’s Rochester UMC 2025 – 2028 Capital Campaign

Updated 2/12/2025

2 of 8

Projects are Characterized by:

  • Restore
    • Fix a Current System
  • Renew
    • Install a New System
  • Reach Out
    • Add a New Capability

Projects can be a Combination of:

  • Restore
  • Renew
  • Reach Out

Or

  • Projects can have only one Characteristic

How are Projects Prioritized?

  • If a Failure Occurs, What is the Impact on Operations?
  • How Likely is a Failure to Occur?
  • Can we wait until a Failure Occurs, i.e. Extend Life?
  • Are Funds Available?

​

How are Decisions Made?

  • Is Staff or Congregational Input Needed?
  • Is Professional Redesign Required?
  • Can the System be Restored (Fixed)?
  • Should the System be Renewed (Install New, or Partial New)
  • Are there Opportunities to Add Capability or Integration?
  • Can it be Integrated with Other Projects?

​

2/10

Projects - Process

Setting Priorities and Making Decisions

3 of 8

Old Low Efficiency Boiler, Pumps, Valves and Piping

Replaced

New High Efficiency Boiler, Pumps, Valves and Piping

  • $215,974 Boiler, Plumbing, Valves, Pumps, Controls
  • $ 21,400 Engineering Design, Quality Oversight
  • $ 15,000 Boiler Room Window Replacement
  • $252,347 Total Project Cost

Projects – Completed 2024

3/10

Replacing Low Efficiency Boiler and Components

4 of 8

Projects – Completed 2024

4/10

  • Light Pole Fell in Storm Due to Corrosion
  • Replaced 11 Poles and Lights
  • Added 110 Volt Outlets to Three Poles
  • $30,335 Project Cost

Emergency Replacement of Parking Lot Lighting

5 of 8

  • Engineering Firm Recommendation:
  • “30-year-old indoor multi-zone air handling unit and air-cooled condenser Both are beyond their useful life and should be replaced.”
  • $100,000 Estimated Cost
  • Condensing Unit for Offices and Classrooms in Courtyard
  • Replace Unit

Major System Planned Update - Renew Classroom HVAC System

  • Air Handler in Mechanical Room for Office and Classroom Areas
  • Update AC Coils, Bearings, Motor, Controls
  • This unit is the size of a school bus

Projects – Major Project 2025

5/10

8” x10”

Frame

6 Zones

6 of 8

Smaller System Planned Update - Hickey Hall Portico Repair

  • Four Poles Severely Corroded
  • Cut-Out Concrete
  • Weld Reinforcing Plates On
  • Repair Damaged Stucco on Portico
  • $10,000 Estimated Cost
  • May Attempt Ourselves

Projects – Smaller Project 2025

6/10

7 of 8

Potential Reach Out Project - Renew Front Lawn Area

  • Add a Portico to Office Entrance
  • Add Benches and Lighting
  • Add an Electronic Sign
  • Combine with Walkway to Hickey Hall Portico
  • Add a Patio Area on Existing Mechanical Room Pad
  • Integrate with Water Intrusion Repair

S Grace

Projects – Reach Out Project 2025

7/10

8 of 8

Potential Reach Out Project – Renew Front Lawn Area

Down to Garden

Of Hope

  • Earlier Leak Fix
  • Removed Bushes
  • Excavated
  • Sealed
  • Added Pavers
  • Sealed Wall

New Electronic LED Sign

  • New Portico
  • Same Design as at Hickey Hall
  • Add Benches
  • Add Lighting
  • Existing Portico
  • Hickey Hall
  • Add Benches

Establish a Patio on the Mechanical

Room Cement Ceiling Slab

Add Electrical Outlets

To Front of Building

Bell Tower

  • Leak Fix -
  • Remove Bushes
  • Excavate
  • Seal
  • Add Paver Walkway

N

Projects – Reach Out Project 2025

8/10