  1. Introduction to the purpose of T-code “IP11U”.
  2. New Maintenance Strategy “Z” (IP11).
  3. Create Task List “TL2” with Strategy “Z” (IA05).
  4. Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  5. Initial Scheduling (IP10).
  6. Scheduling Overview (IP24).
  7. Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  8. Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  9. Rescheduling of Maintenance Plan (IP11U).
  10. Check the Rescheduling Result (IP10) and (IP24).
  11. Try to goto Change mode of the Maintenance Plan (IP02).
  12. Release the 1st Call to Maintenance Order (IP10).
  13. Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  14. Try Rescheduling Maintenance Plan again (IP11U).
  15. Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  16. Rescheduling of Maintenance Plan (IP11U) and check IP02.
  17. Check if IP11 is still locked and if Order Called are deleted by IP11U.

3 of 83

IP11U is a transaction code used for Rescheduling of Maintenance Plans in SAP.

When changing cycle parameters in IP11, there is an option to create Worklist which then will lock the Maintenance Plan for any changes or processing including IP10 or IP30H. IP11U will be used to perform the Rescheduling.

4 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

5 of 83

Strategy “Z”

note

Call Horizon 1 day

6 of 83

Note,

Package

1M, 3M, 12M

7 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

8 of 83

new Task List “TL2”

with

new Strategy “Z”

9 of 83

3 Operations each for the Packages 1M, 3M, 12M

10 of 83

3 Operations each for the Packages 1M, 3M, 12M

11 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

12 of 83

Create new Maintenance Plan

for the Strategy Z

13 of 83

The new Task List “TL2”

14 of 83

1M, 3M, 12M

from

Strategy “Z”

15 of 83

Call Horizine and Date determination from the Strategy when the MP is first created

16 of 83

17 of 83

new

Maintenance Plan

91 is created

18 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

19 of 83

use IP10 to schedule in (IP30H also possible)

20 of 83

21 of 83

As usual based on the 1M, 3M, 12M Strategy “Z”

Call Horizon

1 Day

22 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

23 of 83

check Scheduling result in

report IP24

24 of 83

as per IP10 results

25 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

26 of 83

change

3M to 6M

27 of 83

change

3M to 6M

28 of 83

try to also change Call Horizon from 1 day to 2 day

BUT

the change in this screen do not seem to change the existing Maint.Plan

29 of 83

for the first change, let’s

set “YES” to setup a worklist

30 of 83

note Message that the Strategy is locked for further changes (due to the “YES” to setup Worklist)

31 of 83

note Message that the Strategy is locked for further changes (due to the “YES” to setup Worklist)

32 of 83

due to the “YES” to setup Worklist when SAVING the changes, the Strategy is now locked from further changes.

33 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

34 of 83

Run IP11 again, and still the SAME (no changes allowed)

35 of 83

Run IP11 again, and still the SAME (no changes allowed)

36 of 83

IP02 also not allowed change to the Maint.Plan

In fact both IP10 and IP30H are also no longer allowed for the Maint.Plan until IP11U Rescheduling is executed for this any Maint.Plan assigned to Strategy “Z”

37 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

38 of 83

only when set “YES” at SAVING changes to IP11 that the Rescheduling via IP11U is allowed!

39 of 83

System generate only Maint.Plan 91 in this worklist as it only found ONE M.Plan assigned with Strategy “Z” that required Rescheduling!

40 of 83

Maint.Plan 91 Rescheduled and removed from the Worklist.

41 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

42 of 83

whether IP10 or IP24 will be showing the same result.

43 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

44 of 83

After IP11U Rescheduling, check if the Maint.Plan is unlocked

45 of 83

Maint.Plan is unlocked and the new cycle

1M, 6M, 12M was updated to the Maint.Plan

46 of 83

Note Call Horizon is NOT changed

Changes in this screen do not update existing Maint.Plan data

47 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

48 of 83

Release Call# 1 to Maint.Order

49 of 83

50 of 83

check the Called Object which is a Maint.Order

51 of 83

Maint.Order called

52 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

53 of 83

We already checked earlier that changing data in this screen will not affect Existing Maint.Plan

54 of 83

But let’s change from

1M, 6M, 12M

to

1M, 2M, 12M

and SAVE

55 of 83

BUT this time, “NO” to setup a worklist when try to SAVE the changes in the Strategy

56 of 83

Data changed to the Strategy and

IP11 is NOT locked

57 of 83

IP02 is allowed (not locked) and note cycle is updated

58 of 83

as expected the Call Horizon is NOT changed

59 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

60 of 83

try to Reschedule the Maint.Plan using IP11U

61 of 83

no Object (no Maint.Plan) found because Worklist

is not generated

62 of 83

For this case of without Worklist, the affected Maint.Plan can be rescheduled via IP10 or IP30H

63 of 83

64 of 83

65 of 83

New Schedule

66 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

67 of 83

Simulate another change to the Strategy from

1M, 2M, 12M

to

2M, 4M, 12M

68 of 83

Simulate another change to the Strategy from

1M, 2M, 12M

to

2M, 4M, 12M

69 of 83

This time “YES” again to create a Worklist

70 of 83

with Set Worklist option as YES, as expected,

the Strategy is locked for further changes until the Maint.Plan affected in the Worklist are Rescheduled via IP11U.

71 of 83

IP02,

change Maint.Plan

not allowed

72 of 83

IP10,

Maint.Plan Scheduling

NOT allowed

73 of 83

IP30H also

NOT allowed

74 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

75 of 83

Only IP11U allowed for Rescheduling to the affected Maint.Plans

76 of 83

77 of 83

affected Maint.Plans in the Worklist to be Rescheduled

78 of 83

Done

79 of 83

after IP11U completed,

Maint.Plan is unlocked for changes in IP02

note the latest

Strategy cycles updated to the Maint.Plan

80 of 83

IP11U Rescheduling results

with the new cycle of

2M, 4M, 12M

81 of 83

  • Introduction to the purpose of T-code “IP11U”.
  • New Maintenance Strategy “Z” (IP11).
  • Create Task List “TL2” with Strategy “Z” (IA05).
  • Create Maintenance Plan for EQ with Task List “TL2” (IP42).
  • Initial Scheduling (IP10).
  • Scheduling Overview (IP24).
  • Change some parameters in Strategy “Z” and “Yes” to Worklist (IP11).
  • Try to change Strategy “Z” (IP11) and Maint.Plan (IP02).
  • Rescheduling of Maintenance Plan (IP11U).
  • Check the Rescheduling Result (IP10) and (IP24).
  • Try to goto Change mode of the Maintenance Plan (IP02).
  • Release the 1st Call to Maintenance Order (IP10).
  • Change the Strategy “Z” again and “No” to Worklist (IP11) and check the Maint.Plan updates (IP02).
  • Try Rescheduling Maintenance Plan again (IP11U).
  • Change some parameters in Strategy “Z” again and “Yes” to Worklist (IP11) then try t-code IP02, IP10 and IP30H.
  • Rescheduling of Maintenance Plan (IP11U) and check IP02.
  • Check if IP11 is still locked and if Order Called are deleted by IP11U.

82 of 83

Since the Worklist is cleared in IP11U for Strategy “Z”, the Strategy is unlocked for changes

83 of 83

IP10 also is not accessible for the Maint.Plan