PRESENTATION ON
Bramhayani Hydropower Project – 36.50MW
(Sindhupalchok, Nepal)
Presented by :
Narayan Poudel, CA
(Financial Analyst)
And
Er. Subash Chandra Baral – Technoquarry Consults Pvt. Ltd
May 2022
Project Location :
28o 01’ 24″ N to 28o 04′ 16″ N Latitude 85o44′38″ E to 85o47′30″ E Longitude |
Location:
Jugal Rural Municipality,
Sindhupalchowk District, Bagmati Pradesh
Bramhayani HEP
Licensed area VDCs (Golche and Gumba)
Project Location :
Golche
Gumba
PROJECT LOCATION :
Road Access
Kathmandu- Balephi = 72 Km
Balephi – Kartike = 1 8 Km
Kartike – Nyasem = 15 Km
Nyasem – Tembathan = 6 Km
Tembathan - Ladanbesi = 7 Km
Access Road required constructing for
Project Area is 15 Km
PROJECT UNDER BALEPHI BASIN :
Bramhayani HPP 35.47 MW
Upper Bramhayani HPP 15.15 MW
TECHNICAL INFORMATION
Project Location :
28o 01’ 24″ N to 28o 04′ 16″ N Latitude 85o44′38″ E to 85o47′30″ E Longitude |
Location:
Jugal Rural Municipality,
Sindhupalchowk District, Bagmati Pradesh
Bramhayani HEP
PROJECT UNDER BALEPHI BASIN :
Bramhayani HPP 35.47 MW
Upper Bramhayani HPP 15.15 MW
Licensed area VDCs (Golche and Gumba)
Project Location :
Golche
Gumba
Project Components Overview- Topo Map
28° 04' 16" N
85° 47' 30" E
28° 01' 24" N
85° 44' 38" E
Headworks
Headrace Pipe
Headrace Tunnel
Surge Tank
Powerhouse
Headworks
Headrace Tunnel
Underground Powerhouse
Underground Surge Tank
Underground Penstock
Connecting
Arrangement
Overall Project Components Overview- Google Map
Upper Brahmyani HPP
Brahmyani HPP
Connecting Alignment from Upper Brahmyani (D-1.8m, L=863m)
Weir, 22m long, EL. 2623.50 m)
Desander: Underground, 2Nos. (59m X 7m X 9.97m)
Brahmyani headrace Tunne Junction (EL.2616m)
Powerhouse(EL.2632.50m)
Headrace tunnel ( size= D-shaped, 3.2 X 3.5 m, L=5785m)
Adit -1( size= D-shaped, 3.2 X 3.5 m, L=235m)
Adit -2( size= D-shaped, 3.2 X 3.5 m, L=253m)
Surgetank (Underground, 5m H=37 m)
Horizantal Pressure shaft
Size= 3.2 X 3.5 m , L=460 m
Incline Pressure shaft
D= 3.5m , L=636 m
Powerhouse (Underground, 54m X15.4m X16.6m)
Turbine Axis= El. 2027.78m
Project Components - Google Map
Connecting Alignment from Upper Brahmyani (D-1.8m, L=863m)
Weir, 22m long, EL. 2623.50 m)
Desander: Underground, 2Nos. (59m X 7m X 9.97m)
Brahmyani headrace Tunne Junction (EL.2616m)
Powerhouse(EL.2632.50m)
Headrace tunnel ( size= D-shaped, 3.2 X 3.5 m, L=5785m)
Adit -1( size= D-shaped, 3.2 X 3.5 m, L=235m)
Adit -2( size= D-shaped, 3.2 X 3.5 m, L=253m)
Surgetank (Underground, 5m H=37 m)
Horizantal Pressure shaft
Size= 3.2 X 3.5 m , L=460 m
Incline Pressure shaft
D= 3.5m , L=636 m
Powerhouse (Underground, 57.00m X12.89m X17.47m)
Turbine Axis= El. 2027.78m
Detailed Project Components - Google Map
Upper Brahmyani Powerhouse EL. 2632.50
Upper Brahmyani tailrace
Connecting alignment (D=1.8 m , L=863m
Brahmyani Headrace Connection. EL. 2616m
Brahmyani Headworks
Project Components - Google Map- Junction Details
Underground Powerhouse( size= 57.00m X 12.89m X 17.470m, Turbine axis=EL.2027.78 m
Switchyard
= 50 m X 30m
Tailrace, D Shaped, 3.2 X 3.5 m,
