1 of 89

Resource Planning

Chapter 11

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-1

2 of 89

What is Resource Planning?

Resource Planning

A process that takes sales and operations plans; processes information in the way of time standards, routings, and other information on how services or products are produced; and then plans the input requirements

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-2

3 of 89

Materials Requirements Planning

  • Material Requirements Planning (MRP)
    • A computerized information developed specifically to help manufacturers manage dependent demand inventory and schedule replenishment orders

  • MRP Explosion
    • A process that converts the requirements of various final products into a material requirements plan that specifies the replenishment schedules of all the subassemblies, components, and raw materials needed to produce final products

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-3

4 of 89

MRP Inputs

Inventory

transactions

Inventory

records

Bills of

materials

Engineering

and process

designs

Other

sources

of demand

Authorized

master production

schedule

Material

requirements

plan

MRP

explosion

Figure 11.1

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-4

5 of 89

Material Requirements Planning

  • Dependent demand
    • The demand for an item that occurs because the quantity required varies with the production plans for other items held in the firm’s inventory

  • Parent
    • An product that is manufactured from one or more components
  • Component
    • An item that goes through one or more operations to be transformed into or become part of one or more parents

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-5

6 of 89

Material Requirements Planning

| | | | | | | | | |

1 5 10

Day

2,000 –

1,500 –

1,000 –

500 –

0

Bicycles

(a) Parent inventory

Reorder point

Order

1,000 on

day 3

Order

1,000 on

day 8

(b) Component demand

2,000 –

1,500 –

1,000 –

500 –

0

Rims

| | | | | | | | | |

1 5 10

Day

Figure 11.2

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-6

7 of 89

Master Production Scheduling

  • Master Production Schedule (MPS)
    • A part of the material requirements plan that details how many end items will be produced within specified periods of time

  • In a Master Production Schedule:
    • Sums of quantities must equal sales and operations plan.
    • Production quantities must be allocated efficiently over time.
    • Capacity limitations and bottlenecks may determine the timing and size of MPS quantities.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-7

8 of 89

Master Production Scheduling

April

May

1

2

3

4

5

6

7

8

Ladder-back chair

Kitchen chair

Desk chair

Aggregate production plans for chair family

150

150

120

120

200

200

200

200

670

670

Figure 11.3

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-8

9 of 89

Master Production Scheduling

No

Material�requirements�planning

Yes

Authorized master�production�schedule

Are resources�available?

Prospective master�production�schedule

Authorized

production

plan

Figure 11.4

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-9

10 of 89

Master Production Scheduling

Step 1: Calculate projected on-hand inventories

=

+

Projected on-hand�inventory at end�of this week

On-hand�inventory at �end of last week

MPS quantity�due at start�of this week

Projected�requirements�this week

where:

Projected requirements = Max(Forecast, Customer Orders Booked)

=

Inventory

+

55 chairs�currently�in stock

MPS quantity�(0 for week 1)

38 chairs already�promised for�delivery in week 1

= 17 chairs

Developing a Master Production Schedule

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-10

11 of 89

Master Production Scheduling

Item: Ladder-back chair

Quantity on Hand:

Forecast

Customer orders (booked)

Projected on-hand inventory

MPS quantity

MPS start

April

1

2

55

30

30

38

27

17

–13

0

0

Explanation:

Forecast is less than booked orders in week 1; projected on-hand inventory balance �= 55 + 0 – 38 = 17.

Explanation:

Forecast exceeds booked orders in week 2; projected on-hand inventory balance = 17 + 0 – 30 = –13. The shortage signals a need to schedule an MPS quantity for completion in week 2.

Figure 11.6

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-11

12 of 89

Master Production Scheduling

Step 2: Determine the timing and size of MPS quantities

  • The goal is to maintain a nonnegative projected on-hand inventory balance
  • As shortages in inventory are detected, MPS quantities should be scheduled to cover them

=

Inventory

17 chairs in�inventory at the�end of week 1

+

MPS quantity�of 150 chairs

Forecast of�30 chairs

= 137 chairs

Developing a Master Production Schedule

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-12

13 of 89

Master Production Schedule (MPS)

Item: Ladder-back chair

Order Policy: 150 units

Lead Time: 1 week

1

2

3

4

5

6

7

8

April

Forecast

Customer�orders booked

Projected on-hand inventory

MPS quantity

MPS start

Quantity�on Hand:

30

38

30

27

30

24

30

8

0

35

0

35

0

0

35

35

55

May

17

137

107

77

42

7

122

87

0

150

0

0

0

0

150

0

150

0

0

0

0

150

0

0

Explanation:

On-hand inventory balance = 17 + 150 – 30 = 137. The MPS quantity is needed to avoid a shortage of 30 – 17 = 13 chairs in week 2.

