Protecting and Restoring the Ocean’s natural Capital, building Resilience and supporting region-wide Investments for sustainable Blue socio-Economic development
Agenda Item 11
Proposed way forward for project implementation
(for review & adoption at PBM3)
PROCARIBE+ Mid-Term Meeting of the Project Board ● Bogota, Colombia (Hybrid) ● 2-3 June 2026
Adaptive Project Management
PROCARIBE+ PBM3. 02-03 June, 2026
EVALUATE
PROPOSE ADJUSTMENTS
Enhanced regional coordination and collaboration
1
SUGGESTED WAY FORWARD
☞ sense of realism: PMCU capacity limitations, stakeholder engagement/response times, need to align OCM WP activities with ocean governance processes native to the region
*to accommodate for compacted project timeline
**already advance selected Phase 2 activities during Q2-3
***procurement processes take time
Knowledge Management and Marine Data Infrastructure
4
SUGGESTED WAY FORWARD
☞ sense of realism: PMCU capacity limitations, stakeholder engagement/response times, need to align OCM WP activities with ocean governance processes native to the region
*to accommodate for compacted project timeline
**already advance selected Phase 2 activities during Q2-3
***procurement processes take time
Enhanced national capacity and enabling conditions
Key actions by all sectors of society
2
3
SUGGESTED WAY FORWARD
Component 1:
Regional coordination and collaboration
Component 2:
National capacity and enabling conditions
Component 3:
Key actions by all sectors of society
Component 4:
Knowledge Management and Marine Data Infrastructure
SGP (UNOPS)
PEW
Under Implementation
IOCARIBE
UNEP Cartagena Convention Sec.
Venezuela
IMA
IOCARIBE
MAR Fund
OSPESCA
CRFM
Traceability Brazil
(CEA TBD)
Definition of Work and/or Selection of CEA ongoing
PMCU*/OCM
PMCU
PMCU*/OCM
UNEP Cartagena Convention Sec.
PEW
NCA / National SOMEE in Costa Rica (CEA TBD)
UNOPS Panama & CNAP Cuba
PROCARIBE+ Implementing Arrangements
Pending: Brazil, Costa Rica and Venezuela
10 agreements
9 partners
Costa Rica: National SOMEE with Natural Capital Accounting & Blue Economy Strategy-Plan
Pursue finalization of Co-executing Agreement - likely through competitive process
Adjusting scope of work (new baseline/adjusted priorities): Discussions ongoing with MINAE
Exploring potential to work with Global Ocean Accounts Partnership
Face to Face meetings in Mar 2025 and Apr 2026
MINAE determining next steps based on established roadmap for the development of Ocean Accounts, national ambition to develop a Sustainable Ocean Plan (SOP)
PROCARIBE+ PBM2. 24-25 June, 2025
PROCARIBE+ PBM3. 02-03 June, 2026
Venezuela: MSP in Gulf of Paria
UNDP Country Office in Venezuela selected as Co-Executing Partner (included in ProDoc)
UN2UN agreement signed in Apr 2025
UNDP unable to proceed with execution of activities and discontinued the UN2UN agreement on 25 Mar 2026
PMCU seeking a partner for implementation
Ongoing talks with MINEC on way forward
PROPOSAL TO REDUCE SCOPE OF ACTIVITIES AND BUDGET CONSIDERING LIMITED REMAINING TIMELINE
PROCARIBE+ PBM3. 02-03 June, 2026
Brazil: Fisheries traceability
PROPOSAL TO FORMALLY CANCEL THE TRACEABILITY ACTIVITIES IN BRAZIL
PROCARIBE+ PBM3. 02-03 June, 2026
Agenda Item 11.1.
Proposed adjustments to the Project Results Framework
Protecting and Restoring the Ocean’s natural Capital, building Resilience and supporting region-wide Investments for sustainable Blue socio-Economic development
PROCARIBE+ Mid-Term Meeting of the Project Board ● Bogotá, Colombia (Hybrid) ● 2-3 June 2026
Preliminary Recommendation from MTR: Streamline + simplify Results Framework
PROCARIBE+ PBM3. 02-03 June, 2026
Review of Results Framework under MTR
Preliminary PMCU analysis
PMCU and Mid-term evaluator to review and propose revisions as part of the Management Response to the MTR
PROCARIBE+ PBM3. 02-03 June, 2026
How can we improve the Results Framework?
