1 of 48

What has the Village of Constantine DDA Done

October 2023

2 of 48

Village of Constantine�Downtown Development Authority�Board Members

2

Member

Date Appointed

Term Expiration

Type

Piper, Larry

12/31/2015

12/31/2023

At Large

Eley, Mike

12/31/2015

12/31/2023

Business Owner, Resident

Hall, Seth

12/31/2020

12/31/2024

Business Owner

Hoover, Greg

12/03/2020

12/31/2024

Business Owner

Mathers, Gary

N/A

N/A

Village President

Heskett, John

12/31/2021

12/31/2025

Business Owner

Mathers, Myra

12/31/2021

12/31/2025

At Large – Resident

Wolcott, Veronica

07/01/2022

12/31/2026

Bank Manager

Helman, D

07/01/2022

12/31/2026

Business/ Resident

Byler, Brenda

12/31/2018

12/31/2027

At Large-Business Owner

Larink, Mike

12/31/2018

12/31/2027

Business Owner, Resident

3 of 48

CDBG Grants�(Community Development Block Grant)

4 of 48

CDBG Grants

Location

Development

Local

Rehabilitation

Total Investment

176 S Washington St

$ 45000

$ 15,000

$ 10,000

$ 70,000

105 S Washington St

$ 45,000

$ 15,000

$ 20,000

$ 80,000

130 E Water St

$ 33,750

$ 11,862

$ 40,100

$ 85,712

 

 

 

 

CDBG Total Investment into the community

 

 

 