L= 343m
Main Access tunnel, D Shaped,
6.0 X 5.0 m, L= 320m
Adit-4, D Shaped, 3.2 X 3.5 m,
L= 248m
Adit-3, D Shaped, 3.2 X 3.5 m,
L= 305m
Surgetank= D=5m, H=37m
Inclined pressure shaft-2
D=3.5m, L=355m
Inclined pressure shaft-1
D=3.5m, L=281m
Project Components Profile- Google Map
Underground Powerhouse( size= 57.00m X 12.89m X 17.47m, Turbine axis=EL.2027.78 m
Switchyard
= 50 m X 30m
Tailrace, D Shaped, 3.2 X 3.5 m,
L= 343m
Main Access tunnel, D Shaped,
6.0 X 5.0 m, L= 320m
Adit-4, D Shaped, 3.2 X 3.5 m,
L= 248m
Adit-3, D Shaped, 3.2 X 3.5 m,
L= 305m
Surgetank= D=5m, H=37m
Inclined pressure shaft-2
D=3.5m, L=355m
Inclined pressure shaft-1
D=3.5m, L=281m
Project Components - Google Map
Adit -1( size= D-shaped, 3.2 X 3.5 m, L=235m)
Adit -2( size= D-shaped, 3.2 X 3.5 m, L=253m)
Headrace Tunnel( size= D-shaped, 3.2 X 3.5 m, L=5785m)
Inclined pressure shaft-2
D=3.5m, L=355m
Inclined pressure shaft-1
D=3.5m, L=281m
Project Components Profile- Google Map
2000m
1900m
1785m
PROJECT LAYOUT – CONTOUR MAP
PROJECT GROUND PROFILE
Headrace tunnel
Underground Desander
Feeder Tunnel
Weir/Intake & Gravel Trap
HRT Adit-1
HRT Adit-2
Surge Shaft
Pressure Shaft
Powerhouse
Tailrace canal
HRT Adit-3
PROJECT STRUCTURES
Headworks
Headworks
asasasasasasasasasass
Crest EL. 2623.50m, L=22m
Headworks
asasasasasasasasasass
Desander Basin
asasasasasasasasasass
H
Desander= Underground, 2 bays,59.0m, 7.0m X 9.97m
Desander Basin
asasasasasasasasasass
Desander= Underground, 2 bays,59.0m, 7.0m X 9.97m
Pressure Shaft Alignment
asasasasasasasasasass
Surgetank, D=5.0m, H=37m
355m
281m
Powerhouse layout
Main Access Tunnel= Size= 5.0m X 6.0 m, H=319m
Powerhouse= Size 53.0 X 15.40.0 m, X 16.64m
Tailrace= L=343m, 3.2 *3.5m
Powerhouse layout
Turbine Axis= EL. 2027.78
Powerhouse Layout
Technical Sailent Feature
Intake Lagan Khola | 1. Lagan Khola
|
2. Cascade arrangement to tap tail water from Power House of Upper Bramhayani HEP | |
Gravel Trap | 1. Lagan Khola
|
Settling Basin |
|
Headrace Tunnel |
|
Technical Sailent Feature
Adit Tunnel 1. Adit Tunnel - I 2. Adit Tunnel - II 3. Adit Tunnel - III 4. Adit Tunnel - IV | 1. Adit Tunnel-I
|
2. Adit Tunnel-II
| |
3. Adit Tunnel-III
| |
4. Adit Tunnel-IV
| |
Surge Shaft |
|
Technical Sailent Feature
Horizontal Shaft 1. Horizontal Shaft – I 2. Horizontal Shaft – II 3. Horizontal Shaft - III | 1. Horizontal Shaft-I
|
2. Horizontal Shaft-II
| |
3. Horizontal Shaft-III
| |
Inclined Shaft 1. Inclined Shaft - I 2. Inclined Shaft - II | 1. Inclined Shaft-I
|
2. Inclined Shaft-II
| |
Powerhouse |
|
Switchyard | - Size; (50m x 30m) (L x B) |
Tailrace Canal |
|
Technical Sailent Feature
Turbine |
|
Generator |
|
Transmission Line |
|
GEOLOGY
Geology
Geology
WEIR AXIS AREA�
Weir Axis
Geology
Outlet of Sand Flushing:
Geology
INLET PORTAL AREA�
Inlet Portal
Geology
TUNNEL ALIGNMENT�
Tunnel Alignment
Rock Class
Class II= 35%
Class III= 35%
Class IV= 20%
Class VI=10%
Geology
Adit Portal
Surge Shaft Adit Tunnel
Surge tank
Geology
Powerhouse and Penstock
Main Access Tunnel Portal (320m)
Pressure Shaft