Explanation:

The time needed to assemble 150 chairs is 1 week. The assembly department must start assembling chairs in week 1 to have them ready by week 2.

Figure 11.7

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-13

14 of 89

Master Production Scheduling

  • Available-to-promise (ATP) inventory
    • The quantity of end items that marketing can promise to deliver on specific dates
    • It is the difference between the customer orders already booked and the quantity that operations is planning to produce

  • Freezing the MPS
    • Disallow changes to the near-term portion of the MPS

  • Reconciling the MPS with Sales and Operations Plans

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-14

15 of 89

Master Production Schedule (MPS)

Item: Ladder-back chair

Order Policy: 150 units

Lead Time: 1 week

1

2

3

4

5

6

7

8

April

Forecast

Customer�orders booked

Projected on-hand inventory

MPS quantity

MPS start

Quantity�on Hand:

30

38

30

27

30

24

30

8

0

35

0

35

0

0

35

35

55

May

17

137

107

77

42

7

122

87

0

150

0

0

0

0

150

0

150

0

0

0

0

150

0

0

Available-to-promise (ATP)�inventory

17

91

150

Explanation:

The total of customer orders booked until the next MPS receipt is 38 units. The ATP = 55 (on-hand) + 0 (MPS quantity) – 38 = 17.

Explanation:

The total of customer orders booked until the next MPS receipt is 27 + 24 + 8 = 59 units. The ATP = 150 (MPS quantity) – 59 = 91 units..

Figure 11.8

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-15

16 of 89

Application 11.1

  • Determine the MPS for Product A that has a 50-unit policy and 55 units on hand.

  • The demand forecast and booked orders are shown in the partially completed plan.

  • The lead time is one week.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-16

17 of 89

Application 11.1

Item: Product A

Order Policy: 50 units

Lead Time: 1 week

Quantity on Hand 55

1

2

3

4

5

6

7

8

9

10

Forecast

20

10

40

10

0

0

30

20

40

20

Customer orders (booked)

30

20

5

8

0

2

0

0

0

0

Projected on-hand inventory

MPS quantity

MPS start

Available-to-promise (ATP) inventory

25

5

50

15

5

5

3

23

3

13

43

50

50

50

50

50

50

50

5

35

50

50

50

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-17

18 of 89

MRP Explosion

  • Bill of Materials
    • A record of all the components of an item, the parent-component relationships, and the usage quantities derived from engineering and process designs
  • End items
  • Intermediate items
  • Subassemblies
  • Purchased items
  • Part commonality (sometimes called standardization of parts or modularity)

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-18

19 of 89

MRP Explosion

Seat cushion

Seat-frame boards

Front legs

A

Ladder-back chair

Back legs

Leg supports

Back slats

Bill of Materials for a Ladder-Back Chair

Figure 11.10

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-19

20 of 89

MRP Explosion

J (4)

Seat-frame boards

G (4)

Back slats

F (2)

Back legs

I (1)

Seat cushion

H (1)

Seat frame

C (1)

Seat

subassembly

D (2)

Front

legs

B (1)

Ladder-back

subassembly

E (4)

Leg

supports

A

Ladder-back

chair

Figure 11.10

Bill of Materials for a Ladder-Back Chair

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-20

21 of 89

MRP Explosion

  • Inventory record
    • A record that shows an item’s lot-size policy, lead time, and various time-phased data.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-21

22 of 89

MRP Explosion

  • The time-phase information contained in the inventory record consists of:
    • Gross requirements
    • Scheduled receipts
    • Projected on-hand inventory

    • Planned receipts
    • Planned order releases

=

+

Projected on-hand�inventory balance�at end of week t

Inventory on�hand at end of�week t–1

Scheduled or planned receipts in week t

Gross�requirements�in week t

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-22

23 of 89

MRP Explosion

  • The on-hand inventory calculations for each week in the following slide are as follows

Week 1: 37 + 230 – 150 = 117

Weeks 2 and 3: 117 + 0 – 0 = 117

Week 4: 117 + 0 – 120 = –3

Week 5: –3 + 0 – 0 = –3

Week 6: –3 + 0 – 150 = –153

Week 7: –153 + 0 – 120 = –273

Week 8: –273 + 0 – 0 = –273

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-23

24 of 89

MRP Explosion

Item: C

Description: Seat subassembly

Lot Size: 230 units

Lead Time: 2 weeks

Week

1

2

3

4

5

6

7

8

Gross�requirements

0

0

0

0

Scheduled�receipts

0

0

0

0

0

0

0

Projected�on-hand�inventory

117

117

–3

–3

–153

–273

–273

Planned �receipts

Planned order releases

Explanation:

Gross requirements are the total demand for the two chairs. Projected on-hand inventory in week 1 is 37 + 230 – 150 = 117 units.