Targets at risk of not being achieved under current timeline
Activities that are not currently considered
Propose changes to better capture impact of project results (e.g. traceability)
Challenge with Outcome 2.3: Increased mobilization of private capital …
How do we measure Project Beneficiaries?
Agenda Item 11.1.
Revised overall Project (Multi-Year) Work Plan and Budget
Agenda Item 11.3
Key milestones for 2026
Protecting and Restoring the Ocean’s natural Capital, building Resilience and supporting region-wide Investments for sustainable Blue socio-Economic development
PROCARIBE+ Mid-Term Meeting of the Project Board ● Bogota, Colombia (Hybrid) ● 2-3 June 2026
PROJECT TIMELINE AND KEY DATES
2 yrs left in project
Most CEA end Dec 2027
3 yrs elapsed since start of project
Project Year 1 | Project Year 2 | Project Year 3 | Project Year 4 | Project Year 5 | |||||||||||||||
2023 | 2024 | 2025 | 2026 | 2027 | 28 | ||||||||||||||
| | | | | 2 CEA signed | 2 CEA signed | 5 CEA signed | 1 CEA signed | | | | PBM3 MTR | PIR | | | PBM4 | PIR | | Final PBM TE |
Q1 2026
Q1 2026
Inception Phase
Advance according to revised 2026 Work Plan and evaluate progress made by Q4 2026
If sufficient progress is made by YE under CEA and OCM Work Programme, proceed with “fine-tuned” Plan A (current project timeline)
or
If progress by YE is insufficient / inform Project Board and proceed with “fine-tuned” Plan B (project extension)
PROCARIBE+ PBM3. 02-03 June, 2026
Multi-Year Work Plan
PMCU to send revised Plan A or Plan B to Project Board in Q1 2027 to determine way forward
PROCARIBE+ PBM3. 02-03 June, 2026
MAY 2023
JUNE 2026
APRIL 2028
DEC 2028
May 2023 - May 2026
MYWP & BUDGET
IMPLEMENTED
PLAN A
MYWP & BUDGET
PLAN B
MYWP & BUDGET (EXTENSION)
PBM3
DEC 2026
S2 2026
WP & BUDGET
Year End
Current Project End
Project Start
Multi-Year Work Plan beyond 2026: Plan A and B
Plan A: Current timeline, project ends April 2028
PROCARIBE+ PBM3. 02-03 June, 2026
Plan B: 8-month project extension, project ends YE (Q4) 2028
Balancing “acceptable” implementation gaps with long-term sustainability of flagship outputs
Questions?
www.procaribeplus.org
PROCARIBE+ Mid-Term PBM. 02-03 June, 2026
REVISED 2026 BUDGET
www.procaribeplus.org
| Amount Year 1 (USD) 2023 | Amount Year 2 (USD) 2024 | Amount Year 3 (USD) 2025 | Amount Year 4 (USD) 2026 |
C1 | $87.59K | $251.31K | $461.55K | $661.10K |
C2 | $39.36K | $126.41K | $437.05K | $605.80K |
C3 | $128.41K | $614.03K | $1,82M | $2,94M |
C4 | $54.15K | $190.31K | $169.73K | $624.08K |
C5 MnE | $0.00 | $157.86K | $4.64K | $64.33K |
C6 PMC | $25.56K | $61.03K | $79.52K | $206.42K |
GRAND TOTAL | $335.08K | $1,40M | $2,97M | $5,10M |
Multi-Year Budget, per Project Component, for PBM3 review & approval
MTR
PROCARIBE+ PBM3. 02-03 June, 2026
www.procaribeplus.org
Account Description | Year 1 (USD) 2023 | Year 2 (USD) 2024 | Year 3 (USD) 2025 | Year 4 (USD) 2026 |
Audio Visual&Print Prod Costs | $10.58K | $27.30K | $35.18K | $139.20K |
Contractual Services - Companies | $14.80K | $292.15K | $1,74M | $2,95M |
Contractual Services – Imp Part | $256.00K | $631.71K | $698.51K | $720.72K |
Information Technology Equipmt | $4.55K | $12.99K | $2.06K | $2.85K |
International Consultants | $4.94K | $87.23K | $95.02K | $301.07K |
Local Consultants | $0.00 | $5.66K | $26.59K | $209.84K |
Professional services | $0.00 | $0.00K | $0.00 | $0.00 |
Rental & Maint of Info Tech Eq | $1.42K | $4.30K | $0.56K | $5.27K |
Supplies | $3.39K | $14.51K | $10.06K | $14.13K |
Training. Workshops and Confer | $1.36K | $168.24K | $98.23K | $245.50K |
Travel | $38.03K | $156.87K | $268.30K | $513.59K |
Grand Total | $335.08K | $1,40M | $2,98M | $5,10M |
Multi-Year Budget. per UNDP Accounts Code/Expenditure Type
PROCARIBE+ PBM3. 02-03 June, 2026
(PMCU & OCM Sec.)
