DESIGN AND CONSTRUCTION OF �LUSAKA CITY DECONGESTION PROJECT ZAMBIA
ENG. BENJAMIN HENRIQUE
LUSAKA CITY COUNCIL
DATE – 7TH June, 2019
Stakeholders
Client
MINISTRY OF LOCAL GOVERNMENT - LUSAKA CITY COUNCIL - ZAMBIA
Contractor
Buyer’s credit by
Project consultant
ALLIONE CONSULTING ENGINEERS LTD.
2
Objective
Objective
Capacity Augmentation
Improvement of existing roads & Widening of Roads
Enhancing some key junctions to avoid bottlenecks by Constructing Flyovers & Junction Improvement.
Creation of bus lanes for better traffic management facilities.
3
Project Benefits:
Decongestion of City
A sign of development for foreign investors and locals
Real Estate growth around the new roads built
Increase in productivity by saving 90 minutes on an average
Much cleaner quality of air within the expanding city
Fuel Saving of average 90 minutes for thousands of vehicles daily
4
Ministry of Local Government/LCC
EXIM Bank, India
AFCONS Infrastructure Limited
Project Value
$ 289. 1 Mn
Project Duration
36 Months
Road Construction
65.64 Km
Road Construction with Bus lane road
25.68 Km
New Flyovers
6 Nos.
At-Grade Junctions
5 Nos.
Project Background & Contract Information
5
New Ring Roads
Road Widening/Rehabilitation
Dedicated Bus Lanes & Road Widening/Rehabilitation
Scope of Work - Rehabilitation / Upgradation of Ring Roads
6
Dedicated Bus Lanes & Road Widening/Rehabilitation
Scope of Work - Rehabilitation / Upgradation of Ring Roads
7
New Ring Roads
Road Widening/Rehabilitation
Dedicated Bus Lanes & Road Widening/Rehabilitation
Scope of Work - Rehabilitation / Upgradation of Bus Lane Roads
8
Dedicated Bus Lanes & Road Widening/Rehabilitation
Scope of Work – Additional Scope
9
New Ring Roads
Road Widening/Rehabilitation
Dedicated Bus Lanes & Road Widening/Rehabilitation
Scope of Work - Improvement of Junction
10
New Ring Roads
Road Widening/Rehabilitation
Dedicated Bus Lanes & Road Widening/Rehabilitation
Scope of Work - Miscellaneous Works
- Built up area 66,500 Sqft and Parking facilities.
11
New Ring Roads
Road Widening/Rehabilitation
Dedicated Bus Lanes & Road Widening/Rehabilitation
Progress on Internal Milestones
Execution
Design & Drawings
12
New Ring Roads
Road Widening/Rehabilitation
Dedicated Bus Lanes & Road Widening/Rehabilitation
Road wise Progress
13
New Ring Roads
Major Structure Progress
14
Photographs
Clearing & Grubbing in Progress for Road No. 1 – Kafue-Mumbwa
Progress Photographs
16
Progress Photographs
Rock Breaking in progress for Road No. 1 – Kafue-Mumbwa
DBM Laying in progress for Road No. 1 – Kafue-Mumbwa
17
Progress Photographs
Earthwork in Progress for Kabulong Road
18
WMM Laying in Progress for Road No. 6 – Nangwenya-Kamloops
Progress Photographs
19
BC Laying in Progress for Road No. 21 – Rail Roadway-Chilanga to Tokyo
Progress Photographs
20
BC Work Completed for Road No. 07 – Lake Mwapona
Progress Photographs
21
Laying of DBM on Road No.6 Nangwenya Kamloops Alick Nkata
Progress Photographs
22
Makeni Flyover Substructure Completed
Dirt Wall (A1 L)
Lilaye
P2 L
P1 L
Dirt Wall (A2 L)
Progress Photographs
23
Progress Photographs
RE Wall work in progress for Makeni Flyover
24
Concreting for Foundation for Arcades Flyover
Progress Photographs
25
Progress Photographs
Pier Completed for Arcades Flyover
26
Footpath and Kerb Completed for Road No. 32 – Mosi-O-Tunya
Progress Photographs
27
Progress Photographs
A utility duct chamber constructed and Construction of Walkways on Road No.21.
28
Drain Completed for Road No. 7 – Lake-Mwapona (LHS)
Progress Photographs
29
Construction of Trapezoidal Drains in progress on Road No.7 Lake Mwapona
Progress Photographs
30
Construction of an access culvert on Road No.33 Munali Mutumbi
Progress Photographs
31
Office, Laboratory & Store
Progress Photographs
32
Aggregate Stock at Camp
Progress Photographs
33
Material Store at Base Camp
Progress Photographs
34
Batching Plant Operational
Progress Photographs
35
WMM Plant Operational
Progress Photographs
36
THANK YOU...!!