37

120

120

150

150

117

230

Figure 11.11

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-24

25 of 89

MRP Explosion

Item: C

Description: Seat subassembly

Lot Size: 230 units

Lead Time: 2 weeks

Week

1

2

3

4

5

6

7

8

Gross�requirements

150

0

0

Scheduled�receipts

230

0

0

Projected�on-hand�inventory

117

117

117

Planned �receipts

Planned order releases

37

Without a planned receipt in week 4, a shortage of 3 units will occur: 117 + 0 + 0 – 120 = –3 units. Adding the planned receipt brings the balance to 117 + 0 + 230 – 120 = 227 units.

The first planned receipt lasts until week 7, when projected inventory would drop to 77 + 0 + 0 – 120 = –43 units. Adding the second planned receipt brings the balance to 77 + 0 + 230 – 120 = 187 units.

120

0

227

230

230

230

230

187

120

0

77

0

150

0

0

227

0

0

187

Figure 11.12

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-25

26 of 89

Planning Factors

  • Planning lead time
    • An estimate of the time between placing an order and receiving the item in inventory.
  • Planning lead time consists of estimates for:
    • Setup time
    • Processing time
    • Materials handling time between operations
    • Waiting time

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-26

27 of 89

Planning Factors

  • Lot-sizing rules
    • Fixed order quantity (FQO) rule maintains the same order quantity each time an order is issued
      • Could be determined by quantity discounts, truckload capacity, minimum purchases, or EOQ

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-27

28 of 89

Planning Factors

  • Lot-sizing rules
    • Periodic order quantity (POQ) rule allows a different order quantity for each order issued but issues the order for predetermined time intervals

=

POQ lot size �to arrive in �week t

Total gross requirements�for P week, including�week t

Projected on-hand �inventory balance at �end of week t–1

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-28

29 of 89

Planning Factors

=

(POQ lot size)

Gross requirements�for weeks �4, 5, and 6

Inventory at �end of week 3

Using P = 3:

(POQ lot size) = (120 + 0 + 150) – 117 = 153 units

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-29

30 of 89

Planning Factors

Figure 11.13

Using POQ Rule

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-30

31 of 89

Planning Factors

=

L4L lot size �to arrive in �week t

Gross requirements�for week t

Projected on-hand �inventory balance at �end of week t – 1

=

(L4L lot size)

Gross requirements�in week 4

Inventory balance �at end of week 3

(L4L lot size) = 120 – 117 = 3 units

  • Lot-sizing rules
    • Lot-for-lot (L4L) rule under which the lot size ordered covers the gross requirements of a single week

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-31

32 of 89

Planning Factors

Figure 11.14

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-32

33 of 89

Application 11.2

Item: H10-A

Description: Chair seat assembly

Lot Size: FOQ = 80 units

Lead Time: 4 weeks

Week

31

32

33

34

35

36

37

38

39

40

Gross�requirements

60

35

45

60

Scheduled�receipts

80

Projected�on-hand�inventory

Planned �receipts

Planned order releases

20

20

40

40

40

40

5

5

Item H10-A is a produced item (not purchased) with an order quantity of 80 units. Complete the rest of its MRP record using the fixed order quantity (FOQ) rule

80

80

40

40

80

80

60

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-33

34 of 89

Application 11.3

Now complete the H10-A record using a POQ rule. The P should give an average lot size of 80 units.

Assume the average weekly requirements are 20 units.

P = = 4 weeks

80

20

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-34

35 of 89

Application 11.3

Item: H10-A

Description: Chair seat assembly

Lot Size: POQ = 4

Lead Time: 4 weeks

Week

31

32

33

34

35

36

37

38

39

40

Gross�requirements

60

35

45

60

Scheduled�receipts

80

Projected�on-hand�inventory

Planned �receipts

Planned order releases

20

20

40

40

40

40

5

5

100

100

60

60

0

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-35

36 of 89

Application 11.4

Revise the H10-A record using the lot-for-lot (L4L) Rule. (Complete the highlighted section)

Item: H10-A

Description: Chair seat assembly

Lot Size: L4L

Lead Time: 4 weeks

Week

31

32

33

34

35

36

37

38

39

40

Gross�requirements

60

35

45

60

Scheduled�receipts

80

Projected�on-hand�inventory

Planned �receipts

Planned order releases

20

40

40

40

40

5

5

20

40

40

0

0

60

60

0

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-36

37 of 89

Planning Factors

  • Comparing lot-sizing rules

FOQ:

