1 of 77

Bedford Hills ES – Bedford Village ES – Mount Kisco ES – Pound Ridge ES – West Patent ES – Fox Lane MS – Fox Lane HS

BEDFORD CENTRAL SCHOOL DISTRICT

“Inspiring and Challenging Our Students”

Potential Spring 2022 Bond Referendum & Master Plan Update

January 26, 2022

DRAFT

01-26-22

2 of 77

Bedford Central School District January 26, 2022

Air Conditioning

Master Planning

​

Air conditioning within the District came up in discussion at the December 15, 2021 BOE Meeting. Some air conditioning work has already been included within the suggested infrastructure work for a Spring 2022 Bond; other work could be considered.

DRAFT

01-26-22

3 of 77

Potential Air Conditioning Projects

​

Bedford Hills Elementary $ 189,230

Mount Kisco Elementary $ 533,400

Fox Lane Middle School $ 450,000

Fox Lane High School $ 6,327,800

​

Note: There is air conditioning work included within $24.9M Infrastructure Work Reviewed 12-15-21 Total for Pound Ridge and

West Patent, not included within $7.5M listed on this slide.

​

​

​

Subtotal of Reviewed Work Scope

​

( DRAFT: not yet proposed )

$ 7,500,430

DRAFT

01-26-22

4 of 77

Potential Spring 2022 Bond Reviewed Projects

​

District-Wide Infrastructure Projects $ 24,893,777 12-15-21

MS New Stairs & Connecting Corridors $ 11,022,200 12-15-21

MS Courtyard & Outdoor Gym Improvements $ 2,610,200 12-15-21

MS Central Building Improvements $ 8,270,500 12-15-21

MS Houses Reconstruction $ 7,474,600 12-15-21

MS Wellness, Fitness, Library & Dining $ 4,683,125 12-15-21

HS Library, Cafeteria, Guidance & Art Offices $ 16,760,000 12-15-21

HS STEM, Gallery & Fitness/ Wellness $ 8,940,000 12-15-21

Fox Lane Campus Athletics $ 15,003,205 12-15-21

​

Air Conditioning $ 7,500,430 Extended Master Plan Review

Additionally Reviewed non-Priority 1 BCS Items $ Future + + + Extended Master Plan Review

Other Potential Projects to Review $ Future + + + Extended Master Plan Review

$ 70,000,000

Bond Counsel for the District has advised that the development of a Spring 2022 Bond Referendum up to approximately $70M would not impact the tax levy.

$ 107,158,037

$ 99,657,607

Additional discussion at the 12-15-21 Board of Education Meeting brought back air conditioning as a thought for consideration;

Master Planning work scope will continue to evolve and develop into the future.

DRAFT

01-26-22

5 of 77

Part 2 Potential Spring 2022 Bond Timeline

Part 3 BCS & Infrastructure Projects

Part 4 Learning Environments

Part 5b Fox Lane High School

Part 6 Elementary Schools

Part 8 Potential Spring 2022 Bond Referendum

Part 1 Master Plan: Vision & Facilities

Part 7 Master Planning & Next Steps

DRAFT

01-26-22

6 of 77

Bedford Central School District January 26, 2022

Fox Lane High School

DRAFT

01-26-22

7 of 77

Classroom Sections

Support Classrooms

Administration, Nurse, Faculty

Core & Special Dedicated Spaces

3rd Floor

1st Floor

2nd Floor

DRAFT

01-26-22

8 of 77

Inspiration

Imagery

HS Learning Environments

DRAFT

01-26-22

9 of 77

Traditional School Design

“Double-Loaded” Corridor

Conceptual Diagram of a more Traditional Approach

to (K-12) Educational Design (“Boxes” of Spaces)

DRAFT

01-26-22

10 of 77

‘Decompartmentalization’

of the Student Experience

Conceptual Diagram of a New Approach

to (K-12) Educational Design (“Exchange” of Spaces)

DRAFT

01-26-22

11 of 77

Learning Environment Design

DRAFT

01-26-22

12 of 77

Learning Environment Design

DRAFT

01-26-22

13 of 77

Learning Environment Design – Completed Suffolk County HS Project

DRAFT

01-26-22

14 of 77

Learning Environment Design – Completed Nassau County HS Project

DRAFT

01-26-22

15 of 77

Learning Environment Design – Current Westchester County HS Project

DRAFT

01-26-22

16 of 77

Learning Environment Design – Current Westchester County HS Project

DRAFT

01-26-22

17 of 77

Learning Environment Design – Current Westchester County HS Project

DRAFT

01-26-22

18 of 77

Learning Environment Design – Current Westchester County HS Project

DRAFT

01-26-22

19 of 77

Conceptual Plans:

Fox Lane High School

HS Learning Environments

DRAFT

01-26-22

20 of 77

DRAFT

01-26-22

21 of 77

DRAFT

01-26-22

22 of 77

DRAFT

01-26-22

23 of 77

Science

Academics

Academics

Arts

Arts

STEAM

P.E.