Power House 200m Inside
Tailrace Portal
355m
281m
Geology
Seismicity�
Geology
Geology
Construction survey material
Geology
Geology
Geology Feature of Project
Geology
Geology
Risks/Challenges
Fig :- Landslide at the Gang Kharka Kholsi
Geology
Hydrology
Nyamya Masal Khola
A=110.63 KM2,
Qd=4.02 m3/s
Lagan Khola
A=86.08 KM/m2
Qd= 3.93m3/s
Headworks
Powerhouse
Waterways
Drainage Distributions In Elevation
<3000m = 1%
3000-5000m = 65%
>5000m= 35%
Hydrology
Catchment area Design flood | 196.71km2 7.95 m3/s |
Mean monthly flow |
Flow duration curve |
Probability of Exceedance % | Nyamya Masal Khola | Lagan Khola | Total |
5 | 57.48 | 44.92 | 102.41 |
10 | 41.09 | 31.67 | 72.76 |
15 | 33.43 | 25.69 | 59.12 |
20 | 27.18 | 20.84 | 48.02 |
25 | 23.30 | 18.10 | 41.41 |
30 | 17.52 | 13.67 | 31.19 |
35 | 11.62 | 8.96 | 20.58 |
40 | 8.58 | 6.58 | 15.16 |
45 | 6.62 | 5.05 | 11.67 |
50 | 5.38 | 4.10 | 9.48 |
55 | 4.71 | 3.58 | 8.29 |
60 | 4.05 | 3.07 | 7.12 |
65 | 3.46 | 2.50 | 5.96 |
70 | 3.31 | 2.50 | 5.81 |
75 | 3.07 | 2.31 | 5.38 |
80 | 2.78 | 2.09 | 4.87 |
85 | 2.50 | 1.87 | 4.37 |
90 | 2.46 | 1.78 | 4.24 |
95 | 2.08 | 1.57 | 3.65 |
100 | 1.45 | 1.20 | 2.65 |
Month | Discharge (m3/s) |
Baisakh (Apr/May) | 6.12 |
Jestha (May/Jun) | 17.79 |
Ashadh (Jun/Jul) | 56.89 |
Shrawan (Jul/Aug) | 81.34 |
Bhadra (Aug/Sep) | 66.82 |
Ashwin (Sep/Oct) | 39.02 |
Kartik (Oct/Nov) | 18.69 |
Mangsir (Nov/Dec) | 9.91 |
Poush (Dec/Jan) | 6.82 |
Magh (Jan/Feb) | 5.75 |
Falgun (Feb/Mar) | 4.52 |
Chaitra (Mar/May) | 4.79 |
Average | 26.03 |
Hydrology
Monthly hydrograph at the proposed intake site
Month | Discharge (m3/s) | Percentage of Snow Contribution (%) | ||
CAR Method | Measured Mean Monthly Discharge | Snow Contribution Discharge | ||
January | 4.02 | 4.33 | 0.31 | 7.16 |
February | 3.49 | 5.30 | 1.81 | 34.18 |
March | 3.34 | 4.23 | 0.89 | 20.95 |
April | 3.77 | 3.74 | -0.03 | -0.80 |
May | 5.37 | - | - | - |
June | 16.16 | - | - | - |
July | 42.03 | - | - | - |
August | 51.68 | - | - | - |
September | 36.69 | - | - | - |
October | 16.07 | 19.88 | 3.81 | 19.16 |
November | 7.9 | 12.52 | 4.62 | 36.90 |
December | 5.36 | 7.39 | 2.03 | 27.47 |
Calculated Vs Measured flow
Hydrology
Flow Duration Curve at the proposed intake site
Power and Energy
Power and Energy
Power and Energy
Estimated energy (GWh) for different months
Power and Energy
S.N. | Months | Days | Flow (m3/s) | Net head (m) | Generation capacity (MW) | Energy (GWh) | ||
Monthly | Design | Dry | Wet | |||||
1 | Baishakh | 31 | 6.12 | 3.060 | 550.805 | 14.43 | 10.632 |
|
2 | Jestha | 31 | 17.79 | 7.950 | 539.425 | 36.73 | 13.089 | 13.962 |
3 | Ashadh | 31 | 56.89 | 7.950 | 539.425 | 36.73 |
| 27.051 |
4 | Shrawan | 32 | 81.34 | 7.950 | 539.425 | 36.73 |
| 27.924 |
5 | Bhadra | 31 | 66.82 | 7.950 | 539.425 | 36.73 |
| 27.051 |
6 | Ashwin | 31 | 39.02 | 7.950 | 539.425 | 36.73 |
| 27.051 |
7 | Kartik | 30 | 18.69 | 7.950 | 539.425 | 36.73 |
| 26.179 |
8 | Mangsir | 29 | 9.91 | 4.955 | 547.668 | 23.24 | 8.283 | 7.731 |
9 | Paush | 30 | 6.82 | 3.410 | 550.339 | 16.07 | 11.456 |