= 181 units

227 + 227 + 77 + 187 + 187

5

POQ:

= 60 units

150 + 150 + 0 + 0 + 0

5

L4L:

= 0 units

0 + 0 + 0 + 0 + 0

5

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-37

38 of 89

Planning Factors

  • Lot sizes affect inventory, setup, and ordering costs
    1. The FOQ rule generates a high level of average inventory because it creates inventory remnants.
    2. The POQ rule reduces the amount of average on-hand inventory because it does a better job of matching order quantity to requirements.
    3. The L4L rule minimizes inventory investment, but it also maximizes the number of orders placed.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-38

39 of 89

Planning Factors

  • Safety stock for dependent demand items with lumpy demand (gross requirements) is helpful only when future gross requirements, the timing or size of scheduled receipts, and the amount of scrap that will be produced are uncertain.
    • Used for end items and purchased items to protect against fluctuating customer orders and unreliable suppliers of components but avoid using it as much as possible for intermediate items.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-39

40 of 89

Planning Factors

Safety Stock

Figure 11.15

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-40

41 of 89

Outputs from MRP

Manufacturing resources plan

Performance reports

Material requirements plan

Action notices

  • Releasing new orders
  • Adjusting due dates

Priority reports

  • Dispatch lists
  • Supplier schedules

Capacity reports

  • Capacity requirements planning
  • Finite capacity scheduling
  • Input-output control

Cost and price data

MRP explosion

Routings and time standards

Figure 11.16

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-41

42 of 89

Outputs from MRP

  • Material Requirements
    • An item’s gross requirements are derived from three sources:
      • The MPS for immediate parents that are end items
      • The planned order releases for immediate parents below the MPS level
      • Any other requirements not originating in the MPS, such as the demand for replacement parts

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-42

43 of 89

Outputs from MRP

J(4)

Seat-frame�boards

C(1)

Seat�subassembly

H(1)

Seat�frame

I(1)

