1 of 8

New Henry Clay High School

1

  • Completed/Work in Progress:
    • ICF placing and pouring, and the installation of IFAs at ICF walls is in progress.
    • Laying of CMU walls and the installation of hollow metal frames is underway.
    • Under-slab plumbing/electrical and concrete slabs are in progress.
    • Steel erection is underway in all areas.
    • Area D concrete roof structure is complete.
    • Above ceiling MEP installation is in progress at areas A,B and C.
    • Installation of stairs in all areas but the Gym is complete.
    • West driveway retaining wall construction is complete.
    • Interior metal stud wall & soffit framing in progress at Areas A, B & C.
    • Area A & Area B roofing is in progress.
    • Mechanical penthouse construction is in progress.
    • CMU finishing & painting, and hanging drywall is in progress at areas A & B.

  • Upcoming Look Ahead:
    • Continue site grading.
    • Continue with ICF walls, IFA frames, laying CMU walls and installing hollow metal frames.
    • Continue with under-slab plumbing and electrical at Areas F & C.
    • Continue pouring concrete slabs on grade at Areas F & C.
    • Continue with steel erection A, C, E, F and G.
    • Continue with above ceiling MEP installation at all areas.

A

B

C

D

G

E

F

Week Ending July 03, 2026

2 of 8

New Henry Clay High School

2

Areas A, B & C (Classroom Wings): Stone & Brick Veneer Masonry in Progress

Week Ending July 03, 2026

3 of 8

New Henry Clay High School

3

Level 1 Area G (Gym Lobby Entrance, Weight Room, ROTC & Health Classrooms): Stair G Installation is Complete with the Erection of Steel for the Curtain Wall in Progress

Week Ending July 03, 2026

4 of 8

New Henry Clay High School

4

Level 2 Area G (Media Center & Med Clinic): Floor Slab is Complete, ICF Walls & Framed Openings in Progress

Week Ending July 03, 2026

5 of 8

New Henry Clay High School

5

Level 2 Area G (Media Center & Med Clinic): Floor Slab & Stair G Installation is Complete, CMU Furring Walls are in Progress

Week Ending July 03, 2026

6 of 8

New Henry Clay High School

6

Area E (Gym): Concrete Floor Slab is Complete with South Locker Room CMU Walls in Progress

Week Ending July 03, 2026

7 of 8

New Henry Clay High School

7

Level 1 Area C (Cafeteria): Erection of Roof Structural Steel, ICF Construction at Cafeteria Perimeter Continues

Week Ending July 03, 2026

8 of 8

New Henry Clay High School

8

Area A Levels 1, 2, 3 (Classroom Wing): Painting of Hollow Metal Frames is in Progress

Week Ending July 03, 2026