Student

Learning

Exchange

Wellness

DRAFT

01-26-22

24 of 77

$25.7M

  • Student Learning Exchange at Current Library, Dining, Guidance, Art Offices, Gallery & Connecting Corridors
  • New Addition for SLE & Guidance
  • Site Work, Gardens & Misc.
  • Renovate Small Gym to Wellness & Fitness
  • Renovate Locker Rooms, Trainer & Storage
  • New STEAM & Gallery @ Courtyard

Fox Lane HS

Interior Reconstruction

Color Key:

New Construction

First Floor Plan Diagram

DRAFT

01-26-22

25 of 77

CURRENT PROGRAM AREAS

​

Library 9,884 SF

Large Cafeteria 3,619 SF

Small Cafeteria 2,381 SF

Guidance & Faculty Office 3,944 SF

Gallery 539 SF

Student Commons 6,023 SF

Small Gym 3,813 SF

30,203 SF

DRAFT

01-26-22

26 of 77

CURRENT PROGRAM AREAS

Library 9,884 SF

Library Mezzanine 929 SF

Large Cafeteria 3,619 SF

Small Cafeteria 2,381 SF

Guidance & Faculty Office 3,944 SF

Gallery 539 SF

Student Commons 6,023 SF

Small Gym 3,813 SF

OVERALL 31,159 SF

​

POTENTIAL PROGRAM AREAS

Library/ Learning Exchange 8,189 SF

Ellipse/ Exchange 626 SF

Conference Room/ Exchange 454 SF

Dining/ Learning Exchange 3,980 SF

Dining/ Learning Exchange 2,799 SF

Guidance & Faculty/ Exchange 5,113 SF

Gallery/ Exchange 837 SF

Student Commons/ Exchange 12,977 SF

Wellness/ Fitness/ Exchange 3,576 SF

Engineering/ STEAM/ Exchange 1,601 SF

OVERALL 40,152 SF

DRAFT

01-26-22

27 of 77

Conceptual Renderings:

Fox Lane High School

HS Learning Environments

DRAFT

01-26-22

28 of 77

Current Photo of Library @ Upper Windows & Mezzanine

DRAFT

01-26-22

29 of 77

Current Rendered View of Library @ Upper Windows & Mezzanine

DRAFT

01-26-22

30 of 77

Potential Rendered View of Library @ Upper Windows - No Mezzanine

DRAFT

01-26-22

31 of 77

Current Photo of Library @ Lower Windows

DRAFT

01-26-22

32 of 77

Current Rendered View of Library @ Lower Windows

DRAFT

01-26-22

33 of 77

Potential Rendered View of Library @ Lower Windows

DRAFT

01-26-22

34 of 77

Current Photo of Library @ Mezzanine

DRAFT

01-26-22

35 of 77

Current Rendered View of Library @ Mezzanine

DRAFT

01-26-22

36 of 77

Potential Rendered View of Library without Mezzanine

DRAFT

01-26-22

37 of 77

Current Photo of Library underneath Mezzanine

DRAFT

01-26-22

38 of 77

Current Rendered View of Library underneath Mezzanine

DRAFT

01-26-22

39 of 77

Potential Rendered View of Library without Mezzanine

DRAFT

01-26-22

40 of 77

Current Photo of Library between Mezzanine & Guidance

DRAFT

01-26-22

41 of 77

Current Rendered View of Library between Mezzanine & Guidance

DRAFT

01-26-22

42 of 77

Potential Rendered View of Library & Guidance (no Mezzanine)

