Resource Planning
Chapter 11
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-1
What is Resource Planning?
Resource Planning
A process that takes sales and operations plans; processes information in the way of time standards, routings, and other information on how services or products are produced; and then plans the input requirements
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-2
Materials Requirements Planning
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-3
MRP Inputs
Inventory
transactions
Inventory
records
Bills of
materials
Engineering
and process
designs
Other
sources
of demand
Authorized
master production
schedule
Material
requirements
plan
MRP
explosion
Figure 11.1
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-4
Material Requirements Planning
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-5
Material Requirements Planning
| | | | | | | | | |
1 5 10
Day
2,000 –
1,500 –
1,000 –
500 –
0
Bicycles
(a) Parent inventory
Reorder point
Order
1,000 on
day 3
Order
1,000 on
day 8
(b) Component demand
2,000 –
1,500 –
1,000 –
500 –
0
Rims
| | | | | | | | | |
1 5 10
Day
Figure 11.2
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-6
Master Production Scheduling
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-7
Master Production Scheduling
| April | May | ||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Ladder-back chair | | | | | | | | |
Kitchen chair | | | | | | | | |
Desk chair | | | | | | | | |
Aggregate production plans for chair family | | | ||||||
150
150
120
120
200
200
200
200
670
670
Figure 11.3
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-8
Master Production Scheduling
No
Material�requirements�planning
Yes
Authorized master�production�schedule
Are resources�available?
Prospective master�production�schedule
Authorized
production
plan
Figure 11.4
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-9
Master Production Scheduling
Step 1: Calculate projected on-hand inventories
=
+
–
Projected on-hand�inventory at end�of this week
On-hand�inventory at �end of last week
MPS quantity�due at start�of this week
Projected�requirements�this week
where:
Projected requirements = Max(Forecast, Customer Orders Booked)
=
Inventory
+
55 chairs�currently�in stock
–
MPS quantity�(0 for week 1)
38 chairs already�promised for�delivery in week 1
= 17 chairs
Developing a Master Production Schedule
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-10
Master Production Scheduling
Item: Ladder-back chair
Quantity on Hand:
Forecast
Customer orders (booked)
Projected on-hand inventory
MPS quantity
MPS start
April
1
2
55
30
30
38
27
17
–13
0
0
Explanation:
Forecast is less than booked orders in week 1; projected on-hand inventory balance �= 55 + 0 – 38 = 17.
Explanation:
Forecast exceeds booked orders in week 2; projected on-hand inventory balance = 17 + 0 – 30 = –13. The shortage signals a need to schedule an MPS quantity for completion in week 2.
Figure 11.6
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-11
Master Production Scheduling
Step 2: Determine the timing and size of MPS quantities
=
Inventory
17 chairs in�inventory at the�end of week 1
+
MPS quantity�of 150 chairs
–
Forecast of�30 chairs
= 137 chairs
Developing a Master Production Schedule
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-12
Master Production Schedule (MPS)
Item: Ladder-back chair
Order Policy: 150 units
Lead Time: 1 week
1
2
3
4
5
6
7
8
April
Forecast
Customer�orders booked
Projected on-hand inventory
MPS quantity
MPS start
Quantity�on Hand:
30
38
30
27
30
24
30
8
0
35
0
35
0
0
35
35
55
May
17
137
107
77
42
7
122
87
0
150
0
0
0
0
150
0
150
0
0
0
0
150
0
0
Explanation:
On-hand inventory balance = 17 + 150 – 30 = 137. The MPS quantity is needed to avoid a shortage of 30 – 17 = 13 chairs in week 2.
Explanation:
The time needed to assemble 150 chairs is 1 week. The assembly department must start assembling chairs in week 1 to have them ready by week 2.
Figure 11.7
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-13
Master Production Scheduling
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-14
Master Production Schedule (MPS)
Item: Ladder-back chair
Order Policy: 150 units
Lead Time: 1 week
1
2
3
4
5
6
7
8
April
Forecast
Customer�orders booked
Projected on-hand inventory
MPS quantity
MPS start
Quantity�on Hand:
30
38
30
27
30
24
30
8
0
35
0
35
0
0
35
35
55
May
17
137
107
77
42
7
122
87
0
150
0
0
0
0
150
0
150
0
0
0
0
150
0
0
Available-to-promise (ATP)�inventory
17
91
150
Explanation:
The total of customer orders booked until the next MPS receipt is 38 units. The ATP = 55 (on-hand) + 0 (MPS quantity) – 38 = 17.
