BEDFORD CENTRAL SCHOOL DISTRICT
“Inspiring and Challenging Our Students”
Potential Spring 2022 Bond Referendum & Master Plan Update
January 26, 2022
DRAFT
01-26-22
Bedford Central School District January 26, 2022
Air Conditioning
Master Planning
Air conditioning within the District came up in discussion at the December 15, 2021 BOE Meeting. Some air conditioning work has already been included within the suggested infrastructure work for a Spring 2022 Bond; other work could be considered.
DRAFT
01-26-22
Potential Air Conditioning Projects
Bedford Hills Elementary $ 189,230
Mount Kisco Elementary $ 533,400
Fox Lane Middle School $ 450,000
Fox Lane High School $ 6,327,800
Note: There is air conditioning work included within $24.9M Infrastructure Work Reviewed 12-15-21 Total for Pound Ridge and
West Patent, not included within $7.5M listed on this slide.
Subtotal of Reviewed Work Scope
( DRAFT: not yet proposed )
$ 7,500,430
DRAFT
01-26-22
Potential Spring 2022 Bond Reviewed Projects
District-Wide Infrastructure Projects $ 24,893,777 12-15-21
MS New Stairs & Connecting Corridors $ 11,022,200 12-15-21
MS Courtyard & Outdoor Gym Improvements $ 2,610,200 12-15-21
MS Central Building Improvements $ 8,270,500 12-15-21
MS Houses Reconstruction $ 7,474,600 12-15-21
MS Wellness, Fitness, Library & Dining $ 4,683,125 12-15-21
HS Library, Cafeteria, Guidance & Art Offices $ 16,760,000 12-15-21
HS STEM, Gallery & Fitness/ Wellness $ 8,940,000 12-15-21
Fox Lane Campus Athletics $ 15,003,205 12-15-21
Air Conditioning $ 7,500,430 Extended Master Plan Review
Additionally Reviewed non-Priority 1 BCS Items $ Future + + + Extended Master Plan Review
Other Potential Projects to Review $ Future + + + Extended Master Plan Review
$ 70,000,000
Bond Counsel for the District has advised that the development of a Spring 2022 Bond Referendum up to approximately $70M would not impact the tax levy.
$ 107,158,037
$ 99,657,607
Additional discussion at the 12-15-21 Board of Education Meeting brought back air conditioning as a thought for consideration;
Master Planning work scope will continue to evolve and develop into the future.
DRAFT
01-26-22
Part 2 Potential Spring 2022 Bond Timeline
Part 3 BCS & Infrastructure Projects
Part 4 Learning Environments
Part 5b Fox Lane High School
Part 6 Elementary Schools
Part 8 Potential Spring 2022 Bond Referendum
Part 1 Master Plan: Vision & Facilities
Part 7 Master Planning & Next Steps
DRAFT
01-26-22
Bedford Central School District January 26, 2022
Fox Lane High School
DRAFT
01-26-22
Classroom Sections
Support Classrooms
Administration, Nurse, Faculty
Core & Special Dedicated Spaces
3rd Floor
1st Floor
2nd Floor
DRAFT
01-26-22
Inspiration
Imagery
HS Learning Environments
DRAFT
01-26-22
Traditional School Design
“Double-Loaded” Corridor
Conceptual Diagram of a more Traditional Approach
to (K-12) Educational Design (“Boxes” of Spaces)
DRAFT
01-26-22
‘Decompartmentalization’
of the Student Experience
Conceptual Diagram of a New Approach
to (K-12) Educational Design (“Exchange” of Spaces)
DRAFT
01-26-22
Learning Environment Design
DRAFT
01-26-22
Learning Environment Design
DRAFT
01-26-22
Learning Environment Design – Completed Suffolk County HS Project
DRAFT
01-26-22
Learning Environment Design – Completed Nassau County HS Project
DRAFT
01-26-22
Learning Environment Design – Current Westchester County HS Project
DRAFT
01-26-22
Learning Environment Design – Current Westchester County HS Project
DRAFT
01-26-22
Learning Environment Design – Current Westchester County HS Project
DRAFT
01-26-22
Learning Environment Design – Current Westchester County HS Project
DRAFT
01-26-22
Conceptual Plans:
Fox Lane High School
HS Learning Environments
DRAFT
01-26-22
DRAFT
01-26-22
DRAFT
01-26-22
DRAFT
01-26-22
Science
Academics
Academics
Arts
Arts
STEAM
P.E.
