SAP Plant Maintenance
PLM322
Capacity Planning and Scheduling
in Maintenance Projects
Unit 07 Reaction to Changes
Exercise 11
Identifying and Attaching Emergent Work
Additional unplanned work neds to be carried out in order to complete the project. Create a new work order for additional labor required for the project. Assign the emergent PM order to the turnaround project. Create relationships between the PM order operations.
1 goto IW24
Create Malfunction repot using M2 with short text above for FL ##-KGV-1
2 Create Order
Use Order type PM01
We plan 3 operations above
Assign WBS
K.900##.01.01
YES and SAVE order
If encounter error message regarding budget situation when saving order, see the cost log here
Extend supplement budget using CJ36
Supplement additional budget to K.900##.01.01
Now there should be enough budget for this work
In MEB, 1 select Notification
2 Enter
FL ##-KGV*
click EXECUTE
Next, Select the Revision (filter by user ID)
Drop the Notification to the Revision
Choose to highlight Revision, then click the ICON to assign to the Maintenance Order manually to the Project
Assign the new Order to Network activity 20
New Additional Order assigned.
SAVE