Middle School Modulars Project

2 of 10

Next Steps for Modular Middle School Project

​

​

Design/Permitting

December 2023

Groundbreaking and Renewal Celebration

April 2024 Design and permitting process begins

November 2024

    • Site grading design completed
    • Project permit filed
    • Building permit filed

January/February 2025

    • Site permits pending review
    • BGE electrical power load letter filed

Construction

March/April 2025

    • Soil and erosion control work
    • Modular unit fabrication begins

April/May 2025 Modular Unit Fabrication

June 2025

    • June 1 – Modular Unit delivery
    • June 1 through June 14 – Modular unit setting

June/July 2025

    • Internal fit out
    • Electrical tie-in
    • Water and sewer tie-in

Project Completion

July 31, 2025

Substantial Completion

August 1 – August 2025

Furniture, fixtures and equipment move-in

3 of 10

Middle School Modular Rendering

4 of 10

Middle School Floor Plan and Proposed Classroom Assignments*

Electrical Room

Administrative/Secretary

Administrative

Watershed Staff

Social Work/Psychologist (Itinerant)

5/6/7 Math

5/6/7 Social Studies

5/6/7 Science

5/6/7 ELA

6/7/8 Math

6/7/8 ELA

6/7/8 Science

6/7/8 Social Studies

Resource

5 of 10

Main Building Floor Plan and Proposed Classroom Assignments*

Electrical Room

Administrative/Secretary

Administrative

Watershed Staff

Social Work/Psychologist (Itinerant)

5th Grade

5th Grade

5thGrade

6th Grade

6th Grade

8th Grade

7th Grade

7th Grade

Resource

Art

2nd Grade

Kindergarten

1st Grade

Kindergarten

1st Grade

6 of 10

Main Building Floor Plan and Proposed Classroom Assignments*

Electrical Room

Administrative/Secretary

Administrative

Watershed Staff

Social Work/Psychologist (Itinerant)

5th Grade

5th Grade

5thGrade

6th Grade

6th Grade

8th Grade

7th Grade

7th Grade

Resource

Art

2nd Grade

2nd Grade

1st Grade

2nd Grade

1st Grade

4th Grade

4th Grade

3rd Grade

3rd Grade

Music

Special Areas/Language/

Library

Innovation

Special Education

Faculty Room

7 of 10

Plan B for Modular Middle School Project

  • School Plan if Substantial Completion not met by July 31, 2025:
    • 8th Grade temporarily in Art Room
    • Art pushes into classrooms: “Art on a Cart”
    • Specials (Music and Innovation) remain in Gymnasium classrooms
    • 5th Grade remains in temporary classroom trailers until Middle School building opens
  • Exploring other space options with St. Gabriel Church

​

​

​

​

​

8 of 10

Resources

  • Overall Middle School Modulars

Project

​

​

​

​

​

​

​

Staff Resources

​

​

​

​

9 of 10

Communication Plans

Quarterly meet and greet with Board President and Community Stakeholders

Weekly Facilities updates in Staff news

Bi-weekly updates to Watershed community in Turtle Talk

Daily facilities updates in Daily Coverage e-mail, when work is happening

10 of 10