Executive Staff Meeting
September 16, 2013
OPEN SOURCE
OPEN SOURCE
Shuttleworth Expectations
OPEN SOURCE
OPEN SOURCE
3rd Quarter Priorities (July - September)
OPEN SOURCE
OPEN SOURCE
Current Week Priorities
Week Priorities | Previous Week | Current Week | Issues/Risk | Quarterly Goal |
Project Manager Scheduling | Review during Ex. Staff Meeting | | | Schedule projects in PM through 4th Quarter |
LifeTrac 6 | Correct 3 design issues and verify equipment status | | Source tires, shafts, and pick up parts from MoKan | Build LifeTrac 6 while beta testing process |
Design Sprint | DS on Saturday | | | |
OPEN SOURCE
OPEN SOURCE
Current Week Priorities
Week Priorities | Previous Week | Current Week | Issues/Risk | Quarterly Goal |
Microhouse | None | Chris for producing BOM (September 19) | Pitch to Shuttleworth | Sept 28: Complete |
DPV and Design Sprint Recruiting | 1. Plan / advertise / schedule University tour, 2. Volunteer primary position descriptions | | | Sept 30: 3 DPVs |
OSE Structuring | Colby received quotes and recommended open discussions with Maxwell Health | Maxwell Health | Redirection after time spent researching. Slowing process. | Make decision by Sept 5 |
CAB Step by Step | Working | | | |
OPEN SOURCE
OPEN SOURCE
Resources and Personnel
Schedule and Routing Review
OPEN SOURCE
OPEN SOURCE
Other Tasks
Date Added | Tasks | Status |
August 22 | Development Process - Product Development Board’s Step Instructions and Sample Deliverables | Ongoing |
August 16 | ED respond to FAQ#Reporter Questions | |
August 26 | Sweiger Shop - steel pick up | |
August 20 | Mo-kan Fasteners (KC) bolts pick up | Urgent - going out of business |
August 30 | DPV Orientation, Message Board and check out | |
August 30 | OSE Ford Ranger repairs | |
Sept 04 | The Feast needs Marcin’s Presentation by Sept 20 | DM is working Prezi as of Sept 03 |
Sept 11 | Cut off Saws (HARBOR FREIGHT) and Bolts (MOKAN) - SOMEONE NEEDS TO GO FRIDAY, bring Debit Cards to activate, MoKan receipt and Grainger return. | |
Reference: Parking Lot, Other Tasks