|
10 | Magh | 29 | 5.75 | 2.875 | 551.031 | 13.57 | 9.348 |
|
11 | Falgun | 30 | 4.52 | 2.260 | 551.679 | 10.68 | 7.611 |
|
12 | Chaitra | 30 | 4.79 | 2.395 | 551.551 | 11.31 | 8.064 |
|
Maximum power generation (MW) | 36.73 |
|
| |||||
Total annual gross seasonal energy (GWh) | 68.484 | 156.950 | ||||||
Total outage energy (@ 4 %) | 2.739 | 6.278 | ||||||
Total annual marketable seasonable energy after outage (GWh) | 65.744 | 150.672 | ||||||
Total annual marketable energy after outage (GWh) | 216.416 | |||||||
Percentage of seasonal energy with respect to total energy (%) | 30.379 | 69.621 | ||||||
Plant factor | 67.267% | |||||||
Input Parameters | Symbol | Value | Unit |
Design discharge | Qd | 7.95 | m3/s |
Gross head | Hg | 552.72 | m |
Turbine efficiency |
| 90.00 | % |
Generator efficiency |
| 97.00 | % |
Transformer efficiency |
| 99.00 | % |
Overall efficiency | Ƞ | 86.427 | % |
Outage |
| 4 | % |
Power and Energy
Power and Energy
Energy Table as per PPA
Generator Specification
Particular | Specification |
No of Units | Three |
Generator Type | Horizontal,3ØAC |
Rated Capacity | 15686 KVA each |
Rated Efficiency | 95% |
Power Factor | 0.85 lag |
Rated Speed | 600 rpm |
Frequency | 50 Hz |
Generation Voltage | 11 kV |
Insulation Grade | Grade F |
Phase Connection | Star- connected |
Grid Connection and PPA Provision
Grid Connection and PPA Provision
As of PPA
Connection : 220V/132 kV, Single Circuit
Voltage : 132 KV
Length : 15 km
From : Powerhouse
To : NEA Proposed Pangtang Sub-Station
Transmission Line Status
Connection Arrangement
Switchyard of Brahmayani HEP
NEA Proposed Substation;
Pangtang S/S
15 km, 132 KV Single Circuit Line
5 Km, 132 KV Single Circuit Line
Nyamya masi Khola
Lagan Khola
Switchard of Upper Brahmayani
Connection Arrangement
Nyamya masi Khola
Lagan Khola
Switchyard of Brahmayani HEP
16 km, 132 KV Single Circuit Line
NEA Proposed Substation;
Pangtang S/S
Headrace Tunnel, Length = 6036.50 m
Switchyard of Upper Brahmayani HEP
5 km, 132 KV Single Circuit Line
Headrace Tunnel, Length = 4705.75 m
Land Acquisition Status
It will be finalized after Completion of Demarcation and it has already been approved from EIA
Pvt. Land – Near about 41 Ropani
Government - Minimum
Technical Conclusion
Work Progress
Survey at headwork's
Discontinuity measurements at proposed adit
Field Photographs Bramhayani
asasasasasasasasasasasasasasassasas
Gauge being installed
Installed Gauge
Discharge Measurement @powerhouse (Balephi)
Discharge Measurement @headwork's (Langan khola)
Test pit for construction material @powerhouse area
Field Photographs of Access Road (Under Construction)
asasasasasasasasasasasasasasassasas
Project Review site visit
PROJECT PHOTOGRAPHS
Headworks Area
Water Flow at Headwroks area at Lagan Khola
Inlet Portal Area
Inlet Portal
Adit Tunnel Area
Adit Portal
Downstream
Geology
Powerhouse and Penstock
Main Access Tunnel Portal (320m)
Pressure Shaft
Power House 200m Inside
Tailrace Portal
355m
281m
Water flows at headworks
Thank You !!!!!