Explanation:
The total of customer orders booked until the next MPS receipt is 27 + 24 + 8 = 59 units. The ATP = 150 (MPS quantity) – 59 = 91 units..
Figure 11.8
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-15
Application 11.1
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-16
Application 11.1
Item: Product A | Order Policy: 50 units | |||||||||
| | Lead Time: 1 week | ||||||||
Quantity on Hand 55 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Forecast | 20 | 10 | 40 | 10 | 0 | 0 | 30 | 20 | 40 | 20 |
Customer orders (booked) | 30 | 20 | 5 | 8 | 0 | 2 | 0 | 0 | 0 | 0 |
Projected on-hand inventory | | | | | | | | | | |
MPS quantity | | | | | | | | | | |
MPS start | | | | | | | | | | |
Available-to-promise (ATP) inventory | | | | | | | | | | |
25 | 5 |
| |
| 50 |
| |
15 | 5 | 5 | 3 | 23 | 3 | 13 | 43 |
50 | | | | 50 | | 50 | 50 |
| | | 50 | | 50 | 50 | |
| | | | | | | |
5
35
50
50
50
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-17
MRP Explosion
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-18
MRP Explosion
Seat cushion
Seat-frame boards
Front legs
A
Ladder-back chair
Back legs
Leg supports
Back slats
Bill of Materials for a Ladder-Back Chair
Figure 11.10
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-19
MRP Explosion
J (4)
Seat-frame boards
G (4)
Back slats
F (2)
Back legs
I (1)
Seat cushion
H (1)
Seat frame
C (1)
Seat
subassembly
D (2)
Front
legs
B (1)
Ladder-back
subassembly
E (4)
Leg
supports
A
Ladder-back
chair
Figure 11.10
Bill of Materials for a Ladder-Back Chair
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-20
MRP Explosion
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-21
MRP Explosion
=
+
–
Projected on-hand�inventory balance�at end of week t
Inventory on�hand at end of�week t–1
Scheduled or planned receipts in week t
Gross�requirements�in week t
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-22
MRP Explosion
Week 1: 37 + 230 – 150 = 117
Weeks 2 and 3: 117 + 0 – 0 = 117
Week 4: 117 + 0 – 120 = –3
Week 5: –3 + 0 – 0 = –3
Week 6: –3 + 0 – 150 = –153
Week 7: –153 + 0 – 120 = –273
Week 8: –273 + 0 – 0 = –273
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-23
MRP Explosion
Item: C Description: Seat subassembly | Lot Size: 230 units Lead Time: 2 weeks | |||||||
| Week | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross�requirements | | 0 | 0 | | 0 | | | 0 |
Scheduled�receipts | | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Projected�on-hand�inventory | | 117 | 117 | –3 | –3 | –153 | –273 | –273 |
Planned �receipts | | | | | | | | |
Planned order releases | | | | | | | | |
Explanation:
Gross requirements are the total demand for the two chairs. Projected on-hand inventory in week 1 is 37 + 230 – 150 = 117 units.
37
120
120
150
150
117
230
Figure 11.11
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-24
MRP Explosion
Item: C Description: Seat subassembly | Lot Size: 230 units Lead Time: 2 weeks | |||||||
| Week | |||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross�requirements | 150 | 0 | 0 | | | | | |
Scheduled�receipts | 230 | 0 | 0 | | | | | |
Projected�on-hand�inventory | 117 | 117 | 117 | | | | | |
Planned �receipts | | | | | | | | |
Planned order releases | | | | | | | | |
37
Without a planned receipt in week 4, a shortage of 3 units will occur: 117 + 0 + 0 – 120 = –3 units. Adding the planned receipt brings the balance to 117 + 0 + 230 – 120 = 227 units.
The first planned receipt lasts until week 7, when projected inventory would drop to 77 + 0 + 0 – 120 = –43 units. Adding the second planned receipt brings the balance to 77 + 0 + 230 – 120 = 187 units.