Student
Learning
Exchange
Wellness
DRAFT
01-26-22
$25.7M
Fox Lane HS
Interior Reconstruction
Color Key:
New Construction
First Floor Plan Diagram
DRAFT
01-26-22
CURRENT PROGRAM AREAS
Library 9,884 SF
Large Cafeteria 3,619 SF
Small Cafeteria 2,381 SF
Guidance & Faculty Office 3,944 SF
Gallery 539 SF
Student Commons 6,023 SF
Small Gym 3,813 SF
30,203 SF
DRAFT
01-26-22
CURRENT PROGRAM AREAS
Library 9,884 SF
Library Mezzanine 929 SF
Large Cafeteria 3,619 SF
Small Cafeteria 2,381 SF
Guidance & Faculty Office 3,944 SF
Gallery 539 SF
Student Commons 6,023 SF
Small Gym 3,813 SF
OVERALL 31,159 SF
POTENTIAL PROGRAM AREAS
Library/ Learning Exchange 8,189 SF
Ellipse/ Exchange 626 SF
Conference Room/ Exchange 454 SF
Dining/ Learning Exchange 3,980 SF
Dining/ Learning Exchange 2,799 SF
Guidance & Faculty/ Exchange 5,113 SF
Gallery/ Exchange 837 SF
Student Commons/ Exchange 12,977 SF
Wellness/ Fitness/ Exchange 3,576 SF
Engineering/ STEAM/ Exchange 1,601 SF
OVERALL 40,152 SF
DRAFT
01-26-22
Conceptual Renderings:
Fox Lane High School
HS Learning Environments
DRAFT
01-26-22
Current Photo of Library @ Upper Windows & Mezzanine
DRAFT
01-26-22
Current Rendered View of Library @ Upper Windows & Mezzanine
DRAFT
01-26-22
Potential Rendered View of Library @ Upper Windows - No Mezzanine
DRAFT
01-26-22
Current Photo of Library @ Lower Windows
DRAFT
01-26-22
Current Rendered View of Library @ Lower Windows
DRAFT
01-26-22
Potential Rendered View of Library @ Lower Windows
DRAFT
01-26-22
Current Photo of Library @ Mezzanine
DRAFT
01-26-22
Current Rendered View of Library @ Mezzanine
DRAFT
01-26-22
Potential Rendered View of Library without Mezzanine
DRAFT
01-26-22
Current Photo of Library underneath Mezzanine
DRAFT
01-26-22
Current Rendered View of Library underneath Mezzanine
DRAFT
01-26-22
Potential Rendered View of Library without Mezzanine
DRAFT
01-26-22
Current Photo of Library between Mezzanine & Guidance
DRAFT
01-26-22
Current Rendered View of Library between Mezzanine & Guidance
DRAFT
01-26-22
Potential Rendered View of Library & Guidance (no Mezzanine)
DRAFT
01-26-22
Current Photo in Library under Mezzanine Stair
DRAFT
01-26-22
Current Rendered View in Library under Mezzanine Stair
DRAFT
01-26-22
Potential Rendered View in Library without Mezzanine
DRAFT
01-26-22
Current Photo of Entry into Small Cafeteria
DRAFT
01-26-22
Current Rendered View of Entry into Small Cafeteria
DRAFT
01-26-22
Potential Rendered View of Entry into Student Dining/ Exchange
DRAFT
01-26-22
Current Photo of Entry into Large Cafeteria
DRAFT
01-26-22
Current Rendered View of Entry to Large Cafeteria
DRAFT
01-26-22
Potential Rendered View of Entry into Student Dining/ Exchange
DRAFT
01-26-22
Conceptual Renderings:
Fox Lane High School
HS Learning Environments
DRAFT
01-26-22
Current
Potential
DRAFT
01-26-22
Cafeterias to the Right
Current Main Corridor
Library to the Left
Commons Beyond
DRAFT
01-26-22
Potential Occupied Main Corridor
Library & Exchange to the Left
Commons Beyond
Dining & Exchange to the Right
DRAFT
01-26-22
Potential Occupied Main Corridor
Library & Exchange to the Left
CURRENT HALLWAY LOCATION
This area currently
in the “back” of the library
Dining & Exchange to the Right
Commons Beyond
DRAFT
01-26-22
Current view of first floor.
Kitchen
Auditorium
Guidance
Small Gym
Library
Large Cafeteria
Small Cafeteria
Courtyard
Gallery
DRAFT
01-26-22
Proposed view of Student Learning Exchange (SLE) at first floor.
Kitchen
Auditorium
SLE
DRAFT
01-26-22
Current view of first floor.
Large Cafeteria
Kitchen
Commons
Small Gym
Small Cafeteria
Auditorium
Courtyard
Gallery
Library
Guidance
DRAFT
01-26-22
Kitchen
Auditorium
Proposed view of Student Learning Exchange (SLE) at first floor.
Fitness/
Wellness
SLE
STEAM
Commons
Gallery
DRAFT
01-26-22
Potential
DRAFT
01-26-22
Potential
DRAFT
01-26-22
Potential
DRAFT
01-26-22
Potential
DRAFT
01-26-22
Potential
DRAFT
01-26-22
Potential
DRAFT
01-26-22
Potential
DRAFT
01-26-22
Potential from Main Entry; Library to left; Dining to right
DRAFT
01-26-22
Potential View of Library Entrance to right; Dining to left
DRAFT
01-26-22
Potential View within Library looking towards Dining
DRAFT
01-26-22
Potential View in Main Hallway; Guidance to left; Dining to right
DRAFT
01-26-22
Potential View of New Gallery straight ahead
DRAFT
01-26-22
Potential View of Widened Access to Student Commons to left
DRAFT
01-26-22
Potential View of Wellness/Fitness to left; STEAM to right
DRAFT
01-26-22
Conceptual Video:
Current & Potential
Fox Lane High School
HS Learning Environments
DRAFT
01-26-22
Cost Components by Area
A Library, Cafeterias, Guidance, Art Offices & Connectors (Interior Reconstruction)
$ 14,200,000
B New Guidance/ Offices (New Construction)
$ 2,560,000
C Site Work, Gardens & Misc.
$ 500,000
D Renovate Small Gym to Wellness & Fitness (Interior Reconstruction)
$ 1,140,000
E Renovate Locker Rooms,Trainer & Adjacent Storage (Interior Reconstruction)
$ 4,800,000
F New STEAM Classroom & Gallery @ Courtyard (New Construction)
$ 2,500,000
Overall
$ 25,700,000
B
D
A
F
C
E
C
E
F
DRAFT
01-26-22
Bedford Hills ES – Bedford Village ES – Mount Kisco ES – Pound Ridge ES – West Patent ES – Fox Lane MS – Fox Lane HS
BEDFORD CENTRAL SCHOOL DISTRICT
“Inspiring and Challenging Our Students”
Potential Spring 2022 Bond Referendum & Master Plan Update
January 26, 2022
DRAFT
01-26-22