LArPix and Related Developments in �Scalable Electronics for Noble Liquid Detectors
Dan Dwyer (Berkeley Lab)
CPAD 2026
22 Oct 2026
3D LArTPC Readout Concept: LArPix
D. Dwyer | LArPix
2
22 Oct. 2026
Concept:
- Use grid of charge-collecting
pixels/pads for anode
- Uniquely identify signals on
each pixel
- Provides true 3D imaging of
TPC ionization
Technical Challenges:
High channel density:
O(100k) pixels/m2 of anode area
Low noise:
<1000 e- equivalent noise charge (ENC)
Low power / Cryo-compatible:
Stringent limits on heat load in cryogenic environment, O(10) W/m2
Electronics behavior stable & predictable at LAr temp (87 K)
Digital multiplexing:
Must reliably transmit O(10k) pixel signals through few wires
Scalability:
Design and production method must scale to ~107 pixels
to be viable for the DUNE Near Detector
3D Pixel TPC
10k-channel LArPix prototype pixel anode tile
LArPix Concept
D. Dwyer | LArPix
3
15 Sep. 2026
Approach: Integrating Amplifier with Self-triggered Digitization and Streaming Readout
Front-end amplifier
Self-triggering Discriminator
O(100) keV threshold
SAR Digitizer
Digital Control
Achieve low power: avoid digitization and readout of mostly quiescent data.
Typical hit cycle time:
2.6 us (~4mm drift)
LArPix and The DUNE Liquid Argon Near Detector (ND-LAr)
D. Dwyer | LArPix
4
22 Oct. 2026
LBNF Beam Pulse Simulation in ND-LAr (May 2025)
(DUNE Work-in-Progress)
Neutrino Pileup:
- LBNF beam intensity results in O(100) interactions visible in ND-LAr per 10μs beam pulse.
(Compare to ionization readout time of ~300μs and scintillation readout time of ~10ns)
Pileup Mitigations:
- Optically segmented (70 regions) with ~30% optical coverage per segment
- Native 3D pixelated ionization readout → 14M LArPix channels
Engineering
model of
ND-LAr
detector
DUNE ND-LAr Prototype: 2x2 Demonstrator
D. Dwyer | LArPix
5
22 Oct. 2026
Description:
- Four mid-scale Pixelated LArTPC modules, 2.4 tons total, >300k pixels
- Includes upstream/downstream steel/scintillator trackers,
repurposed from MINERvA experiment
- Located in underground hall in NuMI neutrino beam at FNAL
Run #1: First antineutrinos July 8-12, 2024
- Collected initial ~40k antineutrino interactions in 4.5 days
Run #2: Tuning and Calibration Studies Oct-Dec, 2025
- Improved tuning of pixel and scintillation light readout systems
- Performed Calibrations:
- External sources: 22Na, 60Co, 88Y, AmBe, DT Generator
- 220Rn injection
Run #3: Return of the NuMI neutrino beam Oct. 2026 → 2027
- Detector refilled/recommissioned over past month
- Neutrino beam returned yesterday (Oct. 21).
- Expect beam through early 2027 (~2 x 1020 protons-on-target)
Operation of a Modular 3D-Pixelated Liquid Argon Time-Projection Chamber in a Neutrino Beam
Instruments 2026, 10(1), 18
Performance of a Modular Ton-Scale Pixel-Readout Liquid Argon Time Projection Chamber
Instruments 2024, 8(3), 41
Example antineutrino
interactions on argon
imaged in true 3D
during Run #1
ND-LAr Full-Scale Demonstrator @ Univ. of Bern
D. Dwyer | LArPix
6
22 Oct. 2026
Full-Scale Demonstrator:
- Built/operated first full-sized ND-LAr TPC module in late 2024
- Used 40 LArPix-v2d tiles, >400k pixels
Example cosmic ray images
Developments in System Reliability: Hydra-I/O
D. Dwyer | LArPix
7
22 Oct. 2026
Designed for robust I/O and control architecture
Difficult to access & repair electronics within large LAr cryostats
Hydra-I/O prevents tile failure due to single-chip errors
- I/O can occur between any neighboring chips on pixel tile
- Network is built by programming I/O connections between neighboring ASICs
Successfully exercised with LArPix-v2 chip in 2x2 Demonstrator Program
Upstream configuration commands
Downstream data flow
Example: 5 x 5 Pixel Tile
Four chips have direct off-tile I/O channels
(10 MHz, < 7 m)
Network reconfigured to avoid failed ASIC
Example failed chip.
Major Lessons from the LArPix-v2 Era
D. Dwyer | LArPix
8
22 Oct. 2026
Cryo-compatibility
- Established a design that meets requirements for cryo-operation (performance at 87 K, heat management to avoid boiling LAr)
- Vast majority of performance quality issues identified at room temp; few new problems emerge at LAr temp
Reliability
- System design sufficiently reliable to field two multi-ton LArTPCs
- Hydra-I/O successfully mitigates issues from problematic chips and unreliable I/O channels
Scalability
- Demonstrated a scalable design, fully produced by leveraging standard ASIC and PCB production processes.
