1 of 77

Crane and Lifting Safety

(For Rigger and Operator)

2 of 77

Training Outline

  • Introduction
  • Personal Protective Equipment (PPE)
  • Manual Lifting Safe Practices
  • Crane Lifting Safe Practices
  • Lifting Equipments Safe Practices
  • Lifting Near Power Line
  • Rigging and Slinging
  • Lifting Equipments
  • Wear & Damage of Rigging Equipments
  • Static Line
  • Pipe Rigging Incident-1
  • Pipe Rigging Incident-2

2

3 of 77

Introduction

  • Lifting is very common in the construction industry as a method for material transfer. Through mechanical means such cranes, lifting equipment and manual handling.
  • The risk of injury can be reduced through training and application of correct lifting & handling techniques.

3

4 of 77

Personal Protective Equipment (PPEs) worn by Riggers

4

5 of 77

5

Improper manual lifting can result in a variety of occupational injuries, i.e. musculoskeletal injuries, cumulative trauma disorders hernia, and most common – back injuries which can even lead to a permanent partial or total disability. Avoidance of these expensive and most often debilitating injuries requires maximum awareness on proper body mechanics and correct lifting techniques.

Manual Lifting Safe Practices

6 of 77

DW-HSE-TM036

6

Basic points in proper lift:

  • Firm grip
  • Back straight
  • Arms & load close to the body
  • Feet apart

Manual Lifting Safe Practices

7 of 77

7

Two – Man Carry

Two – Man Pole Lift

Manual Lifting Safe Practices

8 of 77

8

Keep an eye on the load

Keep all parts of your body out from the load

Keep the load low & slow

Crane Lifting Safe Practices

9 of 77

9

Crane Lifting Safe Practices

10 of 77

10

Crane Lifting Safe Practices

11 of 77

11

Crane Lifting Safe Practices

12 of 77

12

Crane Lifting Safe Practices

13 of 77

13

Crane Lifting Safe Practices

14 of 77

14

Crane Lifting Safe Practices

15 of 77

15

Crane Lifting Safe Practices

16 of 77

16

Pay attention to the boom sections . . they should be kept EQUAL. Unequal boom give NO structural stability.

Crane Lifting Safe Practices

17 of 77

17

Pay attention to the remaining rope between the hoist block and boom tip, while raising the load. . . Prevent two-blocking !

Crane Lifting Safe Practices

18 of 77

18

When visibility is Poor. .

NO Lifting! No Crane Work!

Crane Lifting Safe Practices

19 of 77

19

Signal man should position in full view of the operator!

Signal man

Crane Lifting Safe Practices

20 of 77

20

Lifting Equipments Safe Practices

21 of 77

21

Lifting Equipments Safe Practices

22 of 77

22

Lifting Equipments Safe Practices

23 of 77

23

Lifting Equipments Safe Practices

24 of 77

24

Never take chance,

know and observe Absolute Limit of Approach!

Lifting Near Power Line

25 of 77

25

  • Use signalman near power line!

Lifting Near Power Line

26 of 77

26

Point of tangency

OK

Extra Localized Stress

Do not force the choked eye down close to the load

NO

Rigging and Slinging

27 of 77

27

If L is greater than S, then sling angle is OK

60O Lifting Angle

Lifting Angles (in between legs):

60O – Safest (most recommended)

40O – Minimum

90O - Maximum

S

L

L

S

Rigging and Slinging

28 of 77

28

Rigging and Slinging

29 of 77

29

Single Basket Hitch

with Inclined legs

Single Basket Hitch

Single Chocker Hitch

Single Vertical Hitch

Or Straight pull

Rigging and Slinging

30 of 77

30

Rigging and Slinging

31 of 77

31

Rigging and Slinging

32 of 77

32

Rigging and Slinging

33 of 77

33

  • The tension on sling leg depends on its angle to the load and the weight of the load to be lifted

Rigging and Slinging

34 of 77

34

  • When a multi leg sling is used with the sling legs at an angle, the load (tension) in the individual slings will increase as the angle between the legs becomes greater

Rigging and Slinging

35 of 77

35

Rigging and Slinging

36 of 77

36

Rigging and Slinging

37 of 77

37

Rigging and Slinging

38 of 77

38

Rigging and Slinging

39 of 77

39

Rigging and Slinging

40 of 77

40

Rigging and Slinging

41 of 77

DW-HSE-TM036

41

Rigging and Slinging

42 of 77

42

Rigging and Slinging

43 of 77

43

Rigging and Slinging

44 of 77

44

Rigging and Slinging

45 of 77

45

Rigging and Slinging

46 of 77

46

Rigging and Slinging

47 of 77

47

Rigging and Slinging

48 of 77

48

Rigging and Slinging

49 of 77

49

Rigging and Slinging

50 of 77

50

Rigging and Slinging

51 of 77

51

Lifting Equipments

52 of 77

52

Lifting Equipments

53 of 77

53

Lifting Equipments

54 of 77

54

Lifting Equipments

55 of 77

55

Lifting Equipments

56 of 77

56

Lifting Equipments

57 of 77

57

Lifting Equipments

58 of 77

58

Lifting Equipments

59 of 77

59

Wear & Damage of Rigging Equipment

60 of 77

60

Wear & Damage of Rigging Equipment

61 of 77

61

Wear & Damage of Rigging Equipment

62 of 77

62

Wear & Damage of Rigging Equipment

63 of 77

63

Wear & Damage of Rigging Equipment

64 of 77

64

Wear & Damage of Rigging Equipment

65 of 77

65

Wear & Damage of Rigging Equipment

66 of 77

66

Wear & Damage of Rigging Equipment

67 of 77

67

Wear & Damage of Rigging Equipment

68 of 77

DW-HSE-TM036

68

Wear & Damage of Rigging Equipment

69 of 77

DW-HSE-TM036

69

Static Line

Double wrap

or w/ a stable

Stopper

immediately

below the rope

(e.g. pair of

beam clamp)

70 of 77

70

Pipe Rigging Incident - 1

71 of 77

71

Pipe Rigging Incident - 1

72 of 77

72

Pipe Rigging Incident - 1

73 of 77

73

Pipe Rigging Incident - 2

74 of 77

74

Pipe Rigging Incident - 2

75 of 77

75

Pipe Rigging Incident - 2

76 of 77

76

Pipe Rigging Incident - 2

77 of 77

Summary

Prior to any lifting operation taking place the following must be performed

  • Assess the lifting task to identify and reduce the risk that may be inherent in the operation
  • Where possible, eliminate the need to carry out the manual handing operation and resort to mechanical lifting operation
  • Where risk is identified, implement mitigation measure to reduce the risk
  • Consideration must be given to weight of the load, location of lifting area, equipments to be use and personnel competency

77