�SETTING OUT PROCEDURES
Aim & Objectives
Aim: Setting Out Procedures
Objectives: At the end of the lesson, the students should be able to:
Introduction
Figure 1. Setting-out of a small building.
The Setting Out Process
The Setting Out Process
The Setting Out Process
Essential equipment for a small residential building development typically includes:
Hand Tools:
The Setting Out Process
Step 1: Establish the front corners of the building (W and X) using the primary setting-out points (SOPs) as references.
Figure 1. Setting-out of a small building.
The Setting Out Process
Figure 2. Establishing corners with Pythagoras’ rule.
The Setting Out Process
Figure 3. Establishing corners with Pythagoras’ rule.
The Setting Out Process
Figure 4. Establishing corners with Pythagoras’ rule.
The Setting Out Process
Step 3: Erect the profile boards.
Figure 5. Profile boards (Road To Learning, 2020)
Figure 6. Solid blockwork foundation with an insulated cavity wall.
The Setting Out Process
Step 4: Excavate the foundations
Figure 7. Profile boards for foundation excavation (Pearson, 2017)
The Setting Out Process
Step 5: Setting Levels
Figure 7. Profile boards for foundation excavation (Pearson, 2017)
The Setting Out Process
Step 5: Setting Levels
(Note: Thickness of dampproof membrane [DPM] is negligible.)
Figure 8. Solid blockwork foundation with an insulated cavity wall.
The Setting Out Process
Step 5: Setting Levels
Determine the reduced level of the finished ground level.
HPC = 10.000 + 0.807 = 10.807 m
RL of FGL = HPC – IS
RL of FGL = 10.807 – 0.916 = 9.891 m.
Figure 9. Reduced level of the finished ground floor.
The Setting Out Process
Step 5: Setting Levels
Determine the reduced level of the finished flooring screed (TFS).
RL of TFS = RL of FGL + Hard core depth + Oversite concrete bed depth + Flooring screed depth
RL of TFS = 9.891 + 0.100 + 0.020
RL of TFS = 10.011 m
Figure 8. Solid blockwork foundation with an insulated cavity wall.
Figure 10. Reduced level of the top flooring screed.
The Setting Out Process
Step 5: Setting Levels
Determine the staff readings at the top of the flooring screed.
Staff reading for TFS = 10.807 – 10.011 = 0.796 m
Figure 12. Staff readings for the flooring screed and insitu concrete foundation.
The Setting Out Process
Step 5: Setting Levels
Determine the reduced level of the bottom insitu concrete foundation (BICF).
RL of BICF = RL of FGL – Foundation depth
RL of TFS = 9.891- 0.817
RL of TFS = 9.074 m
Figure 8. Solid blockwork foundation with an insulated cavity wall.
Figure 11. Reduced level of the bottom of the insitu concrete foundation.
The Setting Out Process
Step 5: Setting Levels
Determine the staff readings at the bottom of the insitu concrete foundation.
Staff reading for BICF = 10.807 – 9.074 = 1.733 m
Figure 12. Staff readings for the flooring screed and insitu concrete foundation.
The Setting Out Process
Figure 12. Staff readings for the flooring screed and insitu concrete foundation.
You can use this technique with laser levels that have infrared sensors fitted to the staff. These sensors can be adjusted to the correct position on the staff, so that when the staff is raised or lowered a visual and/or audible signal tells you that you have found the required reduced level. Watch for understanding of this: https://www.youtube.com/watch?v=3sLKKhanh9I
Self-assessment Task 1
The proposed dimensions of the foundation and floor slab of a house on a site are given on the drawing shown (Fig. 13). Given the reduced level of the ground floor (10.050 m), determine:
Figure 13. Setting out levels for a solid blockwork foundation.
Self-assessment Task 2
Equipment and materials/tools | How are they used? |
|
|
|
|
|
|
|
|
|
|
Personal protection equipment | Why are they used? |
|
|
|
|
|
|
|
|
Reference/Bibliography