120
0
227
230
230
230
230
187
120
0
77
0 | 150 |
0 | 0 |
227 | |
0 |
0 |
187 |
Figure 11.12
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-25
Planning Factors
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-26
Planning Factors
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-27
Planning Factors
=
–
POQ lot size �to arrive in �week t
Total gross requirements�for P week, including�week t
Projected on-hand �inventory balance at �end of week t–1
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-28
Planning Factors
=
–
(POQ lot size)
Gross requirements�for weeks �4, 5, and 6
Inventory at �end of week 3
Using P = 3:
(POQ lot size) = (120 + 0 + 150) – 117 = 153 units
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-29
Planning Factors
Figure 11.13
Using POQ Rule
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-30
Planning Factors
=
–
L4L lot size �to arrive in �week t
Gross requirements�for week t
Projected on-hand �inventory balance at �end of week t – 1
=
–
(L4L lot size)
Gross requirements�in week 4
Inventory balance �at end of week 3
(L4L lot size) = 120 – 117 = 3 units
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-31
Planning Factors
Figure 11.14
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-32
Application 11.2
Item: H10-A Description: Chair seat assembly | Lot Size: FOQ = 80 units Lead Time: 4 weeks | |||||||||
| Week | |||||||||
| 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 |
Gross�requirements | | 60 | | | | 35 | | 45 | | 60 |
Scheduled�receipts | | 80 | | | | | | | | |
Projected�on-hand�inventory | | | | | | | | | | |
Planned �receipts | | | | | | | | | | |
Planned order releases | | | | | | | | | | |
20
20 | 40 | 40 | 40 | 40 | 5 | 5 | |
Item H10-A is a produced item (not purchased) with an order quantity of 80 units. Complete the rest of its MRP record using the fixed order quantity (FOQ) rule
80
80
40
40
80
80
60
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-33
Application 11.3
Now complete the H10-A record using a POQ rule. The P should give an average lot size of 80 units.
Assume the average weekly requirements are 20 units.
P = = 4 weeks
80
20
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-34
Application 11.3
Item: H10-A Description: Chair seat assembly | Lot Size: POQ = 4 Lead Time: 4 weeks | |||||||||
| Week | |||||||||
| 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 |
Gross�requirements | | 60 | | | | 35 | | 45 | | 60 |
Scheduled�receipts | | 80 | | | | | | | | |
Projected�on-hand�inventory | | | | | | | | | | |
Planned �receipts | | | | | | | | | | |
Planned order releases | | | | | | | | | | |
20
20 | 40 | 40 | 40 | 40 | 5 | 5 | |
100
100
60
60
0
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-35
Application 11.4
Revise the H10-A record using the lot-for-lot (L4L) Rule. (Complete the highlighted section)
Item: H10-A Description: Chair seat assembly | Lot Size: L4L Lead Time: 4 weeks | |||||||||
| Week | |||||||||
| 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 |
Gross�requirements | | 60 | | | | 35 | | 45 | | 60 |
Scheduled�receipts | | 80 | | | | | | | | |
Projected�on-hand�inventory | | | | | | | | | | |
Planned �receipts | | | | | | | | | | |
Planned order releases | | | | | | | | | | |
20 | 40 | 40 | 40 | 40 | 5 | 5 | |
20
40
40
0
0
60
60
0
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-36
Planning Factors
FOQ:
= 181 units
227 + 227 + 77 + 187 + 187
5
POQ:
= 60 units
150 + 150 + 0 + 0 + 0
5
L4L:
= 0 units
0 + 0 + 0 + 0 + 0
5
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-37
Planning Factors
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-38
Planning Factors
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-39
Planning Factors
Safety Stock
Figure 11.15
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-40
Outputs from MRP
Manufacturing resources plan
Performance reports
Material requirements plan
Action notices
Priority reports
Capacity reports
Cost and price data
MRP explosion
Routings and time standards
Figure 11.16
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-41
Outputs from MRP
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-42
Outputs from MRP
J(4)
Seat-frame�boards
C(1)
Seat�subassembly
H(1)
Seat�frame
I(1)
Seat�cushion
BOM for the Seat Subassembly
Figure 11.17
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-43