(Includes all CEA)
2026 Budget: allocations across a PMCU key budget planning classes
PMCU's adaptive budget grouping for day-to-day management
PROCARIBE+ PBM3. 02-03 June, 2026
*All values are shown in thousands of dollars (USD)
PROCARIBE+ PBM3. 02-03 June, 2026
*All values are shown in thousands of dollars (USD)
$630K
Difference between UNDP 2025 Maximum Spending Limit
and
UNOPS 2025 minimum implementation target
PROCARIBE+ PBM3. 02-03 June, 2026
Year | Minimum UNOPS | PBM3 UNDP |
2023 | $335 | $335 |
2024 | $1,401 | $1,401 |
2025 | $3,152 | $3,152 |
2026 | $4,467 | $5,099 |
www.procaribeplus.org
REVISED MULTI-YEAR WORK PLAN
2026 Work Plan
Plan A (No Project Extension)
Plan B (8-Month Project Extension)
PROCARIBE+ Mid-Term PBM. 02-03 June, 2026
2026 Work Plan: Component 1
PLAN A
MYWP
(No Project Extension)
PLAN B
MYWP
(8-mth Project Extension)
Plan A or Plan B to be fine-tuned based on results of progress review
MILESTONES
Operations of OCM
Second Meetings of EG/SG
Approach for SOMEE/SAP adopted
MDI Blueprint adopted
Preparation for OCM sustainability solution
2026 Work Plan: Components 1 and 4 (OCM outputs)
PLAN A
MYWP
(No Project Extension)
PLAN B
MYWP
(8-mth Project Extension)
Plan A or Plan B to be fine-tuned based on results of progress review
MILESTONES
Proposal on way forward with Partnership
2nd Reg. Partnership Forum (tentative)
Engagement of “Partnership” in SOMEE/SAP development
Work on OCM Hub
Development of SOMEE content
Plan A and Plan B: Component 1
PLAN A: No Project Extension
PLAN B: 8-month Extension
Plan A and Plan B: Component 1 & 4 (OCM Outputs)
PLAN A: No Project Extension
PLAN B: 8-month Extension
2026 Work Plan: Components 2 and 3
PLAN A
MYWP
(No Project Extension)
PLAN B
MYWP
(8-mth Project Extension)
Plan A or Plan B to be fine-tuned based on results of progress review
MILESTONES
Advocacy for NICs/Link to OCM/Status update on NICs
Start of activities on Ocean Accounts, indicators and national SOMEE in Costa Rica
Finalization of SGP engagement
Start of BE/SOP work in Costa Rica and MSP in Venezuela
Continuation of work by co-executing partners on: “Blue” NDCs, seagrasses, MPA, MSP, PSSA, Traceability and ADLG Fishing
2026 Work Plan: Component 4 and M&E
PLAN A
MYWP
(No Project Extension)
PLAN B
MYWP
(8-mth Project Extension)
Plan A or Plan B to be fine-tuned based on results of progress review
MILESTONES
Participation in GEF IW Conferences (Paris + Bali)
2nd leg of Twinning Exchange with African SIDS Project (TBD) + South China Sea/Gulf of Mexico Twinning (on the margins of IWC-11 (TBD))
Finalization of MTR w Mngt. Responses
PIR 2026
Ongoing M&E processes
PEG Meeting
PLAN A: No Project Extension
PLAN B: 8-month Extension
Plan A and Plan B: Components 2 & 3
Plan A and Plan B: Component 4 and M&E
PLAN A: No Project Extension
PLAN B: 8-month Extension
Questions?
