Project Management
Operations Management
What is a Project?
A project may be defined as a series of related jobs usually directed toward some major output and requiring a significant period of time to perform.
Project management is a scientific way of planning, implementing, monitoring and controlling the various aspects of a project such as time, money, materials, manpower and other resources.
Elements
Project management comprises various elements such as:
Elements
Project management comprises various elements such as:
Elements of feasibility analysis
The first step of project management is project identification and appraisal which is also often called project feasibility analysis. This comprises the following elements:
Elements of feasibility analysis
Generation of Project ideas. | Screening of the generated ideas. | Detailed evaluation of the screened project ideas. |
| | |
Organizing the Project Team
Before the project starts, senior management must decide which of three organizational structures will be used to tie the project to the parent firm:
Organizing Project Tasks
Concept | Description |
Task | Is a further subdivision of a project. It is usually not longer than several months in duration and is performed by one group or organization. |
SubTask | May be used if needed to further subdivide the project into more meaningful pieces. |
Work package | Is a group of activities combined to be assignable to a single organizational unit. The package provides a description of what is to be done, when it is to be started and completed, the budget, measures of performance, and specific events to be reached at points in time. |
Project milestones | A specific event in a project. |
The work breakdown structure | The hierarchy of project tasks, subtasks, and work packages. |
Activities | Are defined within the context of the work breakdown structure and are pieces of work within a project that consume time. The completion of all the activities of a project marks the end of the project. |
Network-Planning Models
The two best-known network-planning models were developed in the 1950’s.
Network-Planning Models
Critical Path Method (CPM)
The critical path of activities in a project is the sequence of activities that form the longest chain in terms of their time to complete. If any one of the activities in the critical path is delayed, then the entire project is delayed.
It is possible and it often happens that there are multiple paths of the same length through the network so there are multiple critical paths.
Critical Path Method (CPM)
Following the basic steps:
Critical Path Method (CPM)
Activity | Designation | Immediate Predecessors | Time (Weeks) |
Select company | A | None | 1 |
Obtain annual report and perform ratio analysis | B | A | 2 |
Collect stock Price data and perform technical analysis. | C | A | 1 |
Review data and make a decision | D | B and C | 1 |
Critical Path Method (CPM)
The critical path is the path where the sum of the activity times is the longest.
Critical Path Method (CPM)
�����The slack time is the time that an activity can be delayed without delaying the entire project: the difference between the late and early start times of an activity.
CPM with Three Activity Time Estimates
If a single estimate of the time required to complete an activity is not reliable, the best procedure is to use three-time estimates.
CPM with Three Activity Time Estimates
a = Optimistic time: The minimum reasonable period of time in which the activity can be completed.
m = Most likely time: The best guess of the time required.
b = Pessimistic time: The maximum reasonable period of time the activity would take to be completed.
CPM with Three Activity �Time Estimates
ET =
a + 4m + b
6
CPM with Three Activity Time Estimates
Time – Cost Models and Project Crashing
Project managers are as much concerned with the cost to complete a project as with the time to complete the project.
Time – Cost models. Extension of the critical path models that considers the trade off between the time required to complete an activity and the costs.
This models attempt to develop a minimum – cost schedule for an entire project.
Time – Cost Models and Project Crashing
Minimum – Cost Scheduling (Time – Cost Trade-Off). The basic assumption in minimum-cost scheduling, also known as “crashing” is that there is a relationship between activity completion time and the cost of a project.
Crashing refers to the compression or shortening of the time to complete the project.
It costs money to expedite an activity; on the other, it costs money to sustain the project.
Costs associated with the expediting activities are termed activity direct costs and add to the project to the project direct cost (overtime working, hiring more workers).
The costs associated with sustaining the project are termed project indirect costs. (contractual situations)
Time – Cost Models and Project Crashing
Time – Cost Models and Project Crashing
Time – Cost Models and Project Crashing
Time – Cost Models and Project Crashing