Outputs from MRP
Item: Seat subassembly
Lot size: 230 units
Lead
time: 2 weeks
Gross requirements
150
1
230
117
2
3
120
4
5
150
6
120
7
8
Scheduled receipts
Projected on-hand inventory
Planned receipts
Planned order releases
37
Week
117
117
0
0
0
0
0
0
0
0
0
0
0
227
227
77
187
187
230
230
230
230
Figure 11.18
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-44
Outputs from MRP
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross requirements
1
0
2
3
4
5
6
7
8
Scheduled receipts
Projected on-hand inventory
Planned receipts
Planned order releases
40
Week
0
0
0
300
0
0
0
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross requirements
1
0
2
3
4
5
6
7
8
Scheduled receipts
Projected on-hand inventory
Planned receipts
Planned order releases
0
Week
0
0
0
0
0
0
0
Item: Seat subassembly
Lot size: 230 units
Lead
time: 2 weeks
Gross requirements
150
1
2
3
120
4
5
150
6
120
7
8
Planned receipts
Planned order releases
Week
0
0
0
0
230
230
230
230
Usage quantity: 1
Usage quantity: 1
0
230
0
230
0
230
0
0
230
0
Figure 11.18
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-45
Outputs from MRP
Item: Seat subassembly
Lot size: 230 units
Lead
time: 2 weeks
Gross requirements
150
1
2
3
120
4
5
150
6
120
7
8
Planned receipts
Planned order releases
Week
0
0
0
0
230
230
230
230
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross requirements
1
0
2
3
4
5
6
7
8
Scheduled receipts
Projected on-hand inventory
Planned receipts
Planned order releases
40
Week
0
0
0
300
0
0
0
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross requirements
1
0
2
3
4
5
6
7
8
Scheduled receipts
Projected on-hand inventory
Planned receipts
Planned order releases
0
Week
0
0
0
0
0
0
0
0
230
0
230
0
230
0
0
230
0
0
0
0
40
110
110
110
180
180
180
180
300
300
0
0
0
0
0
0
0
0
0
0
0
230
230
230
230
Figure 11.18
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-46
Outputs from MRP
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross requirements
1
2
3
4
5
6
7
8
Planned receipts
Planned order releases
Week
300
300
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross requirements
1
2
3
4
5
6
7
8
Planned receipts
Planned order releases
Week
230
230
230
230
0
0
0
0
230
230
0
0
0
0
0
0
230
230
0
0
Gross requirements
1
0
2
3
4
5
6
7
8
Scheduled receipts
Planned receipts
Planned order releases
200
Week
0
0
0
0
0
0
0
Projected on-hand inventory
Item: Seat-frame boards
Lot size: 1500 units
Lead
time: 1 week
Usage quantity: 4
1200
200
200
200
500
500
500
500
500
1500
1500
Figure 11.18
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-47
Application 11.5
A firm makes a product (Item A) from three components (intermediate Items B and D, and purchased item C).
The latest MPS for product A calls for completion of a 250-unit order in week 8, and its lead time is 2 weeks.
The master schedule and bill of material for Product A are on the following slides:
Item: End Item A | Lead Time: 2 wks | |||||||
Week | ||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
MPS quantity | | | | | | | | 250 |
MPS start | | | | | | 250 | | |
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-48
Application 11.5
Develop a material requirements plan for items B, C, and D, given the following inventory data.
C(2)
C(2)
B(1)
B(1)
C(1)
D(2)
A
Data Category | Item | ||
B | C | D | |
Lot-sizing rule | POQ (P = 5) | FOQ = 1000 | L4L |
Lead time | 2 weeks | 1 week | 3 weeks |
Scheduled receipts | None | 1000 (week 1) | None |
Beginning inventory | 0 | 800 | 0 |
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-49
Application 11.5
An item’s gross requirements cannot be derived until all of its immediate parents are processed.
Thus we must begin with Item D. Its only immediate parent is item A, and its planned “production plan” is shown by the MPS start row.
Item: D Lot Size: L4L Description: Lead Time: 3 weeks | ||||||||
| Week | |||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
Gross requirements | | | | | | | | |
Scheduled receipts | | | | | | | | |
Projected on-hand inventory 0 | | | | | | | | |
Planned receipts | | | | | | | | |
Planned order releases | | | | | | | | |
0
0
0
500
0
0
0
500
500
0
0
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-50
Application 11.5
We can do item B next, because the planned “production quantities” for its two immediate parents (A and D) are known.