www.procaribeplus.org
PROCARIBE+ Mid-Term PBM. 02-03 June, 2026
REVISED MULTI-YEAR BUDGET
Plan A: No Project Extension
www.procaribeplus.org
| Amount Year 5 (USD) 2027 | Amount Year 6 (USD) 2028 | Total (USD) |
C1 | $885.2K | $314.1K | $2,60M |
C2 | $372.7K | $138.6K | $1,72M |
C3 | $1,78M | $203.7K | $7,92M |
C4 | $966.2K | $154.6K | $2,16M |
C5 MnE | $13.7K | $47.5K | $288.0K |
C6 PMC | $81.8K | $216.3K | $728.6K |
GRAND TOTAL | $4,10M | $1,3M | $15,43M |
Multi-Year Budget, per Project Component, for PBM3 review & approval
PROCARIBE+ PBM3. 02-03 June, 2026
$1,338
www.procaribeplus.org
Budget adjustments (revisions) since ProDoc (approved/for approval)
PROCARIBE+ PBM3. 02-03 June, 2026
| PRODOC | PBM1 | PBM2 | PBM3 (To Approved) |
C1 | $2.08M | $2.25M | $2.72M | $2.60M |
C2 | $2.00M | $1.65M | $1.53M | $1.72M |
C3 | $8.73M | $8.19M | $8.10M | $7.92M |
C4 | $1.58M | $1.90M | $2.03M | $2.16M |
C5 MnE | $0.31M | $0.31M | $0.31M | $0.29M |
C6 PMC | $0.73M | $0.73M | $0.73M | $0.73M |
TOTAL | $15.43M | $15.43M | $15.43M | $15.43M |
Log Scale
www.procaribeplus.org
Account Description | Year 5 (USD) 2027 | Year 6 (USD) 2028 | Total (USD) |
Audio Visual&Print Prod Costs | 180.9K | 75.4K | 465.4K |
Contractual Services - Companies | 2,00M | 128.2K | 7,58M |
Contractual Services – Imp Part | 748.0K | 253.5K | 3,31M |
Information Technology Equipmt | 3.8K | 3.0K | 29.2K |
KInternational Consultants | 551.3K | 94.4K | 1,13M |
Local Consultants | 76.7K | 43.1K | 371.4K |
Professional services | 0.0 | 0.0 | 15.8K |
Rental & Maint of Info Tech Eq | 5.3K | 5.3K | 22.1K |
Supplies | 14.2K | 14.2K | 70.6K |
Training. Workshops and Confer | 135.0K | 163.5K | 833.9K |
Travel | 387.0K | 294.3K | 1,61M |
Grand Total | 4,10M | 1,3M | 15,43M |
Multi-Year Budget. per UNDP Accounts Code/Expenditure Type
PROCARIBE+ PBM3. 02-03 June, 2026
(PMCU & OCM Sec.)
(Includes all CEA)
1,338
www.procaribeplus.org
Adjustments of Budget allocations per UNDP accounts code (expenditure type)
PROCARIBE+ PBM3. 02-03 June, 2026
Log Scale
| PRODOC | PBM1 | PBM2 | PBM3 |
Audio Visual&Print Prod Costs | 223,56K | 368,61 | 590,71K | $465,36K |
Contractual Services - Companies | 9,22M | 7,79M | 7,78M | $7,56M |
Contractual Services – Imp Part | 2,23M | 3,39M | 3,30M | $3,30M |
Information Technology Equipmt | 21,06K | 22,426K | 29,33M | $29,20K |
International Consultants | 1,27M | 1,15M | 1,36M | $1,13M |
Local Consultants | 192,78K | 322,80K | 82,67K | $371,40K |
Professional services | 21,60K | 31,63K | 16,87K | $15,9K |
Rental & Maint of Info Tech Eq | 140,94K | 28,26K | 22,78K | $22,10K |
Supplies | 82,08K | 63,31K | 85,46K | $70,56K |
Training, Workshops and Confer | 649,36K | 769,79K | 694,47K | $833,93K |
Travel | 1,37M | 1,48M | 1,46M | $1,61M |
TOTAL | 15,43M | 15,43M | 15,43M9 | $15,43M |
*All values are shown in thousands of dollars (USD)
PROCARIBE+ PBM3. 02-03 June, 2026
www.procaribeplus.org
