1 of 8

Bear Creek

Elementary

​

Community Construction Update

October 27, 2026

1

School Name

Presentation Title

Month/Day/Year

Additional Logos

Additional Logos

2 of 8

Overview

​

Community Construction Update | October 27, 2026

​

1

PART 1

Project

Reclassification

Understanding the shift from classroom additions to space-specific improvements.

PART 2

Current &

Additional Scope

Overview of current scope plus upcoming additional improvements.

PART 3

Anticipated

Project

Timeline

Start of work in Nov ‘26, current scope completion Jan ‘27, and additional scope completion Summer ‘27.

PART 4

Team + Q&A

Introduction of partners and stakeholders

3 of 8

Project Classification

​

Community Construction Update | October 27, 2026

​

2

ORIGINAL SCOPE

Classroom additions

Learning neighborhood expansion including studios (classrooms), art/music rooms, collaboration areas, and professional learning center.

UPDATED SCOPE

Safety, outdoor learning and other improvements

Focuses on exterior safety improvements, outdoor learning expansion, access control, site maintenance, and interior acoustic upgrades.

Why Did the Scope Shift?

Campus enrollment projections:

Immediate Campus Impact:

Current and projected enrollment at the campus does not support the need for classroom additions.

Bond funds will be used to support student safety, expanded outdoor learning/recreation, and dining hall comfort.

4 of 8

Current Scope

​

Community Construction Update | October 27, 2026

​

2

PURPOSE: COMMUNITY SAFETY

PURPOSE: STUDENT RECREATION

PURPOSE: OUTDOOR LEARNING EXPANSION

PURPOSE: ACCESS CONTROL

PURPOSE: EMERGENCY EGRESS

PURPOSE: GROUNDS MAINTENANCE

Removes existing barrier gates, patio fencing, and damaged fence panels to eliminate safety hazards.

Brush clearing, cleaning, and hydromulching within new fence line, tree protection, and silt fence removal to enhance outdoor recreation.

Install fencing along uphill side to expand playground space and secure campus boundaries.

Adds multiple vehicular gates and a new pedestrian gate to manage arrival/dismissal traffic flow and campus security.

Upgrades pedestrian gates with panic hardware, keyed exterior handles, and a designated Knox fire padlock gate.

Grind and smooth damaged sharp edges on existing limestone benches to restore safe outdoor seating.

Demolition & Removals

Site Prep & Clearing

New Fencing Installation

New Gates & Access Control

Hardware Retrofits

Site Repair

5 of 8

Site Plan

​

Community Construction Update | October 27, 2026

​

2

Additional Scope

Outdoor Learning Expansion

Limits of Construction

6 of 8

Additional Scope

​

Community Construction Update | October 27, 2026

​

2

Community & Student Benefit

Community & Student Benefit

Community & Student Benefit

Playground Stair & Ramp

Construction of a stair and ramp addition providing direct accessibility to the playground area.

Ensures safe, inclusive outdoor play and exercise access for all students, staff, and visiting families.

Cafeteria Acoustic Improvements

Acoustical treatments applied to cafeteria walls and ceilings to reduce reverberation and ambient noise.

Creates a quieter, lower-stress dining and gathering space for students, staff supervision, and events.

Additional Bike Racks

Installation of new bike racks in secure designated area near campus entrance.

Encourages active and environmentally friendly transit for students, staff, and neighborhood families.

7 of 8

Anticipated Schedule

Community Construction Update | October 27, 2026

​

7

Nov. 2026

STR Constructors mobilizes on campus to set up temp fencing, tree protection, and initiate site clearing.

​

Jan. 2027

Completion target for fencing, gate installations, access control retrofits, and site seating repairs.

​

Aug. 2027

Completion target for playground stairs/ramp, cafeteria acoustical treatments, and bike rack additions.

​

8 of 8

Team

Project Team Contact Information:

Community Construction Update | October 27, 2026

​

8