Item C cannot be done yet, because one of its parents is item B, and its PORs are still unknown.
Item: B Lot Size: POQ = 5 Description: Lead Time: 2 weeks | ||||||||
| Week | |||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
Gross requirements | | | | | | | | |
Scheduled receipts | | | | | | | | |
Projected on-hand inventory 0 | | | | | | | | |
Planned receipts | | | | | | | | |
Planned order releases | | | | | | | | |
500
250
0
0
250
750
250
750
250
0
0
0
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-51
Application 11.5
Finally we can do Item C, because we now know the planned “production quantities” of both of its immediate parents (A and B).
Item: C Lot Size: 1000 Description: Lead Time: 1 week | ||||||||
| Week | |||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
Gross requirements | | | | | | | | |
Scheduled receipts | 1000 | | | | | | | |
Projected on-hand inventory 800 | | | | | | | | |
Planned receipts | | | | | | | | |
Planned order releases | | | | | | | | |
1500
250
300
300
300
300
300
50
50
50
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-52
Outputs from MRP
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-53
MRP and the Environment
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-54
MRP, Core Processes, and Supply Chain Linkages
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-55
MRP, Core Processes, and Supply Chain Linkages
External Suppliers
External Customers
Supplier
Relationship
Process
MPS
Order
Fulfillment
Process
MRP
Customer
Relationship
Process
New Service/Product Development Process
Bill of Materials
Supplier
Orders
Customer
Orders
Order
Promises
And
Due Dates
Supplier Schedules
(Planned Order Releases)
Figure 11.19
Adjustments to due dates of scheduled releases
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-56
Enterprise Resource Planning
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-57
Enterprise Resource Planning
Back-Office Processes Front-Office Processes
Human
Resources
Data Analysis
Sales and Marketing
Customer Service
Supply-Chain
Management
Accounting and Finance
Manufacturing
ERP System
Figure 11.20
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-58
Resource Planning for �Service Providers
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-59
Bill of Resources
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-60
Bill of Resources
Level 1
Discharge
Level 2
Intermediate care
Level 3
Postoperative care
(Step down)
Level 4
Postoperative care
(Intensive)
Level 7
Preoperative care
(Testing)
Level 5
Surgery
Nurse
(6 hr)
MD
(1 hr)
Therapy
(1 hr)
Bed
(24 hr)
Lab
(3 tests)
Kitchen
(1 meal)
Pharmacy
(10
medicines)
Level 6
Preoperative care
(Angiogram)
Level 6
Preoperative care
(Angiogram
Figure 11.21
Cumulative lead time, or the patient stay time at the hospital, across all seven levels for the entire duration of the aneurysm treatment is 10 days.
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-61
Bill of Resources
Day of the Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 |
Aneurysm Patient | 1 | 2 | 1 | 3 | 2 | 3 | 0 | 1 | 2 | 1 | 2 | 2 | 2 | 2 | 2 |
Table 11.1
The first 10 days of the projected departures represent actual patients who have started the process while the last 5 days are forecasts based on historical records.
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-62
Bill of Resources
Resources Required for Each Aneurysm Patient | Nurse Hours Required Per Day Per Patient | Beds Required Per Day Per Patient | Lab Tests Required Per Day Per Patient |
Level 1 | 0 | 0 | 0 |
Level 2 | 6 | 0 | 0 |
Level 3 | 16 | 1 | 4 |
Level 4 | 12 | 1 | 6 |
Level 5 | 22 | 1 | 2 |
Level 6 | 6 | 1 | 3 |
Level 7 | 1 | 0 | 0 |
Use the information above to calculate the daily resource requirements for treating aneurysm patients (similar to the gross requirements in a MRP record). Begin by calculating the number of patients that will be at each level (or stage) of treatment each day.
Table 11.2
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-63
Bill of Resources
Figure 11.22
As shown below, the aneurysm patient departures become the Master Schedule for Level 1 and these departures drive the need for resources at each level of the process.
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-64
Bill of Resources
Once we know how many patients will need each level of treatment on each day, we can multiply this demand by the amount of each resource required to treat them.