PROCARIBE+ Mid-Term PBM. 02-03 June, 2026
REVISED MULTI-YEAR BUDGET
Plan B: Project Extension
www.procaribeplus.org
| Amount Year 5 (USD) 2027 | Amount Year 6 (USD) 2028 | Total (USD) |
C1 | $839.59K | $363.48K | $2,66M |
C2 | $364.09K | $184.64K | $1,76M |
C3 | $1,75M | $489.37K | $7,74M |
C4 | $980.22K | $236.40K | $2,25M |
C5 MnE | $13.71K | $61.21K | $301.76K |
C6 PMC | $81.79K | $253.13K | $707.44K |
GRAND TOTAL | $4,03M | $1,59M | $15,43M |
Multi-Year Budget, per Project Component, for PBM3 review & approval
PROCARIBE+ PBM3. 02-03 June, 2026
www.procaribeplus.org
Budget adjustments (revisions) since ProDoc (approved/for approval)
PROCARIBE+ PBM3. 02-03 June, 2026
| PRODOC | PBM1 | PBM2 | PBM3 (To Approve) |
C1 | $2.08M | $2.25M | $2.72M | $2.66M |
C2 | $2.00M | $1.65M | $1.53M | $1.76M |
C3 | $8.73M | $8.19M | $8.10M | $7.74M |
C4 | $1.58M | $1.90M | $2.03M | $2.25M |
C5 MnE | $0.31M | $0.31M | $0.31M | $0.30M |
C6 PMC | $0.73M | $0.73M | $0.73M | $0.71M |
TOTAL | $15.43M | $15.03M | $15.43M | $15.43M |
Log Scale
www.procaribeplus.org
Account Description | Year 5 (USD) 2027 | Year 6 (USD) 2028 | Total (USD) |
Audio Visual&Print Prod Costs | $163.46K | $66.44K | $442.17K |
Contractual Services - Companies | $2,00M | $240.81K | $7,248M |
Contractual Services – Imp Part | $748.05K | $766.45K | $3,82M |
Information Technology Equipmt | $3.80K | $2.95K | $29.20K |
International Consultants | $564.74K | $96.50K | $1,15M |
Local Consultants | $76.74K | $78.62K | $397.45K |
Professional services | $0.00K | $0.00K | $0.00 |
Rental & Maint of Info Tech Eq | $5.27K | $5.27K | $22.10K |
Supplies | $14.24K | $14.24K | $70.56K |
Training. Workshops and Confer | $111.79K | $107.57K | $732.70K |
Travel | $340.11K | $209.38K | $1,53M |
Grand Total | $4,03M | $1,58M | $15,43M |
Multi-Year Budget. per UNDP Accounts Code/Expenditure Type
PROCARIBE+ PBM3. 02-03 June, 2026
(PMCU & OCM Sec.)
(Includes all CEA)
www.procaribeplus.org
Adjustments of Budget allocations per UNDP accounts code (expenditure type)
PROCARIBE+ PBM3. 02-03 June, 2026
Log Scale
| PRODOC | PBM1 | PBM2 | PBM3 |
Audio Visual&Print Prod Costs | 223,56K | 368,61 | 590,71K | $442.17K |
Contractual Services - Companies | 9,22M | 7,79M | 7,78M | $7,24M |
Contractual Services – Imp Part | 2,23M | 3,39M | 3,30M | $3,8M |
Information Technology Equipmt | 21,06K | 22,426K | 29,33M | $29.20K |
International Consultants | 1,27M | 1,15M | 1,36M | $1,15M |
Local Consultants | 192,78K | 322,80K | 82,67K | $397.45K |
Professional services | 21,60K | 31,63K | 16,87K | $0.00 |
Rental & Maint of Info Tech Eq | 140,94K | 28,26K | 22,78K | $22.10K |
Supplies | 82,08K | 63,31K | 85,46K | $70.56K |
Training, Workshops and Confer | 649,36K | 769,79K | 694,47K | $732.70K |
Travel | 1,37M | 1,48M | 1,46M | $1,53M |
TOTAL | 15,43M | 15,43M | 15,43M | $15,43M |
*All values are shown in thousands of dollars (USD)
PROCARIBE+ PBM3. 02-03 June, 2026
Questions?