Seat�cushion

BOM for the Seat Subassembly

Figure 11.17

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-43

44 of 89

Outputs from MRP

Item: Seat subassembly

Lot size: 230 units

Lead

time: 2 weeks

Gross requirements

150

1

230

117

2

3

120

4

5

150

6

120

7

8

Scheduled receipts

Projected on-hand inventory

Planned receipts

Planned order releases

37

Week

117

117

0

0

0

0

0

0

0

0

0

0

0

227

227

77

187

187

230

230

230

230

Figure 11.18

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-44

45 of 89

Outputs from MRP

Item: Seat frames

Lot size: 300 units

Lead

time: 1 week

Gross requirements

1

0

2

3

4

5

6

7

8

Scheduled receipts

Projected on-hand inventory

Planned receipts

Planned order releases

40

Week

0

0

0

300

0

0

0

Item: Seat cushion

Lot size: L4L

Lead

time: 1 week

Gross requirements

1

0

2

3

4

5

6

7

8

Scheduled receipts

Projected on-hand inventory

Planned receipts

Planned order releases

0

Week

0

0

0

0

0

0

0

Item: Seat subassembly

Lot size: 230 units

Lead

time: 2 weeks

Gross requirements

150

1

2

3

120

4

5

150

6

120

7

8

Planned receipts

Planned order releases

Week

0

0

0

0

230

230

230

230

Usage quantity: 1

Usage quantity: 1

0

230

0

230

0

230

0

0

230

0

Figure 11.18

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-45

46 of 89

Outputs from MRP

Item: Seat subassembly

Lot size: 230 units

Lead

time: 2 weeks

Gross requirements

150

1

2

3

120

4

5

150

6

120

7

8

Planned receipts

Planned order releases

Week

0

0

0

0

230

230

230

230

Item: Seat frames

Lot size: 300 units

Lead

time: 1 week

Gross requirements

1

0

2

3

4

5

6

7

8

Scheduled receipts

Projected on-hand inventory

Planned receipts

Planned order releases

40

Week

0

0

0

300

0

0

0

Item: Seat cushion

Lot size: L4L

Lead

time: 1 week

Gross requirements

1

0

2

3

4

5

6

7

8

Scheduled receipts

Projected on-hand inventory

Planned receipts

Planned order releases

0

Week

0

0

0

0

0

0

0

0

230

0

230

0

230

0

0

230

0

0

0

0

40

110

110

110

180

180

180

180

300

300

0

0

0

0

0

0

0

0

0

0

0

230

230

230

230

Figure 11.18

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-46

47 of 89

Outputs from MRP

Item: Seat frames

Lot size: 300 units

Lead

time: 1 week

Gross requirements

1

2

3

4

5

6

7

8

Planned receipts

Planned order releases

Week

300

300

Item: Seat cushion

Lot size: L4L

Lead

time: 1 week

Gross requirements

1

2

3

4

5

6

7

8

Planned receipts

Planned order releases

Week

230

230

230

230

0

0

0

0

230

230

0

0

0

0

0

0

230

230

0

0

Gross requirements

1

0

2

3

4

5

6

7

8

Scheduled receipts

Planned receipts

Planned order releases

200

Week

0

0

0

0

0

0

0

Projected on-hand inventory

Item: Seat-frame boards

Lot size: 1500 units

Lead

time: 1 week

Usage quantity: 4

1200

200

200

200

500

500

500

500

500

1500

1500

Figure 11.18

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-47

48 of 89

Application 11.5

A firm makes a product (Item A) from three components (intermediate Items B and D, and purchased item C).

The latest MPS for product A calls for completion of a 250-unit order in week 8, and its lead time is 2 weeks.

The master schedule and bill of material for Product A are on the following slides:

Item: End Item A

Lead Time: 2 wks

Week

1

2

3

4

5

6

7

8

MPS quantity

250

MPS start

250

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-48

49 of 89

Application 11.5

Develop a material requirements plan for items B, C, and D, given the following inventory data.

C(2)

C(2)

B(1)

B(1)

C(1)

D(2)

A

Data Category

Item

B

C

D

Lot-sizing rule

POQ (P = 5)

FOQ = 1000

L4L

Lead time

2 weeks

1 week

3 weeks

Scheduled receipts

None

1000 (week 1)

None

Beginning inventory

0

800

0

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-49

50 of 89

Application 11.5

An item’s gross requirements cannot be derived until all of its immediate parents are processed.

Thus we must begin with Item D. Its only immediate parent is item A, and its planned “production plan” is shown by the MPS start row.

Item: D Lot Size: L4L

Description: Lead Time: 3 weeks

Week

1

2

3

4

5

6

7

8

Gross requirements

Scheduled receipts

Projected on-hand inventory 0

Planned receipts

Planned order releases

0

0

0

500

0

0

0

500

500

0

0

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-50

51 of 89

Application 11.5

We can do item B next, because the planned “production quantities” for its two immediate parents (A and D) are known.

Item C cannot be done yet, because one of its parents is item B, and its PORs are still unknown.

Item: B Lot Size: POQ = 5

Description: Lead Time: 2 weeks

Week

1

2

3

4

5

6

7

8

Gross requirements

Scheduled receipts

Projected on-hand inventory 0

Planned receipts

Planned order releases

500

250

0

0

250

750

250

750

250

0

0

0

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-51

52 of 89

Application 11.5

Finally we can do Item C, because we now know the planned “production quantities” of both of its immediate parents (A and B).

Item: C Lot Size: 1000

Description: Lead Time: 1 week

Week

1

2

3

4

5

6

7

8

Gross requirements

Scheduled receipts

1000

Projected on-hand inventory 800

Planned receipts

Planned order releases

1500

250

300

300

300

300

300

50

50

50

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-52

53 of 89

Outputs from MRP

  • Action notices
    • A computer-generated memo alerting planners about releasing new orders and adjusting the due dates of scheduled receipts.
  • Resource Requirement Reports
    • Theory of constraints principles
    • Capacity requirements planning (CRP)
  • Performance Reports
    • Manufacturing resource planning (MRP II)

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-53

54 of 89

MRP and the Environment

  • Consumer and government concern about the deterioration of the natural environment has driven manufacturers to reengineer their processes to become more environmentally friendly.

  • Companies can modify their MRP systems to help track these waste and plans for their disposal.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-54

55 of 89

MRP, Core Processes, and Supply Chain Linkages

  • The MRP system interacts with the four core processes of an organization
    • Supplier relationship process
    • New service/product development process
    • Order fulfillment process
    • Customer relationship process

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-55

56 of 89

MRP, Core Processes, and Supply Chain Linkages

External Suppliers

External Customers

Supplier

Relationship

Process

MPS

Order

Fulfillment

Process

MRP

Customer

Relationship

Process

New Service/Product Development Process

Bill of Materials

Supplier

Orders

Customer

Orders

Order

Promises

And

Due Dates

Supplier Schedules

(Planned Order Releases)

Figure 11.19

Adjustments to due dates of scheduled releases

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-56

57 of 89

Enterprise Resource Planning

  • Enterprise process
    • A companywide process that cuts across functional areas, business units, geographic regions, product lines, suppliers, and customers
  • Enterprise resource planning (ERP) systems
    • Large, integrated information systems that support many enterprise processes and data storage needs

