SAP ERP MRP Planning
MRP Type
“V1”
Manual reorder point
with External Requirement
600
500
400
300
200
100
700
800
Fixed Lot Size 800
Safety Stock 200
1
2
3
4
5
6
7
8
900
1000
ROP 600
Replenishment Lead Time 6 days
MRP Type “V1” is similar to MRP Type “VB” and shares most of the similar characteristics except External Requirement Considerations.
See MRP Type “V1” here
ROP with External Requirements
Replenishment Lead Time for External Procurement
The system determines the replenishment lead time for a material procured externally by totalling number of days for the processing time for purchasing, the planned delivery time and the goods receipt processing time.
Scenario
ROP = 800
Replenishment Lead Time for External Procurement
The system determines the replenishment lead time for a material procured externally by totalling number of days for the processing time for purchasing, the planned delivery time and the goods receipt processing time.
Purchase Processing time + Planned Delivery Time +
GR Processing Time
= 1 + 5 + 1
= 7 days
Replenishment Lead Time for External Procurement
The system determines the replenishment lead time for a material procured externally by totalling number of days for the processing time for purchasing, the planned delivery time and the goods receipt processing time.
Purchase Processing time + Planned Delivery Time +
GR Processing Time
= 1 + 5 + 1
= 7 days
Which means any Customer Requirement or Manual Reservations beyond 7 days are NOT considered.
Firstly, we shall remove safety stock !!!
Manual Reservation created
Below ReOrder level
MRP run
Nothing Planned
Today is 14.09.2016
22.09.2016 is 8 days from today
(beyond 7 days Replenishment Lead Time)
Today is 14.09.2016, Reservation is changed to 16.09.2016 (within the 7 days Replenishment Lead Time)
Today is 14.09.2016, Reservation is now changed to 16.09.2016 (within the 7 days Replenishment Lead Time)
MRP run
Since Reservation is within the Replenishment Lead time of 7 days causing ROP to fall below 800, system triggers for Procurement of the Fixed Lot Size of 1000
Create a Customer Requirement of 1000 within the Replenishment Lead Time
The new requirement within the replenishment lead time cause the stock level projection below ROP again !
MRP run
Another PR of 1000 triggered
Both Customer Requiremeents and Manual Reservations are considered when it is within the Replenishment Lead Time