1 of 9

Mobile Feeding Program

PJM 6025-Project Scheduling and Cost Planning  

  • Group 5-
  • Adhira Sahni
  • Raghav Gupta
  • Vyom Dalal

2 of 9

Project Summary 

The purpose of the Mobile Feeding Program is to feed the underserved residents of Westfield area with freshly prepared nutritious meals, using donated food, 3 times per week, with a projected 1000 people fed monthly. The implementation of the project, i.e., the food delivery services must start on or by the 30th of September 2022. 

  

3 of 9

Baseline Cost Structure

$24,392

                            $26,064

$82,132

$41,744

  $8,288

Total Project Cost = $161,933.00

Contingency Reserve (10% of pre-baseline cost) = $14,721.00

By Resource Type

Work Type = $125,512.00 

(all human resources)

Cost Type = $35,421.00

(vehicles, utensils, space, insurance, contingency)

Material Type = $1,000

(consumables – ingredients, etc.)

Cost Breakdown By Phase

4 of 9

Baseline Schedule Summary

Project start date 

01/01/2022

Initiation phase start​

01/03/2022

Initiation phase complete​

03/08/2022

Planning phase start​

03/08/2022

Planning phase complete​

05/20/2022

Implementation phase start​

05/23/2022

Implementation phase complete​

07/20/2022

Monitor & control phase start​

07/20/2022

Monitor & control phase complete​

09/20/2022

Closing phase start​

08/31/2022

Closing phase complete​

09/15/2022

Project complete date

09/10/2022

5 of 9

Project Performance Data Analysis

Fig: Pie chart representing the status of the project

Schedule Analysis by Schedule Performance Indicator (SPI):

  • SPI = EV/PV

= $ 29,912 / $ 28,440

= 1.05

  • Based on the table above, we can deduce that the project is ahead by 5%.
  • Reason - Majority part of the execution phase like recruitment activities work package was completed well advance in time.

SPI Values

Status of the project

<1

Behind the Schedule

=1

On track with the schedule

>1

Ahead of the schedule

Fig: Table representing values of SPI which helps us to track the status of the project

6 of 9

Project Performance Data Analysis

Fig: Bar Graph representing the budget status of the project

Cost Analysis by Cost Performance Indicator (SPI):

  • CPI = EV/AC

= $ 29,912.10 / $ 28,440

= 1.05

  • Based on the table above, we can deduce that the project is under budget because BAC is higher than EAC, having a variation (VAC) of $7,969.40.
  • Reasons are - good stakeholder management relations, impediment removal well in advance and setting a realistic schedule.

CPI Values

Status of the project

<1

Over Budget

=1

On track with the budget

>1

Under Budget

Fig: Table representing values of SPI which helps us to track the status of the project

7 of 9

Lessons Learned

Related area 

Impact Type 

Lessons Learned 

1. Resource 

Negative 

Maintain buffer stock of food condiments in case any batch of food is unfit for consumption.

2. Communication

Positive 

Customer feedback helped in improving the menu offerings. 

3. Business 

Negative

Focus on luxury items like grilled cheese and soups to make the program more sustainable.

4. Resource 

Positive 

Always have more than 4 ingredient suppliers so that in case of any emergency they can be used as a backup.

5. Business

Positive

Pair up with local farmers so that the local produce can compliment our menu and hold an advantage over the commercialized food and beverage companies.

8 of 9

Conclusions

Purpose of project - feed 1,000 underserved residents in Westfield area 3 times a week using donated food.

Project start date - 01 Jan 2022.

Max. Funds reserved for work type resources and implementation phase.

Saw some major milestones

As on 20 March 2022 - 64% work completed.

Project - 5% ahead of schedule.

Project ~ $8,000 under expected budget, reasons as mentioned before.

9 of 9

Thank you!

Questions?

Reference:

Hart, R. (2021). Westfield Food Pantry. Food truck business plan proposal.