1 of 15

SAP Plant Maintenance

PLM322

Capacity Planning and Scheduling

in Maintenance Projects

Unit 07 Reaction to Changes

Exercise 11

Identifying and Attaching Emergent Work

Additional unplanned work neds to be carried out in order to complete the project. Create a new work order for additional labor required for the project. Assign the emergent PM order to the turnaround project. Create relationships between the PM order operations.

2 of 15

1 goto IW24

Create Malfunction repot using M2 with short text above for FL ##-KGV-1

2 Create Order

3 of 15

Use Order type PM01

4 of 15

We plan 3 operations above

5 of 15

Assign WBS

K.900##.01.01

6 of 15

YES and SAVE order

7 of 15

If encounter error message regarding budget situation when saving order, see the cost log here

Extend supplement budget using CJ36

8 of 15

Supplement additional budget to K.900##.01.01

9 of 15

Now there should be enough budget for this work

10 of 15

In MEB, 1 select Notification

2 Enter

FL ##-KGV*

click EXECUTE

11 of 15

Next, Select the Revision (filter by user ID)

12 of 15

Drop the Notification to the Revision

13 of 15

Choose to highlight Revision, then click the ICON to assign to the Maintenance Order manually to the Project

14 of 15

Assign the new Order to Network activity 20

15 of 15

New Additional Order assigned.

SAVE