www.procaribeplus.org
Proposed Decisions
9. Having evaluated the revised 2026 Work Plan and Budget, and 2 potential/proposed ways forward for project implementation beyond 2026 as described in documents 2606 02-03 ENG - PROCARIBE+ PBM3 Item 11 - Proposed way forward for project implementation (review & adoption) (Presentation) 2606 02-03 ENG - PROCARIBE+ PBM3 Item 11 - MYWP (Plan A) (PDF) and 2606 02-03 ENG - PROCARIBE+ PBM3 Item 11 - MYWP (Plan B) (PDF), each presenting one possible project implementation scenario/option, together with its associated, revised multi-year work plan and budget, and an evaluation of associated risks: Plan A (which maintains the project’s original end date in April 2028) and Plan B (which -tentatively- proposes an extension of the project duration with 8 months, moving the project end date to 31 December 2028),
PROCARIBE+ PBM3. 02-03 June, 2026
10. Takes note of the challenges encountered on the development of the co-executing agreements in Venezuela and Costa Rica, and the limited time remaining to execute the planned activities and funds, and requests the PMCU and the concerned beneficiary countries to:
www.procaribeplus.org
Proposed Decisions
PROCARIBE+ PBM3. 02-03 June, 2026
11. Acknowledging that, as documented in 2606 02-03 ENG - PROCARIBE+ PBM3 Item 8 - Project Implementation Status (technical and financial), the review process of the first iteration of the GEF-supported TDA-SAP process in the CLME+ region is currently ongoing as part of the implementation of Phase 1 of the OCM Work Programme, and that, based on the outcomes of this process, a fine-tuned approach for the PROCARIBE+-supported second iteration of such regional TDA-SAP process will be developed and presented for consideration and endorsement by the OCM Executive Group and Steering Group, and while additionally taking note of and anticipating that the “Integrated State of the Convention Area (SOCAR)” report mandated under the Cartagena Convention will constitute an important “building block” for the holistic “State of the Marine Environment and associated socio-Economics” (SOMEE) report contemplated under the OCM Work Programme, and noting that the total budget currently allocated for SOMEE development is set at approximately 540,000 USD, agrees that the PROCARIBE+ PMCU, in its dual quality as Project Unit and OCM Secretariat, can (a) determine in consultation with the OCM organs the precise amount of the funds available under the PROCARIBE+ Project Budget for SOMEE development that are to be allocated to the development of the integrated SOCAR report, with the understanding that the co-executing agreement to develop the SOCAR report will constitute a portion of the total SOMEE budget, and that (b) UNOPS and UNEP are authorized by the PROCARIBE+ Project Board to subsequently enter into a UN2UN agreement for such purpose and for such amount, without this matter having to be brought back to the PROCARIBE+ Project Board for decision-making.
www.procaribeplus.org
Proposed Decisions
PROCARIBE+ PBM3. 02-03 June, 2026
12. Authorizes UNOPS to conduct the selection of co-executing partners and to conclude and enter into the corresponding co-executing agreements (which could consist of Grants, Project Cooperation Agreements or UN to UN agreements), in line with its regulatory framework, and following UNDP’s non-objection (if applicable), for the PROCARIBE+-financed activities in Costa Rica and Venezuela.
13. Requests UNOPS, the PMCU, relevant PROCARIBE+ Participating countries and all co-executing partners to expeditiously advance the development of the remaining co-executing agreements.
14. Takes note of the efforts made by the PMCU and UNDP to engage Brazil in the PROCARIBE+ Project (as presented in document 2606 02-03 ENG - PROCARIBE+ PBM3 Item 11 - Proposed way forward for project implementation (review & adoption)) on the implementation of the fisheries traceability output, and in light of the protracted lack of response and the limited remaining timeframe to execute the planned activities under the original project timeline, agrees to formally cancel the traceability activities originally allocated for Brazil; further requests the PMCU to reallocate the funds to the temporary reserve to help enable a potential activation of Plan B.
15. Takes note of the delays and challenges faced with the setting-up of implementation arrangements for project activities in the Dominican Republic under Outputs 3.3.1 and 3.3.2, and agrees with the proposal by the PMCU, IOCARIBE and the Dominican Republic to reduce the scope of activities under the existing co-executing agreement with IOCARIBE to the completion of one marine spatial plan, with an associated reduction of the PROCARIBE+ GEF grant allocated under the co-executing agreement, to be determined between the PMCU, IOCARIBE and the Dominican Republic.
www.procaribeplus.org
Proposed Decisions
PROCARIBE+ PBM3. 02-03 June, 2026
QUESTIONS/COMMENTS