DRAFT

01-26-22

43 of 77

Current Photo in Library under Mezzanine Stair

DRAFT

01-26-22

44 of 77

Current Rendered View in Library under Mezzanine Stair

DRAFT

01-26-22

45 of 77

Potential Rendered View in Library without Mezzanine

DRAFT

01-26-22

46 of 77

Current Photo of Entry into Small Cafeteria

DRAFT

01-26-22

47 of 77

Current Rendered View of Entry into Small Cafeteria

DRAFT

01-26-22

48 of 77

Potential Rendered View of Entry into Student Dining/ Exchange

DRAFT

01-26-22

49 of 77

Current Photo of Entry into Large Cafeteria

DRAFT

01-26-22

50 of 77

Current Rendered View of Entry to Large Cafeteria

DRAFT

01-26-22

51 of 77

Potential Rendered View of Entry into Student Dining/ Exchange

DRAFT

01-26-22

52 of 77

Conceptual Renderings:

Fox Lane High School

HS Learning Environments

DRAFT

01-26-22

53 of 77

Current

Potential

DRAFT

01-26-22

54 of 77

Cafeterias to the Right

Current Main Corridor

Library to the Left

Commons Beyond

DRAFT

01-26-22

55 of 77

Potential Occupied Main Corridor

Library & Exchange to the Left

Commons Beyond

Dining & Exchange to the Right

DRAFT

01-26-22

56 of 77

Potential Occupied Main Corridor

Library & Exchange to the Left

CURRENT HALLWAY LOCATION

This area currently

in the “back” of the library

Dining & Exchange to the Right

Commons Beyond

DRAFT

01-26-22

57 of 77

Current view of first floor.

Kitchen

Auditorium

Guidance

Small Gym

Library

Large Cafeteria

Small Cafeteria

Courtyard

Gallery

DRAFT

01-26-22

58 of 77

Proposed view of Student Learning Exchange (SLE) at first floor.

Kitchen

Auditorium

SLE

DRAFT

01-26-22

59 of 77

Current view of first floor.

Large Cafeteria

Kitchen

Commons

Small Gym

Small Cafeteria

Auditorium

Courtyard

Gallery

Library

Guidance

DRAFT

01-26-22

60 of 77

Kitchen

Auditorium

Proposed view of Student Learning Exchange (SLE) at first floor.

Fitness/

Wellness

SLE

STEAM

Commons

Gallery

DRAFT

01-26-22

61 of 77

Potential

DRAFT

01-26-22

62 of 77

Potential

DRAFT

01-26-22

63 of 77

Potential

DRAFT

01-26-22

64 of 77

Potential

DRAFT

01-26-22

65 of 77

Potential

DRAFT

01-26-22

66 of 77

Potential

DRAFT

01-26-22

67 of 77

Potential

DRAFT

01-26-22

68 of 77

Potential from Main Entry; Library to left; Dining to right

DRAFT

01-26-22

69 of 77

Potential View of Library Entrance to right; Dining to left

DRAFT

01-26-22

70 of 77

Potential View within Library looking towards Dining

DRAFT

01-26-22

71 of 77

Potential View in Main Hallway; Guidance to left; Dining to right

DRAFT

01-26-22

72 of 77

Potential View of New Gallery straight ahead

DRAFT

01-26-22

73 of 77

Potential View of Widened Access to Student Commons to left

DRAFT

01-26-22

74 of 77

Potential View of Wellness/Fitness to left; STEAM to right

DRAFT

01-26-22

75 of 77

Conceptual Video:

Current & Potential

Fox Lane High School

HS Learning Environments

DRAFT

01-26-22

76 of 77

Cost Components by Area

A Library, Cafeterias, Guidance, Art Offices & Connectors (Interior Reconstruction)

$ 14,200,000

B New Guidance/ Offices (New Construction)

$ 2,560,000

C Site Work, Gardens & Misc.

$ 500,000

D Renovate Small Gym to Wellness & Fitness (Interior Reconstruction)

$ 1,140,000

E Renovate Locker Rooms,Trainer & Adjacent Storage (Interior Reconstruction)

$ 4,800,000

F New STEAM Classroom & Gallery @ Courtyard (New Construction)

$ 2,500,000

Overall

$ 25,700,000

B

D

A

F

C

E

C

E

F

DRAFT

01-26-22

77 of 77

Bedford Hills ES – Bedford Village ES – Mount Kisco ES – Pound Ridge ES – West Patent ES – Fox Lane MS – Fox Lane HS

BEDFORD CENTRAL SCHOOL DISTRICT

“Inspiring and Challenging Our Students”

Potential Spring 2022 Bond Referendum & Master Plan Update

January 26, 2022

DRAFT

01-26-22