Forest Hills Elementary School
LAKE OSWEGO SCHOOL DISTRICT
Design Process Timeline
W E E K S
Bond Election
Design Process Outline
2 0 2 5
2 0 2 6
March
April
May
June
July
August
September
October
November
December
January
February
March
Initiate Project
Permit Submittal (Early Work)
★
Pre-Design and Programming
Schematic Design
Design Development
Construction Documents
Bidding
Land Use Submittal
We Are Here
Stakeholder/Focus
Group Meetings
Rooted in Place
Connection to Community
Harmony with Neighborhood
Maintain Entry Location
Pick up/Drop off to Emulate Existing Conditions
Zone Site into Active + Focused Areas
Maximize Fields + Play Areas
Project Drivers
Site Concept
Exterior Studies
Consolidate playgrounds
Clarifying site circulation
Building size
Building height
Budget
Initial Feedback
Reduced School Footprint
Consolidate playgrounds
Clarifying site circulation
Building size
Building height
Budget