SAP Material Management
Purchasing
Confirmation Control Key
as Acknowledgement
(Supplier Acknowledgement)
Pre-requisite
If ony set this indicator without Confirmation Control Key, it is a Simple Acknowledgement
Using Confirmation Control key for Acknowledgement
You must SET BOTH in order to use Confirmation Control Key as Acknowledgement !
Pre-requisite
Configuration of Confirmation Control Key
eg: T-AB confirmation key for Acknowledgement
Example without Inbound (another ppt for scenario of Inbound)
Reference Date for Vendor Confirmation Monitoring Period
Date to which the time specified in the field Monitoring Period relates.
Examples
If you set the parameter to 'Delivery date minus monitoring period' and enter a value of 10 days as monitoring period, the confirmation must be received ten days before the delivery date. If no confirmation has been received prior to this point in time, this PO item will appear in the analyses for the monitoring and follow-up of confirmations.
Simple Acknowledgement Do not have this feature.
GR is referenced to each Confirmation
Once “AB” reported, GR possible
Once “AB” reported, it is udpated to S/R List
Pre-requisite
Today is 28.09.2016, Delivery Date is 3 days from today
10 days 1st reminder
Reminders days are defaulted from Purchasing Value Key
(IMG)
When creating Info Record, it will default from the Material Master Purchasing data view
Reminders dates from Material Master default to PIR, then from PIR defaulted to the PO
(IMG) Purchasing view General view Delivery TAB
Purchasing Value Key -> Material Master -> Info Record -> Purchase Order
Pre-requisite
Define
Output Control
Standard SAP delivered Output Type “AUFB” with Requirement 107 for Dunning purpose (if necessary define own Output Type with New Requirement ABAP logic to pick up the new Output Type based on additional conditions required by business)
Print Program
Form Routine
Form
for the Acknowledgement Output
Access Sequence 0001 assign tu AUFB
Tables (or Key Combinations) for the Access Sequence (you can define your own Table and Access Sequence for new key combinations depending on business requirements)
Pre-requisite
Create Condition Record for Output Type “AUFB”
Select a Key Combination for the Condition Record
Pre-requisite
PO must be Message Outputed
Pre-requisite
In this example, we shall be using
Monitor Order Acknowledgement
20.10.2016
01.10.2016
Monitoring Date (Reference Date)
PO Delivery Date
> 10 days Reminders in the PO
PO
Message Generated
SAVE Message to PO
After SAVE. you can check the Message Detail in ME92F
Output type for reminders in standard sap is “AUFB”
From ME92F, you can also navigate to the PO
“AUFB” waiting for Transmission
Pre-requisite
Ouput AUFB in ME9F
Message Outputed
Continue with the Confirmation Control processing
Supplier Acknowledge 2 partial deliveris
Reflected now in the MD04
Due to MRP Relevancy Indicator
GR is possible after Acknoledgement
Individual Confirmation of partial delivery show in the MIGO
Each partial confirmation is showed in the MIGO due to this config
GR the 80 confirmation line from the PO
BEFORE GR
AFTER GR
80 received into STOCK
AB-1
80 received