SAP Plant Maintenance
Preventive Maintenance
Task List Costing (IA16)
see next slide in IP26/IP27
Cost Center 4300
Act Type 1410
Activity Rate
Cost#1
Control Key “PM01”
Internal Labor Costs
Version 0 (Active Version
Period 9 to 9
Year 2024
Cost Center 4300 +
Activity Type 1410
Cost#1
Control Key “PM01”
Internal Labor Costs
Rate is 50EUR per 1 Hour
Secondary Cost Element 615000
Cost#2
Control Key “PM02”
External Operation Costs
Cost#2
Control Key “PM02”
External Operation Costs
100 EUR per 1 AU
Primary Cost Element 417000
Cost#3
Control Key “PM03”
External Services
Cost#3
Control Key “PM03”
External Services
200 EUR per 1 LE
Primary Cost Element 417000
Cost#4
Component
Cost#4
Component
20 EUR per 1 PC
SPRO
PM&CS�- Maint. & Service Processing
Order Type PM01’s
Planned Costing Variant “PM01” will be used for Costing derivation
SPRO
PM&CS�- Maint. & Service Processing
The Valuation Variant in the Costing Variant provides parameters for Source of the Costs
Material Costs
Priority 1 to get Price depending on
Price Control in Material
Activity Rate (Control Key PM01 Internal Operation)
Priority 1 to get Price depending on Plan Price for the Period
External Operation (Control Key PM02 and PM03), get Price from the Operation in Priority 1
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 415000
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
click Costing Sheet button to check “COPM” Costing Sheet
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR CE 655901
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR CE 655901
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR CE 655901
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
20% x 20EUR = 4EUR
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR CE 655901
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
20% x 20EUR = 4EUR CE 6550901
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR CE 655901
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
20% x 20EUR = 4EUR CE 6550901
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR CE 655901
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
20% x 100EUR = 20EUR
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
20% x 200EUR = 40EUR
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
20% x 20EUR = 4EUR CE 6550901
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR CE 655901
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
20% x 100EUR = 20EUR CE 655901
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
20% x 200EUR = 40EUR CE 655901
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
20% x 20EUR = 4EUR CE 6550901
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR CE 655901
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
20% x 100EUR = 20EUR CE 655901
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
20% x 200EUR = 40EUR CE 655901
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
20% x 20EUR = 4EUR CE 6550901
Total Overhead 5EUR + 20EUR +40EUR + 4EUR
69EUR
use IA16 to calculate Task List Costing
IA16 allows Calculations for 1 or more Task List at the same time
Enter the PM Order type to obtain the necessary Costing Variant for the Source of the Costs (see section 2)
Cost#1 CtrlKey “PM01” Internal Operation 50EUR/Hour Cost Element 615000
10% x 50EUR = 5EUR CE 655901
Cost#2 CtrlKey “PM02” Ext. Oper.Cost 100 EUR/AU Cost Element 417000
20% x 100EUR = 20EUR CE 655901
Cost#3 CtrlKey “PM03” Ext. Services 200 EUR/LE Cost Element 417000
20% x 200EUR = 40EUR CE 655901
Cost#4 S.Parts “M01” Val.Class 3000 “V’ 20 EUR/pc Cost ELement 400000
20% x 20EUR = 4EUR CE 6550901
Total Overhead 5EUR + 20EUR +40EUR + 4EUR
69EUR