SAP Plant Maintenance Processes
in S/4 HANA 1909
using FIORI APP
Maintenance Plan
for Time Based Strategy
IP42 shows 2 Maint.Plan Category
IP42’s
QM InspLot & Stab Study are for QM module (not available in the PM FIORI for MPans)
Select this where the Call Object is MO
Create a Strategy Plan
Select the Strategy for Maintenance Plan at the initial screen
This is the
Maintenance Item
Enter Equipment and press Enter
Default from the Equipment Master
Enter Maint.Item
Description
Enter Order Type if IMG default not set for the Planning Plant
Scroll down to enter the Task List
First, select the Task List Type
You must enter a Task List with the same Strategy of this Maint.Plan entered earlier (see Slide 7)
If the Task List entered contain the same Strategy as the Maint.Plan entered earlier (see Slide 7), system come to this screen else its ERROR and remain in previous screen
Goto
Planning Data
TAB
Enter Scheduling Period
SAVE
Maintenance Plan 61 created