1 of 5

SAP

S/4HANA Project system

Exercise#5

Project F-920XX

2 of 5

S/4HANA Project F-920XX (Project WBS with Network)

S/4HANA Project F-920XX (Project WBS with Network)

  1. Exercise#5 instructions.
  2. Screenshots.

3 of 5

  • Copy from Template/Standard WBS without Network.
    • Project Definition & Top-level WBS description as "Project I/91XX w/o Network".
    • Use CJ20N.
    • Copy Template/Standard Project "I/1000" to new Project "I/91XX".
    • Delete WBS I/91XX-4 (also Delete the levels below it).
    • Use different methods to Append the following new WBS in the Structure:
      • Append WBS I/91XX-1-4 with description "Setup Quality Assurance Team".
      • Append WBS I/91XX-2-3 with description "Prototype".
      • Append WBS I/91XX-2-4 with description "Finalization of Blue Print".
      • Append WBS I/91XX-3-3 with description "Testing".
      • Append WBS I/91XX-3-4 with description "UAT".
      • Append WBS I/91XX-3-5 with description "Data Conversion".
      • Append WBS I/91XX-3-6 with description "Go-Life".
    • At the Project Definition level, use "Mass Change" to change all WBS the the Structure
      • Applicant no as "000000XX" (Pers. XX).
      • Person Responsible as "000000XX" (Pers. XX).
      • Responsible Cost Center as "1110" with Controlling Area "A000".
      • Required Cost Center as "1110" with Controlling Area "A000".

4 of 5

Homework#5:

Project WBS with Network

Create own Project WBS with Network.

5 of 5

The material is managed in 2 storage locations within the same plant but both location 0120 and 0121 is assigned to different warehouse

This is