Areas A, B & C (Classroom Wings): Stone & Brick Veneer Masonry in Progress
Week Ending July 03, 2026
New Henry Clay High School
3
Level 1 Area G (Gym Lobby Entrance, Weight Room, ROTC & Health Classrooms): Stair G Installation is Complete with the Erection of Steel for the Curtain Wall in Progress
Week Ending July 03, 2026
New Henry Clay High School
4
Level 2 Area G (Media Center & Med Clinic): Floor Slab is Complete, ICF Walls & Framed Openings in Progress
Week Ending July 03, 2026
New Henry Clay High School
5
Level 2 Area G (Media Center & Med Clinic): Floor Slab & Stair G Installation is Complete, CMU Furring Walls are in Progress
Week Ending July 03, 2026
New Henry Clay High School
6
Area E (Gym): Concrete Floor Slab is Complete with South Locker Room CMU Walls in Progress
Week Ending July 03, 2026
New Henry Clay High School
7
Level 1 Area C (Cafeteria): Erection of Roof Structural Steel, ICF Construction at Cafeteria Perimeter Continues
Week Ending July 03, 2026
New Henry Clay High School
8
Area A Levels 1, 2, 3 (Classroom Wing): Painting of Hollow Metal Frames is in Progress