- Developed testing program, identifying areas for improvement in advance of production
- Achieved target of O(10) cents per channel for full-system production cost
Signal Fidelity:
- Refined anode grounding to mitigate microphonic-related noise at tile-to-tile boundaries
- Must consider small (but non-negligible) signals from ionization e- collected by other pixels
- Need 10-bit ADC in order to reduce quantization noise (250 e- least-significant-bit) and capture 250k e- maximum signal.
LArPix-v3: Honing in on the ND-LAr final design (2025-2026)�
D. Dwyer | LArPix
9
22 Oct. 2026
v3 Strategy:
- Multiple minor iterations in quick succession
to accelerate pace of prototype-based verification
Increase the LArPix dynamic range:
v3a:
- Replace the 8-bit SAR ADC with a 10-bit SAR
- Differential: Meets power & performance targets in smaller area
- Asynchronous: Faster conversion time than synchronous architecture
- Results: 10-bit ADC successful, with only minor issues with analog-digital handoff
v3b:
- Addressed analog-digital handoff (FIXED)
v3c:
- Add Single-to-Differential (S2D) buffer to match AFE output to ADC input
Resolve issues with data loss:
v3b: Restructure digital core to simplify internal state machines. -> More significant re-write than originally planned.
- Results: Simplified code, but did not resolve data loss (insufficient validation of significant RTL revision)
v3c: Minor refinements of digital core to fully address data loss.
- Implemented much more significant design verification, code coverage now ~90%; one new subtle bug identified and resolved.
- Completing top-level integration, final verification
Final (v3c) channel structure
← We are here
LArPix-v3c: Improvements in ASIC Design Verification
D. Dwyer | LArPix
10
22 Oct. 2026
Core Verification: T. Prakash, P. Zarkos, K. Papadopoulou, D. Gnani (LBNL Eng Division); J. Hoff (FNAL)
- Relies on targeted test design and execution using traditional ASIC design toolkits
- Digital: Constrained-random test bench
- Single-chip and 3x3 multi-chip test bench environments
- Implemented code coverage and functional coverage tracking
- Daily automated regression test suite
- Analog & Mixed Signal:
- 4-corner simulation of gain, BW, phase margin, noise, and power for key amplifier and buffer blocks
- Mixed signal channel simulation with analog and compiled RTL
- Full analog-on-top chip-level simulation
New FPGA-based Verification: N. Patras (LBNL Computing Division)
- Implement LArPix digital design on an FPGA
- 3 x 3 network of LArPix ASICs in a single FPGA
- Enables higher-speed execution of subset of LArPix digital tests
- Identified rare deadlock issue in v3c design, and verified fix
New RTLSwarm Verification: K. Gosine, Y. Mei (UTA)
- Implements clock-accurate RTL model of LArPix on a CPU, with inter-chip communication parallelized on a CPU cluster
- Enables digital tests of full-sized network of LArPix ASICs (160 chips)
- Independently identified v3b data loss issues, and verified v3c fixes
See CPAD talk by K. Gosine!
Joint with NIFTY program (see upcoming slide)
Pixelating a DUNE Far Detector
D. Dwyer | LArPix
11
22 Oct. 2026
Goal
Demonstrate LArPix ‘Charge Readout Plane’
compatible with DUNE Far Detector design
LArPix in CERN NP02 ‘Cold Box’:
- Install 3m x 3.4m LArPix anode (614k pixels)
in CERN Vertical Drift Cold Box
- Demonstrate performance and interfaces
- Target: Collect ~1 week of cosmic ray
test data in Nov. 2026
Next Step: ProtoDUNE Run-III
- Install LArPix anode in ProtoDUNE,
operate in ~2029
- Develop MADCAP cryo-data
multiplexer
- Endorsed by DUNE Collaboration
DUNE Vertical-Drift Far Detector Design (~15 kton)
ND-LAr: 14M channels
Pixel FD: ~100M channels
Pixel Tile Installation on Composite Frame
(@ CERN Neutrino Platform)
CERN Detector R&D 2 (Liquid Detectors): WP 4.3, Task G2.D2
Composite Frame Assembly (@Univ. of Bern)
and Cryo-test (@ Grenoble)
See CPAD talk
by R. Huang!
