Critical impact of prolonged budget impasse on NCSSM
Critical impact of prolonged budget impasse on NCSSM
Inability to make planned repairs to campus or adequately address facilities emergencies:
$2 million in R&R funding had been allocated for NCSSM in the 2019-2020 budget
Critical impact of prolonged budget impasse on NCSSM
No employee salary increases:
Must advocate for a minimum of a 4% salary increase for university employees in FY 2021
Scenario 1
NCSSM delays the start date for the first residential cohort at NCSSM-Morganton to August 2022:
Merits of this scenario:
Scenario 1
NCSSM delays the start date for the first residential cohort at NCSSM-Morganton to August 2022:
Challenges created by this scenario:
Scenario 1
NCSSM delays the start date for the first residential cohort at NCSSM-Morganton to August 2022:
Funding Requirements | ||
Amount | Timing | Purpose |
$250,000 | February 2020 | Non-recurring dollars to fund campus planning infrastructure |
$1,408,631 | July 2020 | New recurring dollars to fund critical operations and personnel |
$5,150 | July 2020 | Non-recurring dollars to fund technology needs |
$1,981,188 | July 2021 | New recurring dollars to fund critical operations and personnel |
$792,369 | July 2021 | Non-recurring dollars to fund start-up infrastructure needs |
Scenario 2
NCSSM maintains the start date of August 2021 for the first residential cohort at NCSSM-Morganton:
Merits of this scenario:
Scenario 2
NCSSM maintains the start date of August 2021 for the first residential cohort at NCSSM-Morganton:
Challenges created by this scenario:
Scenario 2
NCSSM maintains the start date of August 2021 for the first residential cohort at NCSSM-Morganton:
Funding Requirements | ||
Amount | Timing | Purpose |
$500,000 | February 2020 | Non-recurring dollars to fund campus planning infrastructure |
$1,408,631 | April 2020 | New recurring dollars to fund critical operations and personnel (with provision for carry forward) |
$1,981,188 | July 2020 | New recurring dollars to fund critical operations and personnel |
$797,519 | July 2020 | Non-recurring dollars to fund start-up infrastructure needs |
$TBA | July 2021 | New recurring dollars to fund critical operations and personnel |
$TBA | July 2021 | Non-recurring dollars to fund start-up infrastructure needs |
Next steps