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-57

58 of 89

Enterprise Resource Planning

Back-Office Processes Front-Office Processes

Human

Resources

  • Benefits
  • Payroll

Data Analysis

  • Product costing
  • Job costs

Sales and Marketing

  • Sales orders
  • Pricing system

Customer Service

  • Field service
  • Quality

Supply-Chain

Management

  • Forecasting
  • Purchasing
  • Distribution

Accounting and Finance

  • Accounts payable �and receivable
  • General ledgers
  • Asset management

Manufacturing

  • Material requirements planning
  • Scheduling

ERP System

Figure 11.20

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-58

59 of 89

Resource Planning for �Service Providers

  • Dependent demand for services
    • Restaurants
    • Airlines
    • Hospitals
    • Hotels

  • Bill of Resources (BOR)
    • A record of a service firm’s parent-component relationships and all of the materials, equipment time, staff, and other resources associated with them, including usage quantities.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-59

60 of 89

Bill of Resources

  • Consider a regional hospital that among many other procedures performs aneurysm treatments. The BOR (Figure 11.21) for treatment has 7 levels.

  • The hospital is interested in understanding how much of each critical resource of nurses, beds and lab tests will be needed if the projected patient departures from the aneurysm treatment process over the next 15 days are as shown in Table 11.1

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-60

61 of 89

Bill of Resources

Level 1

Discharge

Level 2

Intermediate care

Level 3

Postoperative care

(Step down)

Level 4

Postoperative care

(Intensive)

Level 7

Preoperative care

(Testing)

Level 5

Surgery

Nurse

(6 hr)

MD

(1 hr)

Therapy

(1 hr)

Bed

(24 hr)

Lab

(3 tests)

Kitchen

(1 meal)

Pharmacy

(10

medicines)

Level 6

Preoperative care

(Angiogram)

Level 6

Preoperative care

(Angiogram

Figure 11.21

Cumulative lead time, or the patient stay time at the hospital, across all seven levels for the entire duration of the aneurysm treatment is 10 days.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-61

62 of 89

Bill of Resources

Day of the Month

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

Aneurysm Patient

1

2

1

3

2

3

0

1

2

1

2

2

2

2

2

Table 11.1

The first 10 days of the projected departures represent actual patients who have started the process while the last 5 days are forecasts based on historical records.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-62

63 of 89

Bill of Resources

Resources Required for Each Aneurysm Patient

Nurse Hours Required Per Day

Per Patient

Beds Required Per Day

Per Patient

Lab Tests Required Per Day

Per Patient

Level 1

0

0

0

Level 2

6

0

0

Level 3

16

1

4

Level 4

12

1

6

Level 5

22

1

2

Level 6

6

1

3

Level 7

1

0

0

Use the information above to calculate the daily resource requirements for treating aneurysm patients (similar to the gross requirements in a MRP record). Begin by calculating the number of patients that will be at each level (or stage) of treatment each day.

Table 11.2

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-63

64 of 89

Bill of Resources

Figure 11.22

As shown below, the aneurysm patient departures become the Master Schedule for Level 1 and these departures drive the need for resources at each level of the process.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-64

65 of 89

Bill of Resources

Once we know how many patients will need each level of treatment on each day, we can multiply this demand by the amount of each resource required to treat them.

Example:

Total Number of Lab Tests Projected for Day 5

= [0(2) + 0(3) + 4(3) + 6(3) + 2(2) + 3(2) + 0(2)]

= 40

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-65

66 of 89

Bill of Resources

Day of the Month

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

Nursing Hours Required

179

198

170

170

160

170

190

184

150

132

108

76

44

12

0

Beds required

12

12

11

11

10

12

13

11

10

8

6

4

2

0

0

Lab Tests Required

50

45

46

44

40

50

54

48

48

36

24

16

8

0

0

Table 11.3

The above table shows how much of each critical resource is required in total to treat aneurysm patients for the 15-day master schedule.

This table shows the resources needed from Day 1 to Day 15 for the current schedule.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-66

67 of 89

Solved Problem 1

Refer to the bill of materials for product A shown below.

If there is no existing inventory and no scheduled receipts, how many units of items G, E, and D must be purchased to produce 5 units of end item A?