Example:
Total Number of Lab Tests Projected for Day 5
= [0(2) + 0(3) + 4(3) + 6(3) + 2(2) + 3(2) + 0(2)]
= 40
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-65
Bill of Resources
Day of the Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 |
Nursing Hours Required | 179 | 198 | 170 | 170 | 160 | 170 | 190 | 184 | 150 | 132 | 108 | 76 | 44 | 12 | 0 |
Beds required | 12 | 12 | 11 | 11 | 10 | 12 | 13 | 11 | 10 | 8 | 6 | 4 | 2 | 0 | 0 |
Lab Tests Required | 50 | 45 | 46 | 44 | 40 | 50 | 54 | 48 | 48 | 36 | 24 | 16 | 8 | 0 | 0 |
Table 11.3
The above table shows how much of each critical resource is required in total to treat aneurysm patients for the 15-day master schedule.
This table shows the resources needed from Day 1 to Day 15 for the current schedule.
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-66
Solved Problem 1
Refer to the bill of materials for product A shown below.
If there is no existing inventory and no scheduled receipts, how many units of items G, E, and D must be purchased to produce 5 units of end item A?
LT = 2
LT = 3
B (3)
C (1)
G (1)
LT = 3
LT = 3
LT = 3
D (1)
LT = 6
LT = 1
F (1)
LT = 1
A
Figure 11.23
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-67
Solved Problem 1
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-68
Solved Problem 2
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-69
Solved Problem 2
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-70
Solved Problem 2
Item: A | Order Policy: 50 units Lead Time: 1 week | |||||||||
| Week | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Forecast | 20 | 10 | 40 | 10 | 0 | 0 | 30 | 20 | 40 | 20 |
Customer orders (booked) | 30 | 20 | 5 | 8 | 0 | 2 | 0 | 0 | 0 | 0 |
Projected�on-hand�inventory | 25 | | | | | | | | | |
MPS quantity | 50 | | | | | | | | | |
MPS start | | | | | | | | | | |
Available-to-promise (ATP) inventory | | | | | | | | | | |
Quantity on Hand 5
Figure 11.24
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-71
Solved Problem 2
The projected on-hand inventory for the second week is
=
+
–
Projected on-hand�inventory at end�of week 2
On-hand�inventory in�week 1
MPS quantity�due in week 2
Requirements�in week 2
= 25 + 0 – 20 = 5 units
where requirements are the larger of the forecast or actual customer orders booked for shipment during this period. No MPS quantity is required.
Without an MPS quantity in the third period, a shortage of item A will occur: 5 + 0 – 40 = –35.
Therefore, an MPS quantity equal to the lot size of 50 must be scheduled for completion in the third period. Then the projected on-hand inventory for the third week will be 5 + 50 – 40 = 15.
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-72
Solved Problem 2
The MPS start row is completed by simply shifting a copy of the MPS quantity row to the left by one column to account for the 1-week final assembly lead time. Also shown are the available-to-promise quantities. In week 1, the ATP is
=
+
–
Available-to-�promise in�week 1
On-hand�quantity in�week 1
MPS quantity�in week 1
Orders booked up�to week 3 when the�next MPS arrives
= 5 + 50 – (30 + 20) = 5 units
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-73
Solved Problem 2
The ATP for the MPS quantity in week 3 is
=
–
Available-to-�promise in�week 3
MPS quantity�in week 3
Orders booked up�to week 7 when the�next MPS arrives
= 50 – (5 + 8 + 0 + 2) = 35 units
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-74
Solved Problem 2
Figure 11.25
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-75
Solved Problem 3
The MPS start quantities for product A calls for the assembly department to begin final assembly according to the following schedule:
A
B (1)
C (2)
D (1)
LT = 2
LT = 1
LT = 2
LT = 3
Figure 11.26
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-76
Solved Problem 3
INVENTORY RECORD DATA | |||
| | Item | |
Data Category | B | C | D |
Lot-sizing rule | POQ (P =3) | L4L | FOQ = 500 units |
Lead time | 1 week | 2 weeks | 3 weeks |
Scheduled receipts | None | 200 (week 1) | None |
Beginning (on-hand) inventory | 20 | 0 | 425 |
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-77
