SAP Project System
03
Perform Cost Planning
You need to plan costs for your project. For an initial estimate of the costs to be expected, you want to perform rough cost planning for the individual parts of the project.
Perform rough cost planning for your project by using overall planning via CJ40
Task 1
Rough Cost Planning
Proj I/00##
Version 1
Version 0 usually set for ACTUALs, others for Simulation.
I/00##-1 $25,000 EUR
I/00##-2 $80,000 EUR
I/00##-3 $50,000 EUR
Plan the above cost on Level 2 WBS
The Planning is current set by YEAR. (and not by PERIOD)
Since Level 1 WBS Planned total is 0, the check will result in ERROR (but the Cost Planned can still be SAVED).
Current Annual Value 2018 Less then Plan Value Distributed.
To Roll-up Cost of Lower Level WBS to Upper Level WBS.
Cost Extrapolated to upper level WBS
Planned Total at upper level WBS has been extrapolated from lower levels.
Check Again
Since all lower level WBS Planned Costs is
Equal to or Less than the
highest level WBS Planned Total …
NEW Checked without errors
Evaluate the planning done using Plan/Actual/Variance hierarchy report
Task 2
Evaluate Planning
Click “arrow” to expand to lower level WBS
Actuals are obviously ZERO
at this moment !
Double-click
I/00##-1 WBS
Cost is broken down into Value Category but Current Planned Costs is not assigned to a Value Category. As a result the Planned Costs is not showered with Value Categories.
Now CLICK on
Value Category
Next, Double-click Period/Year
Note, report toggled to view by Period. The Costs are assigned to the current year, but not to individual periods. This is because the Current Cost is not by Period.