$ 235,712

$ 235,712

5 of 48

DDA Façade Grant

6 of 48

Project

Project Total

15%

Total Project

25% Match

Village Match

Amount Due from Owner

Pipers

$ 13,100

$ 1,965

$ 15,065

$ 3,766

$ 3,000

$ 766

Harvey House Hotel & Restaurant

$ 28,860

$ 4,329

$ 33,189

$ 8,297

$ 3,000

$ 5,297

Wolf Graphic’s

$ 43,200

$ 6,480

$ 49,680

$ 12,420

$ 6,000

$ 6,420

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

$ 85,160

$12,774

$ 97,934

$ 24,484

$ 12,000

$ 12,484

$ 97,934

7 of 48

Village of Constantine�DDA Façade�Grants��25 Grants issued to date

8 of 48

Date

Projects

Address

Project Total

Request Amount

Paid out

1/13/2011

Karen's What-Not Shop

160 E Water Street

$3,745

$2,809

$1,623

9/23/2010

Masonic Lodge 35

189 S Washington Street

$4,000

$1,969

$1,969

10/10/2011

Tommy Parsons - Harvey Hotel

125 W Water Street

$28,769

$3,000

$3,000

10/19/2010

Vinette Reames

140 S Washington Street

$7,059

$2,912

$2,912

12/7/2010

Rachel's

130 E Water St

$3,834

$2,876

$2,876

12/19/2012

Shirley Jones

100 S Washington Street

$1,672

$1,254

$1,254

4/22/2011

Tracy Johnson - Meeks Mill Café

138 E Water Street

$8,900

$3,000

$3,000

2/11/2013

MEDC Facada Match Renee Wolf

160 & 170 S Washington Street

$21,390

$6,000

$6,000

8/8/2014

Shear Styles

155 S Washington Street

$3,000

$2,250

$2,250

4/4/2014

Renee Wolf

160 & 170 S Washington Street

$8,695

$6,000

$6,000

6/19/2014

John Schroer

182 S Washington Street

$2,700

$2,100

$2,027

3/23/2015

Matt & Char Ryan

145 & 155 S Washington St

$4,094

$1,988

$1,988

3/3/2016

Don Heskett

120 * 138 S Washington St

$28,055

$6,000

$6,000

1/28/2015

Darius Jusaitis

119 S Washington St

$7,000

$3,000

Holding

1/28/2015

Darius Jusaitis

106-117 S Washington St

$9,350

$3,000

Holding

1/28/2015

Darius Jusaitis

104-108 E Water St

$11,200

$3,000

Holding

12/16/2013

Matt & Char Ryan

145 & 155 S Washington St

$6,000

$4,094

$3,070

6/19/2017

Eley Funeral Home

280 S Washington St

$4,400

$3,000

$3,000

11/15/2018

Tracy Johnson - Meeks Mill Café

138 E Water Street

$3,359

$2,519

$2,519

10/4/2018

Joe Fox

130 E Water St

$2,140

$1,605

$1,605

6/14/2018

Brett Thomspon

140 S Washington Street

$2,247

$1,777

$1,777

7/1/2018

Jeremiah Ussery

116 S Washington St

$2,679

$2,009

$2,009

8/9/2019

Darius Jusaitis

119 S Washington St

$3,000

8/9/2019

Darius Jusaitis

106-117 S Washington St

$3,000

8/9/2019

Darius Jusaitis

100 S Washington Street

$3,000

8/16/2020

Rex Fisher

100 W Water Street

$25,000

$12,500

$12,500

12/14/2022

Mike Larink

182 S Washington Street

$5,958

$2,979

$2,979

04/15/23

James Nowak

150 S Washington St

$16,283

$4,500

$4,500

$221,529

$86,140

$83,857

DDA Façade Grants

$ 83,857

9 of 48

182 S Washington St

Total Improvement $ 5,958

DDA Investment $ 2,949

10 of 48

2023 Projects

150 S Washington St

Total Improvement $ 16,283

DDA Investment $ 4,500

11 of 48

Downtown Infrastructure Grant (DIG)�Funding Sources �

12 of 48

East Parking Lot Improvements

Downtown Infrastructure Grant (DIG)�

13 of 48

CDBG/State

$ 292,124

Local Unit

DDA 20%

$ 67,508

Total

match

$ 390,032

Downtown Infrastructure Grant (DIG)�Funding Sources �

$ 397,032

14 of 48

Elimination Program

15 of 48

1005 S Washington St

16 of 48

Job

Price

Demolition

$ 8,500.00

top soil/seeding

$ 1,054.40

 

$ 9,554.40

5%

$ 477.72

$ 10,032.12

2012 Michigan Elimination Program

$ 10,032

17 of 48

Rental Rehab Grant Funding

  • 3 Different building
  • Total of 11 new apartments

18 of 48

160 1/2 S Washington St

19 of 48

105 ½ S Washington St

20 of 48

177 ½ S Washington St.

21 of 48

Rental Rehab Grant Funding

Location

MSHDA's Match

Owners

Total Investment

170 1/2 S Washington St

$ 70,000

$ 22,500

$ 92,500

105 1/2 S Washington St

$ 70,000

$ 40,000

$ 110,000

177 1/2 S Washington St

$ 330,000

$ 160,000

$ 490,000

 

 

 

 

 

 

 

$ 692,500

$ 692,500

22 of 48

Summary of Grant $$ Spent

Project

Dollar Amount

CDBG

$ 235,712

Façade (Federal)

$ 97,934

Façade (DDA Grants)

$ 89,857

DIG

$ 397,032

Elimination Program

$ 10,032

Rental Rehad

$ 692,500

$ 1,523,067

23 of 48

Village of Constantine �DDA Properties

24 of 48

South Washington Street

Donated to the Village

25 of 48

186 S Washington St.

SOLD

26 of 48

West Water Street

Donated to the Village

27 of 48

Donated to the Village

28 of 48

125 West 2nd Street

SOLD

29 of 48

Also Sold

30 of 48

Recurring Expenses

  • Electric Bills
    • Downtown lights
    • 186 S Washington Street
  • Mowing
    • West Water Park
  • Weeding
    • East Parking Park
  • Wages
    • DDA Director

31 of 48

Changes going on in the Downtown

32 of 48

115 S Washington St

New Construction for Hair Salon

33 of 48

119 S Washington St

34 of 48

135 S Washington Street - Provisioning

Started construction

35 of 48

36 of 48

“NOW” Magnus Brewing

SOLD now OPEN

37 of 48

38 of 48

For Sale – 155 S Washington Street

SOLD

39 of 48

169 S Washington St

Sold

40 of 48

225 S Washington St

Ba Bargain's

41 of 48

186 S Washington St

SOLD

42 of 48

SOLD - 182 S Washington St

Larink Construction

43 of 48

120 S Washington St

Tattoo Shop

44 of 48

45 of 48

Revised Grant Program��Business Investment Program�Constantine DDA�Adopted July 22, 2020

46 of 48

Qualified expenses include permanent property improvements, such as:

  • Creation or expansion of service areas for restaurants and retailers, both inside & out
  • Exterior improvements, including signage, awnings, paint, windows, and brickwork
  • Construction costs related to code compliance for office, restaurant, & retail uses

47 of 48

48 of 48

Thank you!