Solved Problem 3
Item: B | Lot Size: POQ (P = 3) Lead Time: 1 week | |||||||||
| Week | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Gross requirements | | 100 | | 200 | | 120 | 180 | 60 | | |
Scheduled receipts | | | | | | | | | | |
Projected�on-hand�inventory | 20 | 200 | 200 | 0 | 0 | 240 | 60 | 0 | 0 | 0 |
Planned receipts | | 280 | | | | 360 | | | | |
Planned order releases | 280 | | | | 360 | | | | | |
20
Figure 11.27
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-78
Solved Problem 3
Item: C | Lot Size: L4L Lead Time: 2 weeks | |||||||||
| Week | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Gross requirements | | 200 | | 400 | | 240 | 360 | 120 | | |
Scheduled receipts | 200 | | | | | | | | | |
Projected�on-hand�inventory | 200 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Planned receipts | | | | 400 | | 240 | 360 | 120 | | |
Planned order releases | | 400 | | 240 | 360 | 120 | | | | |
0
Figure 11.27
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-79
Solved Problem 3
Item: D | Lot Size: FOQ = 500 units Lead Time: 1 week | |||||||||
| Week | |||||||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Gross requirements | | 400 | | 240 | 360 | 120 | | | | |
Scheduled receipts | | | | | | | | | | |
Projected�on-hand�inventory | 425 | 25 | 25 | 285 | 425 | 305 | 305 | 305 | 305 | 305 |
Planned receipts | | | | 500 | 500 | | | | | |
Planned order releases | 500 | 500 | | | | | | | | |
425
Figure 11.27
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-80
Solved Problem 4
Pet Training Academy Process | Lead Time in Days |
Level 1: Departure Day | 1 |
Level 2: 3rd Day | 1 |
Level 3: 2nd Day | 2 |
Level 4: Arrival Day | 1 |
Total | 5 |
Table 11.5
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-81
Solved Problem 4
Pet Training Academy Process Resources Required | Training Coach (Hours) | Dog Dietician ( Hours) | Care Assistant (Hours) | Boarding Kennel (Hours) |
Level 1: Departure Day | 2 | 1 | 1 | 12 |
Level 2: 3rd Day | 3 | 1 | 2 | 24 |
Level 3: 2nd Day | 3 | 1 | 2 | 24 |
Level 4: Arrival Day | 2 | 1 | 1 | 12 |
Table 11.6
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-82
Solved Problem 4
Day of the month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Master Schedule of Trained Dogs | 5 | 2 | 2 | 8 | 3 | 0 | 1 | 8 | 4 | 3 | 6 | 0 |
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-83
Solved Problem 4
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-84
Solved Problem 4
Figure 11.28
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-85
Solved Problem 4
The previous table shows the number of dogs at each level during their stay at the Pet Training Academy.
The top row of each level shows the number of dogs who will advance to the next level at the end of the day.
The daily resource requirements for each resource required to train the departing dogs are shown in the following slide.
Total number of CA hours Projected for Day 2
[1(2) + 2(2) + 2(11) +1(0)] = 28 hours
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-86
Solved Problem 4
Day of the Month | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Training Coach Hours required | 52 | 43 | 39 | 44 | 41 | 45 | 59 | 55 | 35 | 24 | 12 | 0 |
Dog Dietician hours required | 20 | 15 | 14 | 20 | 16 | 16 | 22 | 21 | 13 | 9 | 6 | 0 |
Care Assistant hours required | 32 | 28 | 25 | 24 | 25 | 29 | 37 | 34 | 22 | 15 | 6 | 0 |
Boarding kennels hours required | 384 | 336 | 300 | 288 | 300 | 348 | 444 | 408 | 264 | 180 | 72 | 0 |
Number of Boarding Kennels required | 16 | 14 | 13 | 12 | 13 | 15 | 19 | 17 | 11 | 8 | 3 | 0 |
Table 11.7
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-87
Solved Problem 4
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-88
Solved Problem 4
Number of Employee Required per Day | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
Training Coaches | 7 | 6 | 5 | 6 | 6 | 6 | 8 | 7 | 5 | 3 | 2 | 0 |
Dog Dieticians | 3 | 2 | 2 | 3 | 2 | 2 | 3 | 3 | 2 | 2 | 1 | 0 |
Care Assistants | 4 | 4 | 4 | 3 | 4 | 4 | 5 | 5 | 3 | 2 | 1 | 0 |
Copyright ©2016 Pearson Education, Inc. All rights reserved.
11-89