LT = 2

LT = 3

B (3)

C (1)

G (1)

LT = 3

LT = 3

LT = 3

D (1)

LT = 6

LT = 1

F (1)

LT = 1

A

Figure 11.23

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-67

68 of 89

Solved Problem 1

  • Five units of item G, 30 units of item E, and 20 units of item D must be purchased to make 5 units of A.
  • The usage quantities indicate that 2 units of E are needed to make 1 unit of B and that 3 units of B are needed to make 1 unit of A; therefore, 5 units of A require 30 units of E (2 × 3 × 5 = 30).
  • One unit of D is consumed to make 1 unit of B, and 3 units of B per unit of A result in 15 units of D (1 × 3 × 5 = 15)
  • One unit of D in each unit of C and 1 unit of C per unit of A result in another 5 units of D (1 × 1 × 5 = 5).
  • The total requirements to make 5 units of A are 20 units of D(15 + 5).
  • The calculation of requirements for G is simply 1 × 1 × 1 × 5 = 5 units.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-68

69 of 89

Solved Problem 2

  • The order policy is to produce end item A in lots of 50 units.
  • Complete the projected on-hand inventory and MPS quantity rows.
  • Complete the MPS start row by offsetting the MPS quantities for the final assembly lead time.
  • Compute the available-to-promise inventory for item A.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-69

70 of 89

Solved Problem 2

  • Assess the following customer requests for new orders.
  • Assume that these orders arrive consecutively and their affect on ATP is cumulative.
  • Which of these orders can be satisfied without altering the MPS Start quantities?
    • Customer A requests 30 units in week 1
    • Customer B requests 30 units in week 4
    • Customer C requests 10 units in week 3
    • Customer D requests 50 units in week 5

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-70

71 of 89

Solved Problem 2

Item: A

Order Policy: 50 units

Lead Time: 1 week

Week

1

2

3

4

5

6

7

8

9

10

Forecast

20

10

40

10

0

0

30

20

40

20

Customer orders (booked)

30

20

5

8

0

2

0

0

0

0

Projected�on-hand�inventory

25

MPS quantity

50

MPS start

Available-to-promise (ATP) inventory

Quantity on Hand 5

Figure 11.24

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-71

72 of 89

Solved Problem 2

The projected on-hand inventory for the second week is

=

+

Projected on-hand�inventory at end�of week 2

On-hand�inventory in�week 1

MPS quantity�due in week 2

Requirements�in week 2

= 25 + 0 – 20 = 5 units

where requirements are the larger of the forecast or actual customer orders booked for shipment during this period. No MPS quantity is required.

Without an MPS quantity in the third period, a shortage of item A will occur: 5 + 0 – 40 = –35.

Therefore, an MPS quantity equal to the lot size of 50 must be scheduled for completion in the third period. Then the projected on-hand inventory for the third week will be 5 + 50 – 40 = 15.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-72

73 of 89

Solved Problem 2

The MPS start row is completed by simply shifting a copy of the MPS quantity row to the left by one column to account for the 1-week final assembly lead time. Also shown are the available-to-promise quantities. In week 1, the ATP is

=

+

Available-to-�promise in�week 1

On-hand�quantity in�week 1

MPS quantity�in week 1

Orders booked up�to week 3 when the�next MPS arrives

= 5 + 50 – (30 + 20) = 5 units

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-73

74 of 89

Solved Problem 2

The ATP for the MPS quantity in week 3 is

=

Available-to-�promise in�week 3

MPS quantity�in week 3

Orders booked up�to week 7 when the�next MPS arrives

= 50 – (5 + 8 + 0 + 2) = 35 units

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-74

75 of 89

Solved Problem 2

Figure 11.25

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-75

76 of 89

Solved Problem 3

The MPS start quantities for product A calls for the assembly department to begin final assembly according to the following schedule:

  • 100 units in week 2; 200 units in week 4
  • 120 units in week 6; 180 units in week 7
  • 60 units in week 8.
  • Develop a material requirements plan for the next 8 weeks for items B, C, and D.

A

B (1)

C (2)

D (1)

LT = 2

LT = 1

LT = 2

LT = 3

Figure 11.26

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-76

77 of 89

Solved Problem 3

INVENTORY RECORD DATA

Item

Data Category

B

C

D

Lot-sizing rule

POQ (P =3)

L4L

FOQ = 500 units

Lead time

1 week

2 weeks

3 weeks

Scheduled receipts

None

200 (week 1)

None

Beginning (on-hand) inventory

20

0

425

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-77

78 of 89

Solved Problem 3

Item: B

Lot Size: POQ (P = 3)