MADCAP-v1 Cryo-Multiplexer ASIC
(in collab with INFN M-B)
Pixel TPC Kits supporting Detector R&D
D. Dwyer | LArPix
12
22 Oct. 2026
Fabricated multiple TPC kits in support of distributed R&D:
- Small kit: 15 cm x 15 cm anode, 10 cm drift, 1600 pixels
- Large kit: 32 cm x 48 cm anode, 48 cm drift, 10k pixels
- Both include complete readout system
- Requires: Cryogenics system with sufficient e- lifetime
Recent Applications:
- Validation tests of LArPix-v3 ASIC (@ Berkeley Lab)
- Tests of photosensitive dopants (@ Fermilab)
- Development of Radon injection for calibration (@ CSU)
- Test of UV-laser calibration (@SLAC)
- Prototyping of anode shield plane for signal shaping
(@ Berkeley Lab)
Large (10k-pixel) TPC Kit
Small (1.6k-pixel) TPC Kit
Large Kit
installed in
test cryostat
@ LBNL
CERN DRD2:
WP 4.3, Task G1.D3
TPC Kit Example: Anode Shield R&D
D. Dwyer | LArPix
13
22 Oct. 2026
Prototype Shield Plane
(from HKUST)
on 1.6k-pixel Tile
Data shows expected sharpening of time profile of integral charge on pixel from muon tracks
No Shield
With Shield
Goal:
Reduce signal induction from e- drift to very near field (few-mm)
- Significant pre-triggering observed during very large particle showers
Details:
- Add copper-clad & perforated PCB in front of anode tile
- Bias to ~-1 kV to ensure ionization e- collected on anode
Key Challenges:
- HV discharge risk, leakage currents, scalable manufacturing
Pretriggering during
large cosmic shower in
2x2 Demonstrator
TPC Kit Example: Radon Injection R&D
D. Dwyer | LArPix
14
22 Oct. 2026
Purpose:
- Facilitate full-volume detector calibration using 220Rn daughters
- Longest-lived unstable daughter: 212Pb, t½ = 10.6 hours
- Effort driven by Mooney group at CSU
Process:
- Developed and validated the injection system using large TPC kit at CSU
- Successfully used the injection system during Run #2 of the 2x2 Demonstrator
DUNE Work-in-progress
LArPix Variants: LightPix
D. Dwyer | LArPix
15
22 Oct. 2026
LArPix Platform:
Provides scalable readout electronics system
for detectors with O(10) to O(107) channels
LightPix:
- Highly-granular cryo-compatible scalable SiPM readout
- Designed for high-channel counts, low occupancy
- LightPix-v3: captures arrival time with sub-ns precision
and integral intensity measurement (over ~1 us)
- Collaborating with MIT and Univ. of Bern for testing
HPK SiPM Dark Count Spectrum
vs Bias Voltage
TDC resolution
and linearity < 1 ns
CERN DRD2: WP 4.3, Task G2.D4
LIghtPix-v3
Channel Diagram
LIghtPix-v3 ASIC
GHe neutron detector with
300-channel LightPix Readout
(McKinsey Group, UC-Berkeley)
LArPix Variants: QPix and NIFTY
D. Dwyer | LArPix
16
22 Oct. 2026
LArPix Platform:
Provides scalable readout electronics system
for detectors with O(10) to O(107) channels
QPix:
- Charge-replenishment based front-end, in collab with
QPix team (UTA, et. al.)
- Exploring integration of QPix front-end into LArPix system
NIFTY:
- Hardware AI: Network Intelligence for Fault Tolerance
- Exploring novel techniques for dynamic data routing
- Simulated expected data loads/profiles
- Explored candidate algorithms for
adaptive data routing
- ASIC design launched, targeting prototype
later this year
Simulated data flow
through Hydra-I/O
network of LArPix chips
CERN DRD2: WP 1, Task G1.D1
Simulated peak
loads on LArPix
memory buffers
during DUNE
beam pulse.
QPix charge-replenishment
front-end concep
QPix pulse-train signal reconstruction
See CPAD talks by R. Carney, T. Heim,
and posters by C. Ceravolo, D. Fellers!
LArPix Development Team
D. Dwyer | LArPix
17
22 Oct. 2026
Summary
D. Dwyer | LArPix
18
22 Oct. 2026
LArPix:
- True 3D pixelated charge readout for LArTPCs
- Low-noise, low-power, cryogenic-compatible
- Self-triggering:
- 100% live, independent of light system
- Inherently low data volumes (no signal from inactive pixels)
- Suitable for rare, low-energy physics searches
- Scalable anode design leverages commercial fabrication
- ~1 million channels deployed in two multi-ton prototypes
- Finalizing the design for use in the DUNE Near Detector
Related Efforts:
- DUNE Phase-II:
- Exploring adaptation for use in future DUNE Far Detector
- 600k-pixel prototype to operate at CERN this summer
- Pixel LArTPC Kits: Supporting generic detector R&D
- LightPix: Scalable cryo-compatible readout for SiPMs
- NIFTY: Adaptive data routing for improved reliability
Potential technologies for
future high-granularity detectors
LArPix-v3 ASIC
LightPix-v3 ASIC
GHe detector
w/LightPix
Readout
10k-pixel tile
10k-pixel
TPC Kit
Antineutrinos in true 3D
Pixel Detector R&D
for DUNE Phase II