Lead Time: 1 week

Week

1

2

3

4

5

6

7

8

9

10

Gross requirements

100

200

120

180

60

Scheduled receipts

Projected�on-hand�inventory

20

200

200

0

0

240

60

0

0

0

Planned receipts

280

360

Planned order releases

280

360

20

Figure 11.27

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-78

79 of 89

Solved Problem 3

Item: C

Lot Size: L4L

Lead Time: 2 weeks

Week

1

2

3

4

5

6

7

8

9

10

Gross requirements

200

400

240

360

120

Scheduled receipts

200

Projected�on-hand�inventory

200

0

0

0

0

0

0

0

0

0

Planned receipts

400

240

360

120

Planned order releases

400

240

360

120

0

Figure 11.27

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-79

80 of 89

Solved Problem 3

Item: D

Lot Size: FOQ = 500 units

Lead Time: 1 week

Week

1

2

3

4

5

6

7

8

9

10

Gross requirements

400

240

360

120

Scheduled receipts

Projected�on-hand�inventory

425

25

25

285

425

305

305

305

305

305

Planned receipts

500

500

Planned order releases

500

500

425

Figure 11.27

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-80

81 of 89

Solved Problem 4

  • The Pet Training Academy offers a 5-day training program for troubled dogs. As seen below, the training process requires 5 days, beginning with the dog’s arrival at 8 A.M. on day one, and departure after a shampoo and trim, at 5 P.M. on day five.

Pet Training Academy Process

Lead Time in Days

Level 1: Departure Day

1

Level 2: 3rd Day

1

Level 3: 2nd Day

2

Level 4: Arrival Day

1

Total

5

Table 11.5

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-81

82 of 89

Solved Problem 4

  • To adequately train a dog, the Academy requires Training Coaches, Dog Groomers, a Dog Dietician, Care Assistants, and Boarding Kennels where the dogs rest.
  • The time required by each employee and resource classifications by process level is given below:

Pet Training Academy Process Resources Required

Training Coach (Hours)

Dog Dietician ( Hours)

Care Assistant (Hours)

Boarding Kennel (Hours)

Level 1: Departure Day

2

1

1

12

Level 2: 3rd Day

3

1

2

24

Level 3: 2nd Day

3

1

2

24

Level 4: Arrival Day

2

1

1

12

Table 11.6

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-82

83 of 89

Solved Problem 4

  • The master schedule for the trained dogs is shown below, noting that departures for trained dogs are actual departures for days 1-5 and forecasted departures for days 6-12.

Day of the month

1

2

3

4

5

6

7

8

9

10

11

12

Master Schedule of Trained Dogs

5

2

2

8

3

0

1

8

4

3

6

0

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-83

84 of 89

Solved Problem 4

  1. Use the above information to calculate the daily resource requirements in hours for employees in each category, and the hours of boarding room needed to train the dogs.
  2. Assuming that each boarding kennel is available for 24 hours in a day, how many kennels will be required each day?
  3. Assuming that each employee is able to work only eight hours per day, how many people in each employee category will be required each day?

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-84

85 of 89

Solved Problem 4

Figure 11.28

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-85

86 of 89

Solved Problem 4

The previous table shows the number of dogs at each level during their stay at the Pet Training Academy.

The top row of each level shows the number of dogs who will advance to the next level at the end of the day.

The daily resource requirements for each resource required to train the departing dogs are shown in the following slide.

Total number of CA hours Projected for Day 2

[1(2) + 2(2) + 2(11) +1(0)] = 28 hours

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-86

87 of 89

Solved Problem 4

Day of the Month

1

2

3

4

5

6

7

8

9

10

11

12

Training Coach Hours required

52

43

39

44

41

45

59

55

35

24

12

0

Dog Dietician hours required

20

15

14

20

16

16

22

21

13

9

6

0

Care Assistant hours required

32

28

25

24

25

29

37

34

22

15

6

0

Boarding kennels hours required

384

336

300

288

300

348

444

408

264

180

72

0

Number of Boarding Kennels required

16

14

13

12

13

15

19

17

11

8

3

0

Table 11.7

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-87

88 of 89

Solved Problem 4

  1. The number of boarding kennels required per day (note all fractional kennels are rounded to the next higher integer) are obtained by dividing the total number of hours needed for boarding kennels by 24, and are shown in the last row of the previous slide.

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-88

89 of 89

Solved Problem 4

  1. The number of people required per day in each employee category are obtained by dividing the resource requirements by working hours in each day. They are shown below. Note that all fractional employees are rounded to the next higher integer.

Number of Employee Required per Day

1

2

3

4

5

6

7

8

9

10

11

12

Training Coaches

7

6

5

6

6

6

8

7

5

3

2

0

Dog Dieticians

3

2

2

3

2

2

3

3

2

2

1

0

Care Assistants

4

4

4

3

4

4

5

5

3

2

1

0

Copyright ©2016 Pearson Education, Inc. All rights reserved.

11-89